  • 7/27/2019 OHSAS presentation.pptx

    1/72

    1

    Awareness Session on OHSASBS OHSAS 18001:2007

    Team MR Office

  • 7/27/2019 OHSAS presentation.pptx

    2/72

    2

    CONTENTS

    1. Introduction of OHSAS

    2. Requirement of OHSAS standard

    Clause 1 : Scope

    Clause 2 : Reference publication

    Clause 3 : Terms and definitions

    Clause 4 : OH&S Management System Requirements

    3. Your Queries

  • 7/27/2019 OHSAS presentation.pptx

    3/72

    33

  • 7/27/2019 OHSAS presentation.pptx

    4/72

    44

    What is OHSAS 18001?

    OHSAS 18001:2007 is an internationally recognized occupational

    health and safety (OH&S) management system developed to match

    the demand for a recognizable standard against which assessing

    and certifying the management system.

    The standard can be applied to all business and operational

    activities and requires also the compliance with all applicable

    regulatory framework. .

  • 7/27/2019 OHSAS presentation.pptx

    5/72

    5

    History :

    Originally developed in early 1990s as BS8800

    Revised in 1999 by BSI to be more compatible with ISO

    14001 Revised in 2007 adding health components

    Framework for an effective OH&S-MS

    17 elements designed in parallel to ISO 14001

    Allows third-party certification/registration

  • 7/27/2019 OHSAS presentation.pptx

    6/72

    66

    What it tells ??This standard does not establish OH&S performance criteria, nor

    does it provide detailed specifications for the design of an OHSAS

    management system but requires the organization to:

    establish its own safety policy and objectives

    identify hazards and risks

    evaluate risks likelihood and impact

    verify the compliance with applicable rules

    plan and deploy suitable countermeasures to prevent injuries,illnesses and fatalities

    monitor and improve performances

  • 7/27/2019 OHSAS presentation.pptx

    7/7277

    Who created this standard?OHSAS 18001 has been developed by a working group lead by BSI

    and several leading national standards bodies, certification bodies,

    and professionals.

    Can the OHSAS 18001 standard be integrated with other

    management systems?

    OHSAS 18001 has been developed to ensure the compatibility with

    the ISO 9001 (Quality) and ISO 14001 (Environmental)

    management systems standards, in order to facilitate theintegration of quality, environmental and occupational health and

    safety management systems by organizations, should they wish to

    do so.

  • 7/27/2019 OHSAS presentation.pptx

    8/7288

    Who does the OHSAS 18001 standard apply to?

    The OHSAS Standard applies to any organization that wishes to:

    Support and promote good OH&S practices

    Minimize safety risks in the work environment

    Ensure the proper deployment of its OH&S policy and theachievement of objectives

    Introduce a common language for health and safety within the

    organization

    Establish, deploy, monitor and improve the OH&S management

    system Achieving the OH&S management system certification by a third

    party certification body

  • 7/27/2019 OHSAS presentation.pptx

    9/7299

    What are the benefits from implementing OHSAS 18001?

    Improving awareness and control of workplace hazards and risks

    Facilitating the reduction in the number and severity of work-

    related accidents and illness, lost time incidents and injuries

    Improving employee health and safety and people satisfaction

    Leading to compliance with legal and regulatory requirements,

    Reducing risks of litigations and penalties

    Establishing a framework for effective risk management

  • 7/27/2019 OHSAS presentation.pptx

    10/721010

    Reducing insurance premiums and other unexpected costs

    related to healthcare

    Improving productivity, people satisfaction and retention

    Increasing ability to attract the best new talent.

    Reducing operating costs - by decreasing down-time through

    incidents and ill health

    Reducing costs associated with legal fees and compensation

    Improving the company image through independent

    management system certification

    BENEFITS OF OH&SMS

  • 7/27/2019 OHSAS presentation.pptx

    11/721111

    How to get OHSAS 18001 certification?

    The management certification process follows the following

    steps:

    I. Application for registration

    II. Initial Certification Audit to verify the compliance withOHSAS 18001 requirement. Such audit consist of Stage 1

    and Stage 2 audits

    III. Certification granting by the Certification Body and

    maintained by the Organization.IV. Surveillance Audit to confirm the maintenance of

    compliance with the requirements

    V. Re-certification audit after three years.

  • 7/27/2019 OHSAS presentation.pptx

    12/721212

    OHSAS Initial Certification Process

    The Initial Certification Process is similar to that of ISO 9001 or ISO 14001 and

    consists of two different audits.

    the purpose of this visit is to determine the organizations

    readiness for a full assessment.

    Stage 2- this Audit shall take place at site and aim to confirm if the

    management system complies with the requirements ofOHSAS 18001 and the internal documentation.

    Stage 1-

  • 7/27/2019 OHSAS presentation.pptx

    13/721313

    Audit the organizations management system documentation

    confirm that the OH&S management system conforms to the

    requirements of the standard

    confirm its implementation status confirm the scope of certification

    check legislative compliance

    evaluate if the internal audits and management review are being

    planned and performed and that the management system

    implementation is ready for Stage 2 Audit produce a report that identifies any non-compliance or potential for non-

    compliance and agree a corrective action plan if required

    produce an audit plan and confirm a date for the Stage 2 assessment

    visit

    Stage 1- The assessor will:

  • 7/27/2019 OHSAS presentation.pptx

    14/721414

    Stage 2 this Audit shall take place at site and aim to confirm if the management

    system complies with the requirements of OHSAS 18001 and theinternal documentation.

    The Auditor shall verify:

    the conformity to all requirements of the applicable management system standard or

    other normative document performance monitoring, measuring, reporting and reviewing against key

    performance objectives and targets (consistent with the expectations in the

    applicable management system standard or other normative document)

    the management system and performance as regards legal compliance

    the effective implementation of the risk management approach

    the operational control of the processes the internal auditing and management review

  • 7/27/2019 OHSAS presentation.pptx

    15/721515

    The auditor shall

    report any non-compliances or potential for non-compliance produce a surveillance plan and confirm a date for the first surveillance

    visit

    If the Auditor identifies any critical or major non-conformance, the organizationcannot be certified until corrective action is taken and verified.

  • 7/27/2019 OHSAS presentation.pptx

    16/721616

    Definitions

  • 7/27/2019 OHSAS presentation.pptx

    17/7217

    Part of an organizations management system used to develop and

    implement its OH&S policy and manage its OH&S risks

    Introduction to OH&S

    Management System.

    Conditions and factors that affect, or could affect, the health and

    safety of employees or other workers (including temporary workers

    and contractor personnel), visitors, or any other person in the

    workplace

    Occupational health and safety (OH&S)

    OH&S Management System

    workplace

    any physical location in which work related activities are performed under the control

    of the organization

  • 7/27/2019 OHSAS presentation.pptx

    18/7218

    Riskcombination of the likelihood of an occurrence of a hazardous event orexposure(s) and the severity of injury orill health (3.8) that can be

    caused by the event or exposure(s)

    Hazardsource, situation, or act with a potential for harm in terms of human

    injury orill health (3.8), or a combination of these

    identifiable, adverse physical or mental condition arising from and/or

    made worse by a work activity and/or work-related situation

    Ill Health

  • 7/27/2019 OHSAS presentation.pptx

    19/72

    19

    Sources of Risks

    Products Materials and their properties

    Work processes andprocedures

    Equipment

    Personnel

    Workplace and location

    Natural environment, climaticconditions

    External / interested parties

  • 7/27/2019 OHSAS presentation.pptx

    20/72

    20

    Risk assessment

    Process of evaluating the risk(s) (3.21) arising from a hazard(s),

    taking into account the adequacy of any existing controls, anddeciding whether or not the risk(s) is acceptable

    Acceptable riskRisk that has been reduced to a level that can be tolerated by the

    organization having regard to its legal obligations and its own

    OH&S policy

  • 7/27/2019 OHSAS presentation.pptx

    21/72

    21

    Incident

    work-related event(s) in which an injury or ill health (regardless of severity) or

    fatality occurred, or could have occurred

    NOTE 1 An accident is an incident which has given rise to injury, ill

    health or fatality.

    NOTE 2 An incident where no injury, ill health, or fatality occurs may

    also be referred to as a near-miss, near-hit, close call or dangerous

    occurrence.

    Interested partyperson or group, inside or outside the workplace, concerned with or affected by the

    OH&S performance of an organization.

  • 7/27/2019 OHSAS presentation.pptx

    22/72

    22

    Requirements in OHSAS Standards

  • 7/27/2019 OHSAS presentation.pptx

    23/72

    23

    PDCA Approach

    This OHSAS Standard is based on the methodology known as

    Plan-Do-Check-Act (PDCA).

  • 7/27/2019 OHSAS presentation.pptx

    24/72

    24

  • 7/27/2019 OHSAS presentation.pptx

    25/72

    25

    Clause 1 Scope

    This OHSAS Standard is applicable to any organization that wishes to:

    establish an OH&S management system

    implement, maintain and continually improve an OH&S management system

    assure itself of its conformance with its O&HS policy

    demonstrate such conformance to others

    seek certification by an external organization make a self-determination and declaration of conformance

    Note :- This OHSAS Standard is intended to address occupational health and safety,and is not intended to address other health and safety areas such as employee

    wellbeing/wellness programmes, product safety, property damage or environmental

    impacts.

  • 7/27/2019 OHSAS presentation.pptx

    26/72

    26

    Clause 2 Reference Publications

    OHSAS 18002,Occupational health and safety managementsystemsGuidelines for the implementation of OHSAS

    18001

    International Labour

    Organization:2001,

    Guidelines on Occupational

    Health and Safety Management Systems

    (OSH-MS)

  • 7/27/2019 OHSAS presentation.pptx

    27/72

    27

    Clause 3 Terms and Definitions

    Discussed in previous session

  • 7/27/2019 OHSAS presentation.pptx

    28/72

    28

    Clause 4 OH&SMS requirements

    4.1 General requirements

    The organization shall define and document the scope

    of its OH&S management system.

    The organization shall establish, document, implement,

    maintain and continually improve an OH&S management

    system

    Scope

  • 7/27/2019 OHSAS presentation.pptx

    29/72

    29

    4.2 OH&S policy

    Appropriate to Risks

    Commit to Prevention of Injury and ill Health and ContinualImprovement

    Commit to Comply with Legislation

    Documented, Implemented, Maintained

    Communicated

    Available to Interested Parties

    Periodic Review

    Provides the framework for setting and reviewing OH&S objectives;

    Environment Occupational Health & Safety Policy

  • 7/27/2019 OHSAS presentation.pptx

    30/72

    30

    Environment, Occupational Health & Safety Policy

    We at PVPL are committed for prevention of pollution, injury and occupational

    ill Health of all employees and other individuals in our premises.

    We all are focused to continually-

    Reduce

    Risk of accidents and health hazards

    Adverse impacts of all our products and processes on

    Environment, Health & Safety

    Consumption & Wastages of natural resources and energy

    Enhance

    Awareness of environmental, health and safety requirements

    Process efficiency and resources utilization

    Adoption to environment and healthy friendly technologies & processes

    Ensure

    Compliance to all applicable legal and other requirements

    to which we subscribe

    Objectives and targets for continual improvement Environment, Health,

    & Safety performance are set, monitored and reviewed

    Appropriately training is given to all individuals enter in our premises

  • 7/27/2019 OHSAS presentation.pptx

    31/72

    31

    Hazard Identification, Risk Assessment and Determining

    Controls

    Legal & Other Requirements

    Objectives and Programme(s)

    4.3 Planning

    Planning Phase

  • 7/27/2019 OHSAS presentation.pptx

    32/72

    32

    developing a methodology for hazard identification and riskassessment,

    identifying hazards,

    estimating the associated risks, taking into account the adequacy

    of any existing controls

    determining whether these risks are acceptable, and

    determining the appropriate risk controls, where these are

    found to be necessary

    Planning Phase

  • 7/27/2019 OHSAS presentation.pptx

    33/72

    33

    4.3.1 Hazard identification, risk assessment and determining controls

    Planning Phase

  • 7/27/2019 OHSAS presentation.pptx

    34/72

    34

    Determining the need for controls

    If new or improved controls are required, their selection should be determined

    by the principle of the hierarchy of controls,

    a) elimination;

    b) substitution;

    c) engineering controls;

    d) signage/warnings and/or administrative controls;

    e) personal protective equipment.

    Planning Phase

  • 7/27/2019 OHSAS presentation.pptx

    35/72

    35

    Procedure of HIRA shall take into account

    a) routine and non-routine activities;

    b) activities of all persons having access to the workplace (including

    contractors and visitors);c) human behavior, capabilities and other human factors;

    d) identified hazards originating outside the workplace capable of

    adversely affecting the health and safety of persons under the

    control of the organization within the workplace;

    Planning Phase

  • 7/27/2019 OHSAS presentation.pptx

    36/72

    36

    e) hazards created in the vicinity of the workplace by work-

    related activities under the control of the organization.

    f) infrastructure, equipment and materials at the workplace,

    whether provided by the organization or others;

    g) changes or proposed changes in the organization, its

    activities, or materials;

    h) modifications to the OH&S management system, includingtemporary changes, and their impacts on operations,

    processes, and activities;

    Planning Phase

  • 7/27/2019 OHSAS presentation.pptx

    37/72

    37

    i) any applicable legal obligations relating to risk assessment andimplementation of necessary controls

    j) the design of work areas, processes, installations,

    machinery/equipment, operating procedures and work organization,

    including their adaptation to human capabilities.

  • 7/27/2019 OHSAS presentation.pptx

    38/72

    38

  • 7/27/2019 OHSAS presentation.pptx

    39/72

    39

    The organizations methodology for hazard identification and risk

    assessment shall:

    a) be defined with respect to its scope, nature and timing to ensure it is

    proactive rather than reactive; and

    b) provide for the identification, prioritization and documentation of risks,

    and the application of controls, as appropriate.

  • 7/27/2019 OHSAS presentation.pptx

    40/72

    40

    4.3.2 Legal and other requirementsThe procedure(s) for identifying and accessing legal requirements

    must be implemented

    All legal and other requirements must be taken into account when

    establishing, implementing and maintaining the OH&S

    Management System

    The organization shall keep this information up-to-date.

    Relevant information on legal and other requirements should be

    communicated to all people working under the control of the

    organization not just employees and interested parties

  • 7/27/2019 OHSAS presentation.pptx

    41/72

    41

    Examples of legal requirements legislation, including statutes, regulations and codes of practice,

    decrees and directives,

    orders issued by regulators,

    permits, licenses or other forms of authorization,

    judgments of courts or administrative tribunals,

    treaties, conventions, protocols.

    Examples of other requirements contractual conditions,

    agreements with employees,

    agreements with interested parties, agreements with health authorities,

    non-regulatory guidelines,

    voluntary principles, best practices or codes of practice, charters,

  • 7/27/2019 OHSAS presentation.pptx

    42/72

    42

    4.3.3 Objectives and programme(s)

    a) Objective to be defined at relevant functions and levels within the

    organization.

    b) Objectives should be S.M.A.R.T.

    Planning Phase

    Examples of types of objectives can include:

    1. objectives to increase or reduce something that specify a numerical figure

    (e.g. to reduce handling incidents by 20%),

    2. objectives to introduce controls or eliminate hazards (e.g. for noisereduction in a workshop),

    3. objectives to introduce less hazardous materials in specific products,

  • 7/27/2019 OHSAS presentation.pptx

    43/72

    43

    a) designation of responsibility and authority for achieving objectives at relevant

    functions and levels of the organization; and

    b) the means and time-frame by which the objectives are to be achieved.

    The organization shall establish, implement and maintain a programme(s) for

    achieving its objectives.

    Programme(s)

    The programme (its like an action plan) should address the following

    requirements as a minimum to be consider

    Planning Phase

  • 7/27/2019 OHSAS presentation.pptx

    44/72

    44

    OH&S Planning

  • 7/27/2019 OHSAS presentation.pptx

    45/72

    45

    DO - Phase

    DO Ph

  • 7/27/2019 OHSAS presentation.pptx

    46/72

    46

    DO Phase

    4.4 Implementation and operation

    4.4.1 Establishing resource, roles, responsibility, accountability and

    authority

    4.4.2 Competence, training and awareness4.4.3 Communication, participation and consultation

    4.4.3.1 Establishing OH&S communication procedures

    4.4.3.2 Establishing Participation and consultation procedures

    4.3.4 Documentation for OH&S management system

    4.4.5 Control of documents4.4.6 Operational control

    4.4.7 Emergency preparedness and response

  • 7/27/2019 OHSAS presentation.pptx

    47/72

    47

    4.4.1 Resources, roles, responsibility, accountability and

    authority

    - Top management commitment

    - Ensuring the availability of resources

    - Defining roles, allocating responsibility and accountability

    - Appointment of Management Representative.

    - MR should ensure OH&SMS is established, implemented and maintained.

    - Reporting the performance of OH&SMS to top management, for review.

  • 7/27/2019 OHSAS presentation.pptx

    48/72

    48

    4.4.2 Competence, training and awareness

    Personnel shall be competent to perform tasks that may impact on

    OH&S in the workplace. Competence shall be defined in terms of

    appropriate education, training and/or experience.

    Requirement for training needs to be identified and theeffectiveness of the training or action taken to be evaluated.

    Associated records to be retained.

    Training take into account differing levels of:

    Responsibility

    Ability

    Literacy

    Risk

  • 7/27/2019 OHSAS presentation.pptx

    49/72

    4949

    4.4.3 Communication, participation and consultation

  • 7/27/2019 OHSAS presentation.pptx

    50/72

    5050

    4.4.3.1 Communication

    Communicate internally at various levels and functions of org.

    Communicate with contractors and other visitors.

    Review, document and respond to relevant communication

    from external interested party.

  • 7/27/2019 OHSAS presentation.pptx

    51/72

    5151

    4.4.3.2 Participation and consultation

    Participation of workers in hazard identification/risk assessments

    Involve them in the development & review of OH&S policies and

    objectives

    Appropriate involvement in incident investigation.

    Consulted where there are changes that affect their OH&S.

  • 7/27/2019 OHSAS presentation.pptx

    52/72

    52

    4.4.4 DocumentationDocumentation shall include :

    a) The OH&S policy and objectives;

    b) Scope of OH&SMS

    c) description of the main elements of the OH&S management

    system and their interaction, and reference to related documents;

    d) documents, including records, required by this OHSAS Standard;

    and

  • 7/27/2019 OHSAS presentation.pptx

    53/72

    53

    4.4.5 Control of Documents Approval of documents prior to issue

    Review and update as necessary and reapprove

    Ensure the changes and current revision status are identified.

    Ensure the relevant documents are available at point of use

    Ensure document remain legible and readily identifiable.

    Ensure external origin documents are identified and their

    distribution is controlled.

    Control of obsolete documents

  • 7/27/2019 OHSAS presentation.pptx

    54/72

    54

    Document and Data Control

    In the right placeRight information is available:

    At the right timeIn the right revision

  • 7/27/2019 OHSAS presentation.pptx

    55/72

    55

    4.4.6 Operational Control

    Identify operations and activities where risk requires further control

    Plan these to ensure that

    documented procedures are developed

    operating criteria specify key steps and requirements

    procedures addressing risks related to contractor goods and services establish design procedures to reduce/eliminate source of risks

    The organization must determine those operations and activities that are

    associated with the identified hazards where the implementation of controls are

    necessary to manage OH&S risk(s)

    Includes the need for controls related to contractors and other visitors to the

    workplace Includes the need for the management of change

  • 7/27/2019 OHSAS presentation.pptx

    56/72

    56

    Consideration to establish and Implement OCP

    OH&S policy and objectives,

    results of hazard identification, risk assessment, evaluation of existing controls

    and determination of new controls,

    management of change processes,

    internal specifications (e.g. for materials, equipment, facilities layout),

    information on existing operating procedures, legal and other requirements to which the organization subscribes (see 4.3.2),

    product supply chain controls related to purchased goods, equipment and

    services,

    feedback from participation and consultation (see 4.4.3),

    the nature of, and extent to which, tasks are to be performed by

    contractors and other external personnel, access to the workplace by visitors, delivery personnel, service contractors, etc.

  • 7/27/2019 OHSAS presentation.pptx

    57/72

    57

    Operational

    Control

  • 7/27/2019 OHSAS presentation.pptx

    58/72

    58

    4.4.7 Emergency Preparedness & Response

    Emergency response procedures to address

    identifying potential for incidents and emergencies

    preventing and mitigating resultant illnesses and injuries

    responding to incidents and emergencies when they occur.

    In planning its emergency response the organization has to take into account

    the needs of relevant interested parties e.g. emergency services and neighbor.

  • 7/27/2019 OHSAS presentation.pptx

    59/72

    59

    Emergency Preparedness & Response

    Check Phase

  • 7/27/2019 OHSAS presentation.pptx

    60/72

    60

    4.5 Checking

    4.5.1 Performance Measurement and monitoring

    4.5.2 Evaluation of compliance

    4.5.3 Incident investigation, non conformity, corrective action and

    preventive action

    4.5.3.1 Incident investigation

    4.5.3.2 Non conformity, corrective action and preventive action

    4.5.4 Control of records

    4.5.5 Internal Audit

    Check Phase

  • 7/27/2019 OHSAS presentation.pptx

    61/72

    61

    4.5.1Performance Measurement &Monitoring

    1. Monitoring the achievement of objectives

    2. Quantitative and qualitative measures

    3. Proactive and reactive methods

    4. Records to facilitate corrective and preventive actions

    5. Calibration of monitoring equipment

    6. The procedure(s) for monitoring and measuring OH&S performance

    should now cover monitoring the effectiveness of controls for health as

    well as safety.

  • 7/27/2019 OHSAS presentation.pptx

    62/72

    62

    Quantitative & Qualitative

    Direct Quantitative Measures

    number of lost work days following an injury

    decibel levels of noise in a work area

    Indirect Qualitative Measures

    review of inspection logs

    observation of a task interviews

  • 7/27/2019 OHSAS presentation.pptx

    63/72

    63

    Proactive & Reactive Measures

    Proactive monitoring of compliance

    routine basis, independent of any event

    monitoring may be required by regulations daily equipment checks

    periodic review of hot-work permits

    Reactive monitoring of accidents or incidents

    in response to an event or trigger accident investigation

    monitoring in response to a complaint

  • 7/27/2019 OHSAS presentation.pptx

    64/72

    64

    4.5.2 Evaluation of compliance

    A new clause split into two sub-clauses

    4.5.2.1 This is a new clause and covers the requirement for organizations to

    establish, implement and maintain a procedure for periodically evaluatingcompliance with applicable legal requirements and to keep records of the

    results of these periodic evaluations.

    4.5.2.2 The organization must also evaluate compliance with other

    requirements to which it subscribes and keep records.

  • 7/27/2019 OHSAS presentation.pptx

    65/72

    65

    4.5.3 Incident investigation, nonconformity,

    corrective action and preventive action

    Formerly Accidents, incidents, nonconformance's, corrective and preventive action.

    Split into 2 sub-clauses 4.5.3.1 (Incident Investigation) & 4.5.3.2 (Nonconformity,

    corrective action & preventive action)

    4.5.3.1 Investigations must be performed in a timely manner, documented and maintained 4.5.3.2 Procedure now includes reviewing the effectiveness of corrective action and risk

    assessment for new/changed controls

    Handle, investigate, mitigate

    Accidents

    Incidents

    non-conformances

    Corrective and preventive actions

    Review action plans through risk assessment process

  • 7/27/2019 OHSAS presentation.pptx

    66/72

    66

    4.5.3 Incident investigation, nonconformity, corrective action and preventive action

    Handle = immediate action

    Notification

    emergency response

    recordkeeping to facilitate investigation Investigation process

    team and procedures

    root cause analysis

    People are involved human elements

  • 7/27/2019 OHSAS presentation.pptx

    67/72

    67

    4.5.3 Incident investigation, nonconformity,

    corrective action and preventive action

    Correct immediate problem

    Mitigate consequences

    Eliminate or control root cause

    Prevent recurrence

    Review action plans through risk assessment

    process

    Communicate results and monitor

  • 7/27/2019 OHSAS presentation.pptx

    68/72

    68

    4.5.4 Control of records

    Identification, maintenance, and disposition

    Records must be:

    Legible

    Identifiable

    traceable to the activities involved

    easily retrievable protected from damage, deterioration, or loss

    held for specified and documented retention times

    Formerly Records and records management

    Section is more concise than the 1999 Specification but includes all the main

    principles.

    Records required to demonstrate conformity to requirements of the OH&S management

    system and OHSAS 18001 Standard. Procedure(s) required for identification, storage,protection,retrieval,retention anddisposal of records

  • 7/27/2019 OHSAS presentation.pptx

    69/72

  • 7/27/2019 OHSAS presentation.pptx

    70/72

    70

    4.5.6 Management Review

    Clause now includes a 9 point checklist of the input and a 4 point list of

    outputs from MR

    Inputs include

    results of internal audits and evaluations of compliance with legalrequirements, participation and consultation, communication/complaints

    OH&S performance, objectives, incident investigations,

    corrective/preventive action

    New requirement that relevant outputs from management review must be

    made available for communication and consultation

  • 7/27/2019 OHSAS presentation.pptx

    71/72

    71

    Management Review

  • 7/27/2019 OHSAS presentation.pptx