7/31/2019 FICHAS ADECUACIN CAOS_0.3
1/17
CAOS PRECIO TOTAL 100% PRECIO TOTAL 30%
Cao Grande 11,590,205,608$ 3,477,061,682$
Cao Barro 45,895,124,642$ 13,768,537,393$
Cao Cedro 13,795,774,853$ 4,138,732,456$
Cao Muoz 134,114,192,606$ 40,234,257,782$
Cao Coroncoro 11,932,984,104$ 3,579,895,231$
Cao San Matias 147,888,477,505$ 44,366,543,251$
Cao Viloria 140,121,383,609$ 42,036,415,083$
Cao Mojaescopeta 5,268,646,038$ 1,580,593,811$
Cao Largo 50,524,062,706$ 15,157,218,812$
Cao Rabn Arriba 110,694,565,935$ 33,208,369,781$
Cao Rabn Abajo 81,685,339,798$ 24,505,601,939$
Cao Las Brisas 18,196,459,039$ 5,458,937,712$
Cao Gramalote 231,728,928,987$ 69,518,678,696$
Cao Mojana 55,595,299,780$ 16,678,589,934$
Cao Los Moncholos 7,554,327,170$ 2,266,298,151$
Cao Mojana Viejo 39,447,713,079$ 11,834,313,924$
TOTAL 1,106,033,485,458$ 331,810,045,637$
-
7/31/2019 FICHAS ADECUACIN CAOS_0.3
2/17
-
7/31/2019 FICHAS ADECUACIN CAOS_0.3
3/17
Excavacin lateral cauce m3 355497.6 5,600.00$ 1,990,786,543.20$
Dragado fondo cauce m3 289372.88 10,000.00$ 2,893,728,810.00$
Descapote (20 cm espesor) m2 1073370.6 1,200.00$ 1,288,044,691.20$
Excavacin de material comn de prestmo
para conformacin de zanjas m3
536063.76
3,895.00$ 2,087,968,345.20$Colocacin geotextil no tejido en zanja de
prestmo m2527885.54
4,184.00$ 2,208,673,116.10$
Riego de liga con emulsin asfaltica m2 527885.54 1,031.00$ 544,249,995.86$
Descargas en PVC 4'' @ 200 m m 1553.808 46,000.00$ 71,475,168.00$
Lleno zanja con material sobrante de
excavacin m3536063.76
5,000.00$ 2,680,318,800.00$
Conformacin de orilla (Terraplenes) m3 621.528 5,296.50$ 3,291,923.05$
13,768,537,392.61$
Valor Total
Adecuacin caos
TOTAL
CantidadComponente o Categora del
GastoRelacin de Actividades Unidades Valor Unitario
-
7/31/2019 FICHAS ADECUACIN CAOS_0.3
4/17
Excavacin lateral cauce m3 139166 5,600.00$ 779,329,488.00$
Dragado fondo cauce m3 72212.07 10,000.00$ 722,120,700.00$
Descapote (20 cm espesor) m2 376445.7 1,200.00$ 451,734,804.00$
Excavacin de material comn de prestmo
para conformacin de zanjas m3
139896
3,895.00$ 544,894,920.00$Colocacin geotextil no tejido en zanja de
prestmo m2128555.3
4,184.00$ 537,875,417.04$
Riego de liga con emulsin asfaltica m2 128555.3 1,031.00$ 132,540,524.61$
Descargas en PVC 4'' @ 200 m m 321.6 46,000.00$ 14,793,600.00$
Lleno zanja con material sobrante de
excavacin m3139896
5,000.00$ 699,480,000.00$
Conformacin de orilla (Terraplenes) m3 48326.82 5,296.50$ 255,963,002.13$
4,138,732,455.78$
Valor Total
Adecuacin caos
TOTAL
CantidadComponente o Categora del
GastoRelacin de Actividades Unidades Valor Unitario
-
7/31/2019 FICHAS ADECUACIN CAOS_0.3
5/17
Excavacin lateral cauce m3 2172671.3 5,600.00$ 12,166,959,168.00$
Dragado fondo cauce m3 367127.28 10,000.00$ 3,671,272,800.00$
Descapote (20 cm espesor) m2 4857376.3 1,200.00$ 5,828,851,584.00$
Excavacin de material comn de prestmo
para conformacin de zanjas m3
671292
3,895.00$ 2,614,682,340.00$Colocacin geotextil no tejido en zanja de
prestmo m2616873.62
4,184.00$ 2,580,999,226.08$
Riego de liga con emulsin asfaltica m2 616873.62 1,031.00$ 635,996,702.22$
Descargas en PVC 4'' @ 200 m m 1543.2 46,000.00$ 70,987,200.00$
Lleno zanja con material sobrante de
excavacin m3671292
5,000.00$ 3,356,460,000.00$
Conformacin de orilla (Terraplenes) m3 1757396.2 5,296.50$ 9,308,048,761.44$
40,234,257,781.74$
Valor Total
Adecuacin caos
TOTAL
CantidadComponente o Categora del
GastoRelacin de Actividades Unidades Valor Unitario
-
7/31/2019 FICHAS ADECUACIN CAOS_0.3
6/17
Excavacin lateral cauce m3 122868.8 5,600.00$ 688,065,000.00$
Dragado fondo cauce m3 59397.48 10,000.00$ 593,974,800.00$
Descapote (20 cm espesor) m2 323509.7 1,200.00$ 388,211,688.00$
Excavacin de material comn de prestmo
para conformacin de zanjas m3
123922.8
3,895.00$ 482,679,306.00$Colocacin geotextil no tejido en zanja de
prestmo m2113877
4,184.00$ 476,461,242.48$
Riego de liga con emulsin asfaltica m2 113877 1,031.00$ 117,407,156.07$
Descargas en PVC 4'' @ 200 m m 284.88 46,000.00$ 13,104,480.00$
Lleno zanja con material sobrante de
excavacin m3123922.8
5,000.00$ 619,614,000.00$
Conformacin de orilla (Terraplenes) m3 37832.07 5,296.50$ 200,377,558.76$
3,579,895,231.31$
Valor Total
Adecuacin caos
TOTAL
CantidadComponente o Categora del
GastoRelacin de Actividades Unidades Valor Unitario
-
7/31/2019 FICHAS ADECUACIN CAOS_0.3
7/17
Excavacin lateral cauce m3 483339.3 5,600.00$ 2,706,700,080.00$
Dragado fondo cauce m3 1801081 10,000.00$ 18,010,810,200.00$
Descapote (20 cm espesor) m2 4290771 1,200.00$ 5,148,925,056.00$
Excavacin de material comn de prestmo
para conformacin de zanjas m3
840002.4
3,895.00$ 3,271,809,348.00$Colocacin geotextil no tejido en zanja de
prestmo m2771907.5
4,184.00$ 3,229,660,854.48$
Riego de liga con emulsin asfaltica m2 771907.5 1,031.00$ 795,836,601.57$
Descargas en PVC 4'' @ 200 m m 1931.04 46,000.00$ 88,827,840.00$
Lleno zanja con material sobrante de
excavacin m3840002.4
5,000.00$ 4,200,012,000.00$
Conformacin de orilla (Terraplenes) m3 1305383 5,296.50$ 6,913,961,271.36$
44,366,543,251.41$
Valor Total
Adecuacin caos
TOTAL
CantidadComponente o Categora del
GastoRelacin de Actividades Unidades Valor Unitario
-
7/31/2019 FICHAS ADECUACIN CAOS_0.3
8/17
Excavacin lateral cauce m3 1259006 5,600.00$ 7,050,434,496.00$
Dragado fondo cauce m3 1343261 10,000.00$ 13,432,611,000.00$
Descapote (20 cm espesor) m2 2977294 1,200.00$ 3,572,752,212.00$
Excavacin de material comn de prestmo
para conformacin de zanjas m3550892.7
3,895.00$ 2,145,727,066.50$
Colocacin geotextil no tejido en zanja de
prestmo m2506234.5
4,184.00$ 2,118,085,106.16$
Riego de liga con emulsin asfaltica m2 506234.5 1,031.00$ 521,927,759.19$
Descargas en PVC 4'' @ 200 m m 1266.42 46,000.00$ 58,255,320.00$
Lleno zanja con material sobrante de
excavacin m3550892.7
5,000.00$ 2,754,463,500.00$
Conformacin de orilla (Terraplenes) m3 1960192 5,296.50$ 10,382,158,622.88$
42,036,415,082.73$
Valor Unitario Valor Total
Adecuacin caos
TOTAL
CantidadComponente o Categora del
GastoRelacin de Actividades Unidades
-
7/31/2019 FICHAS ADECUACIN CAOS_0.3
9/17
Excavacin lateral cauce m3 62165.64 5,600.00$ 348,127,584.00$
Dragado fondo cauce m3 37895.46 10,000.00$ 378,954,600.00$
Descapote (20 cm espesor) m2 120208.3 1,200.00$ 144,249,912.00$
Excavacin de material comn de prestmo
para conformacin de zanjas m3
23529.15
3,895.00$ 91,646,039.25$Colocacin geotextil no tejido en zanja de
prestmo m221621.75
4,184.00$ 90,465,402.00$
Riego de liga con emulsin asfaltica m2 21621.75 1,031.00$ 22,292,024.25$
Descargas en PVC 4'' @ 200 m m 54.09 46,000.00$ 2,488,140.00$
Lleno zanja con material sobrante de
excavacin m323529.15
5,000.00$ 117,645,750.00$
Conformacin de orilla (Terraplenes) m3 72637.47 5,296.50$ 384,724,359.86$
1,580,593,811.36$
Valor Total
Adecuacin caos
TOTAL
CantidadComponente o Categora del
GastoRelacin de Actividades Unidades Valor Unitario
-
7/31/2019 FICHAS ADECUACIN CAOS_0.3
10/17
Excavacin lateral cauce m3 596141.9 5,600.00$ 3,338,394,696.00$
Dragado fondo cauce m3 363401.2 10,000.00$ 3,634,012,200.00$
Descapote (20 cm espesor) m2 1152746 1,200.00$ 1,383,295,104.00$
Excavacin de material comn de prestmo
para conformacin de zanjas m3
225634.5
3,895.00$ 878,846,377.50$Colocacin geotextil no tejido en zanja de
prestmo m2207343.4
4,184.00$ 867,524,827.44$
Riego de liga con emulsin asfaltica m2 207343.4 1,031.00$ 213,771,055.71$
Descargas en PVC 4'' @ 200 m m 518.7 46,000.00$ 23,860,200.00$
Lleno zanja con material sobrante de
excavacin m3225634.5
5,000.00$ 1,128,172,500.00$
Conformacin de orilla (Terraplenes) m3 696562.2 5,296.50$ 3,689,341,851.20$
15,157,218,811.85$
Valor Total
Adecuacin caos
TOTAL
CantidadComponente o Categora del
GastoRelacin de Actividades Unidades Valor Unitario
-
7/31/2019 FICHAS ADECUACIN CAOS_0.3
11/17
Excavacin lateral cauce m3 1651498 5,600.00$ 9,248,387,400.00$
Dragado fondo cauce m3 611662.2 10,000.00$ 6,116,622,300.00$
Descapote (20 cm espesor) m2 2193111 1,200.00$ 2,631,733,416.00$
Excavacin de material comn de prestmo
para conformacin de zanjas m3
423211.5
3,895.00$ 1,648,408,792.50$Colocacin geotextil no tejido en zanja de
prestmo m2388903.8
4,184.00$ 1,627,173,499.20$
Riego de liga con emulsin asfaltica m2 388903.8 1,031.00$ 400,959,817.80$
Descargas en PVC 4'' @ 200 m m 972.9 46,000.00$ 44,753,400.00$
Lleno zanja con material sobrante de
excavacin m3423211.5
5,000.00$ 2,116,057,500.00$
Conformacin de orilla (Terraplenes) m3 1769900 5,296.50$ 9,374,273,655.12$
33,208,369,780.62$
Valor Total
Adecuacin caos
TOTAL
CantidadComponente o Categora del
GastoRelacin de Actividades Unidades Valor Unitario
-
7/31/2019 FICHAS ADECUACIN CAOS_0.3
12/17
Excavacin lateral cauce m3 657839.6 5,600.00$ 3,683,901,648.00$
Dragado fondo cauce m3 695417.9 10,000.00$ 6,954,178,500.00$
Descapote (20 cm espesor) m2 2548291 1,200.00$ 3,057,948,684.00$
Excavacin de material comn de prestmo
para conformacin de zanjas m3
477969.3
3,895.00$ 1,861,690,423.50$Colocacin geotextil no tejido en zanja de
prestmo m2439222.7
4,184.00$ 1,837,707,567.60$
Riego de liga con emulsin asfaltica m2 439222.7 1,031.00$ 452,838,552.15$
Descargas en PVC 4'' @ 200 m m 1098.78 46,000.00$ 50,543,880.00$
Lleno zanja con material sobrante de
excavacin m3477969.3
5,000.00$ 2,389,846,500.00$
Conformacin de orilla (Terraplenes) m3 796176 5,296.50$ 4,216,946,184.00$
24,505,601,939.25$
Valor Total
Adecuacin caos
TOTAL
CantidadComponente o Categora del
GastoRelacin de Actividades Unidades Valor Unitario
-
7/31/2019 FICHAS ADECUACIN CAOS_0.3
13/17
Excavacin lateral cauce m3 186247.4 5,600.00$ 1,042,985,160.00$
Dragado fondo cauce m3 114480.7 10,000.00$ 1,144,807,200.00$
Descapote (20 cm espesor) m2 557612.5 1,200.00$ 669,134,952.00$
Excavacin de material comn de prestmo
para conformacin de zanjas m3
132444.5
3,895.00$ 515,871,132.75$Colocacin geotextil no tejido en zanja de
prestmo m2121707.8
4,184.00$ 509,225,477.04$
Riego de liga con emulsin asfaltica m2 121707.8 1,031.00$ 125,480,752.11$
Descargas en PVC 4'' @ 200 m m 304.47 46,000.00$ 14,005,620.00$
Lleno zanja con material sobrante de
excavacin m3132444.5
5,000.00$ 662,222,250.00$
Conformacin de orilla (Terraplenes) m3 146361.8 5,296.50$ 775,205,167.77$
5,458,937,711.67$
Valor Total
Adecuacin caos
TOTAL
CantidadComponente o Categora del
GastoRelacin de Actividades Unidades Valor Unitario
-
7/31/2019 FICHAS ADECUACIN CAOS_0.3
14/17
Excavacin lateral cauce m3 2905697 5,600.00$ 16,271,901,744.00$
Dragado fondo cauce m3 1787699 10,000.00$ 17,876,990,400.00$
Descapote (20 cm espesor) m2 4584575 1,200.00$ 5,501,489,940.00$
Excavacin de material comn de prestmo
para conformacin de zanjas m3
657459
3,895.00$ 2,560,802,805.00$Colocacin geotextil no tejido en zanja de
prestmo m2604162
4,184.00$ 2,527,813,766.16$
Riego de liga con emulsin asfaltica m2 604162 1,031.00$ 622,891,011.69$
Descargas en PVC 4'' @ 200 m m 1511.4 46,000.00$ 69,524,400.00$
Lleno zanja con material sobrante de
excavacin m3657459
5,000.00$ 3,287,295,000.00$
Conformacin de orilla (Terraplenes) m3 3927116 5,296.50$ 20,799,969,629.18$
69,518,678,696.03$
Valor Total
Adecuacin caos
TOTAL
CantidadComponente o Categora del
GastoRelacin de Actividades Unidades Valor Unitario
-
7/31/2019 FICHAS ADECUACIN CAOS_0.3
15/17
Excavacin lateral cauce m3 288283.1 5,600.00$ 1,614,385,248.00$
Dragado fondo cauce m3 516901.5 10,000.00$ 5,169,015,000.00$
Descapote (20 cm espesor) m2 1440874 1,200.00$ 1,729,048,788.00$
Excavacin de material comn de prestmo
para conformacin de zanjas m3
512016.8
3,895.00$ 1,994,305,241.25$Colocacin geotextil no tejido en zanja de
prestmo m2470510
4,184.00$ 1,968,614,007.36$
Riego de liga con emulsin asfaltica m2 470510 1,031.00$ 485,095,851.24$
Descargas en PVC 4'' @ 200 m m 1177.05 46,000.00$ 54,144,300.00$
Lleno zanja con material sobrante de
excavacin m3512016.8
5,000.00$ 2,560,083,750.00$
Conformacin de orilla (Terraplenes) m3 208420.2 5,296.50$ 1,103,897,748.20$
16,678,589,934.05$
Valor Total
Adecuacin caos
TOTAL
CantidadComponente o Categora del
GastoRelacin de Actividades Unidades Valor Unitario
-
7/31/2019 FICHAS ADECUACIN CAOS_0.3
16/17
Excavacin lateral cauce m3 63137.61 5,600.00$ 353,570,616.00$
Dragado fondo cauce m3 59843.16 10,000.00$ 598,431,600.00$
Descapote (20 cm espesor) m2 205029.5 1,200.00$ 246,035,448.00$
Excavacin de material comn de prestmo
para conformacin de zanjas m3
61824.39
3,895.00$ 240,805,999.05$Colocacin geotextil no tejido en zanja de
prestmo m256812.56
4,184.00$ 237,703,751.04$
Riego de liga con emulsin asfaltica m2 56812.56 1,031.00$ 58,573,749.36$
Descargas en PVC 4'' @ 200 m m 142.14 46,000.00$ 6,538,440.00$
Lleno zanja con material sobrante de
excavacin m361824.39
5,000.00$ 309,121,950.00$
Conformacin de orilla (Terraplenes) m3 40690.38 5,296.50$ 215,516,597.67$
2,266,298,151.12$
Valor Total
Adecuacin caos
TOTAL
CantidadComponente o Categora del
GastoRelacin de Actividades Unidades Valor Unitario
-
7/31/2019 FICHAS ADECUACIN CAOS_0.3
17/17
Excavacin lateral cauce m3 343400.1 5,600.00$ 1,923,040,560.00$
Dragado fondo cauce m3 305691.5 10,000.00$ 3,056,914,500.00$
Descapote (20 cm espesor) m2 1091324 1,200.00$ 1,309,589,100.00$
Excavacin de material comn de prestmo
para conformacin de zanjas m3
312443.1
3,895.00$ 1,216,965,874.50$Colocacin geotextil no tejido en zanja de
prestmo m2287114.9
4,184.00$ 1,201,288,532.40$
Riego de liga con emulsin asfaltica m2 287114.9 1,031.00$ 296,015,410.35$
Descargas en PVC 4'' @ 200 m m 718.26 46,000.00$ 33,039,960.00$
Lleno zanja con material sobrante de
excavacin m3312443.1
5,000.00$ 1,562,215,500.00$
Conformacin de orilla (Terraplenes) m3 233219 5,296.50$ 1,235,244,486.47$
11,834,313,923.72$
Valor Total
Adecuacin caos
TOTAL
CantidadComponente o Categora del
GastoRelacin de Actividades Unidades Valor Unitario