    CAOS PRECIO TOTAL 100% PRECIO TOTAL 30%

    Cao Grande 11,590,205,608$ 3,477,061,682$

    Cao Barro 45,895,124,642$ 13,768,537,393$

    Cao Cedro 13,795,774,853$ 4,138,732,456$

    Cao Muoz 134,114,192,606$ 40,234,257,782$

    Cao Coroncoro 11,932,984,104$ 3,579,895,231$

    Cao San Matias 147,888,477,505$ 44,366,543,251$

    Cao Viloria 140,121,383,609$ 42,036,415,083$

    Cao Mojaescopeta 5,268,646,038$ 1,580,593,811$

    Cao Largo 50,524,062,706$ 15,157,218,812$

    Cao Rabn Arriba 110,694,565,935$ 33,208,369,781$

    Cao Rabn Abajo 81,685,339,798$ 24,505,601,939$

    Cao Las Brisas 18,196,459,039$ 5,458,937,712$

    Cao Gramalote 231,728,928,987$ 69,518,678,696$

    Cao Mojana 55,595,299,780$ 16,678,589,934$

    Cao Los Moncholos 7,554,327,170$ 2,266,298,151$

    Cao Mojana Viejo 39,447,713,079$ 11,834,313,924$

    TOTAL 1,106,033,485,458$ 331,810,045,637$

  • 7/31/2019 FICHAS ADECUACIN CAOS_0.3

    2/17

  • 7/31/2019 FICHAS ADECUACIN CAOS_0.3

    3/17

    Excavacin lateral cauce m3 355497.6 5,600.00$ 1,990,786,543.20$

    Dragado fondo cauce m3 289372.88 10,000.00$ 2,893,728,810.00$

    Descapote (20 cm espesor) m2 1073370.6 1,200.00$ 1,288,044,691.20$

    Excavacin de material comn de prestmo

    para conformacin de zanjas m3

    536063.76

    3,895.00$ 2,087,968,345.20$Colocacin geotextil no tejido en zanja de

    prestmo m2527885.54

    4,184.00$ 2,208,673,116.10$

    Riego de liga con emulsin asfaltica m2 527885.54 1,031.00$ 544,249,995.86$

    Descargas en PVC 4'' @ 200 m m 1553.808 46,000.00$ 71,475,168.00$

    Lleno zanja con material sobrante de

    excavacin m3536063.76

    5,000.00$ 2,680,318,800.00$

    Conformacin de orilla (Terraplenes) m3 621.528 5,296.50$ 3,291,923.05$

    13,768,537,392.61$

    Valor Total

    Adecuacin caos

    TOTAL

    CantidadComponente o Categora del

    GastoRelacin de Actividades Unidades Valor Unitario

  • 7/31/2019 FICHAS ADECUACIN CAOS_0.3

    4/17

    Excavacin lateral cauce m3 139166 5,600.00$ 779,329,488.00$

    Dragado fondo cauce m3 72212.07 10,000.00$ 722,120,700.00$

    Descapote (20 cm espesor) m2 376445.7 1,200.00$ 451,734,804.00$

    Excavacin de material comn de prestmo

    para conformacin de zanjas m3

    139896

    3,895.00$ 544,894,920.00$Colocacin geotextil no tejido en zanja de

    prestmo m2128555.3

    4,184.00$ 537,875,417.04$

    Riego de liga con emulsin asfaltica m2 128555.3 1,031.00$ 132,540,524.61$

    Descargas en PVC 4'' @ 200 m m 321.6 46,000.00$ 14,793,600.00$

    Lleno zanja con material sobrante de

    excavacin m3139896

    5,000.00$ 699,480,000.00$

    Conformacin de orilla (Terraplenes) m3 48326.82 5,296.50$ 255,963,002.13$

    4,138,732,455.78$

    Valor Total

    Adecuacin caos

    TOTAL

    CantidadComponente o Categora del

    GastoRelacin de Actividades Unidades Valor Unitario

  • 7/31/2019 FICHAS ADECUACIN CAOS_0.3

    5/17

    Excavacin lateral cauce m3 2172671.3 5,600.00$ 12,166,959,168.00$

    Dragado fondo cauce m3 367127.28 10,000.00$ 3,671,272,800.00$

    Descapote (20 cm espesor) m2 4857376.3 1,200.00$ 5,828,851,584.00$

    Excavacin de material comn de prestmo

    para conformacin de zanjas m3

    671292

    3,895.00$ 2,614,682,340.00$Colocacin geotextil no tejido en zanja de

    prestmo m2616873.62

    4,184.00$ 2,580,999,226.08$

    Riego de liga con emulsin asfaltica m2 616873.62 1,031.00$ 635,996,702.22$

    Descargas en PVC 4'' @ 200 m m 1543.2 46,000.00$ 70,987,200.00$

    Lleno zanja con material sobrante de

    excavacin m3671292

    5,000.00$ 3,356,460,000.00$

    Conformacin de orilla (Terraplenes) m3 1757396.2 5,296.50$ 9,308,048,761.44$

    40,234,257,781.74$

    Valor Total

    Adecuacin caos

    TOTAL

    CantidadComponente o Categora del

    GastoRelacin de Actividades Unidades Valor Unitario

  • 7/31/2019 FICHAS ADECUACIN CAOS_0.3

    6/17

    Excavacin lateral cauce m3 122868.8 5,600.00$ 688,065,000.00$

    Dragado fondo cauce m3 59397.48 10,000.00$ 593,974,800.00$

    Descapote (20 cm espesor) m2 323509.7 1,200.00$ 388,211,688.00$

    Excavacin de material comn de prestmo

    para conformacin de zanjas m3

    123922.8

    3,895.00$ 482,679,306.00$Colocacin geotextil no tejido en zanja de

    prestmo m2113877

    4,184.00$ 476,461,242.48$

    Riego de liga con emulsin asfaltica m2 113877 1,031.00$ 117,407,156.07$

    Descargas en PVC 4'' @ 200 m m 284.88 46,000.00$ 13,104,480.00$

    Lleno zanja con material sobrante de

    excavacin m3123922.8

    5,000.00$ 619,614,000.00$

    Conformacin de orilla (Terraplenes) m3 37832.07 5,296.50$ 200,377,558.76$

    3,579,895,231.31$

    Valor Total

    Adecuacin caos

    TOTAL

    CantidadComponente o Categora del

    GastoRelacin de Actividades Unidades Valor Unitario

  • 7/31/2019 FICHAS ADECUACIN CAOS_0.3

    7/17

    Excavacin lateral cauce m3 483339.3 5,600.00$ 2,706,700,080.00$

    Dragado fondo cauce m3 1801081 10,000.00$ 18,010,810,200.00$

    Descapote (20 cm espesor) m2 4290771 1,200.00$ 5,148,925,056.00$

    Excavacin de material comn de prestmo

    para conformacin de zanjas m3

    840002.4

    3,895.00$ 3,271,809,348.00$Colocacin geotextil no tejido en zanja de

    prestmo m2771907.5

    4,184.00$ 3,229,660,854.48$

    Riego de liga con emulsin asfaltica m2 771907.5 1,031.00$ 795,836,601.57$

    Descargas en PVC 4'' @ 200 m m 1931.04 46,000.00$ 88,827,840.00$

    Lleno zanja con material sobrante de

    excavacin m3840002.4

    5,000.00$ 4,200,012,000.00$

    Conformacin de orilla (Terraplenes) m3 1305383 5,296.50$ 6,913,961,271.36$

    44,366,543,251.41$

    Valor Total

    Adecuacin caos

    TOTAL

    CantidadComponente o Categora del

    GastoRelacin de Actividades Unidades Valor Unitario

  • 7/31/2019 FICHAS ADECUACIN CAOS_0.3

    8/17

    Excavacin lateral cauce m3 1259006 5,600.00$ 7,050,434,496.00$

    Dragado fondo cauce m3 1343261 10,000.00$ 13,432,611,000.00$

    Descapote (20 cm espesor) m2 2977294 1,200.00$ 3,572,752,212.00$

    Excavacin de material comn de prestmo

    para conformacin de zanjas m3550892.7

    3,895.00$ 2,145,727,066.50$

    Colocacin geotextil no tejido en zanja de

    prestmo m2506234.5

    4,184.00$ 2,118,085,106.16$

    Riego de liga con emulsin asfaltica m2 506234.5 1,031.00$ 521,927,759.19$

    Descargas en PVC 4'' @ 200 m m 1266.42 46,000.00$ 58,255,320.00$

    Lleno zanja con material sobrante de

    excavacin m3550892.7

    5,000.00$ 2,754,463,500.00$

    Conformacin de orilla (Terraplenes) m3 1960192 5,296.50$ 10,382,158,622.88$

    42,036,415,082.73$

    Valor Unitario Valor Total

    Adecuacin caos

    TOTAL

    CantidadComponente o Categora del

    GastoRelacin de Actividades Unidades

  • 7/31/2019 FICHAS ADECUACIN CAOS_0.3

    9/17

    Excavacin lateral cauce m3 62165.64 5,600.00$ 348,127,584.00$

    Dragado fondo cauce m3 37895.46 10,000.00$ 378,954,600.00$

    Descapote (20 cm espesor) m2 120208.3 1,200.00$ 144,249,912.00$

    Excavacin de material comn de prestmo

    para conformacin de zanjas m3

    23529.15

    3,895.00$ 91,646,039.25$Colocacin geotextil no tejido en zanja de

    prestmo m221621.75

    4,184.00$ 90,465,402.00$

    Riego de liga con emulsin asfaltica m2 21621.75 1,031.00$ 22,292,024.25$

    Descargas en PVC 4'' @ 200 m m 54.09 46,000.00$ 2,488,140.00$

    Lleno zanja con material sobrante de

    excavacin m323529.15

    5,000.00$ 117,645,750.00$

    Conformacin de orilla (Terraplenes) m3 72637.47 5,296.50$ 384,724,359.86$

    1,580,593,811.36$

    Valor Total

    Adecuacin caos

    TOTAL

    CantidadComponente o Categora del

    GastoRelacin de Actividades Unidades Valor Unitario

  • 7/31/2019 FICHAS ADECUACIN CAOS_0.3

    10/17

    Excavacin lateral cauce m3 596141.9 5,600.00$ 3,338,394,696.00$

    Dragado fondo cauce m3 363401.2 10,000.00$ 3,634,012,200.00$

    Descapote (20 cm espesor) m2 1152746 1,200.00$ 1,383,295,104.00$

    Excavacin de material comn de prestmo

    para conformacin de zanjas m3

    225634.5

    3,895.00$ 878,846,377.50$Colocacin geotextil no tejido en zanja de

    prestmo m2207343.4

    4,184.00$ 867,524,827.44$

    Riego de liga con emulsin asfaltica m2 207343.4 1,031.00$ 213,771,055.71$

    Descargas en PVC 4'' @ 200 m m 518.7 46,000.00$ 23,860,200.00$

    Lleno zanja con material sobrante de

    excavacin m3225634.5

    5,000.00$ 1,128,172,500.00$

    Conformacin de orilla (Terraplenes) m3 696562.2 5,296.50$ 3,689,341,851.20$

    15,157,218,811.85$

    Valor Total

    Adecuacin caos

    TOTAL

    CantidadComponente o Categora del

    GastoRelacin de Actividades Unidades Valor Unitario

  • 7/31/2019 FICHAS ADECUACIN CAOS_0.3

    11/17

    Excavacin lateral cauce m3 1651498 5,600.00$ 9,248,387,400.00$

    Dragado fondo cauce m3 611662.2 10,000.00$ 6,116,622,300.00$

    Descapote (20 cm espesor) m2 2193111 1,200.00$ 2,631,733,416.00$

    Excavacin de material comn de prestmo

    para conformacin de zanjas m3

    423211.5

    3,895.00$ 1,648,408,792.50$Colocacin geotextil no tejido en zanja de

    prestmo m2388903.8

    4,184.00$ 1,627,173,499.20$

    Riego de liga con emulsin asfaltica m2 388903.8 1,031.00$ 400,959,817.80$

    Descargas en PVC 4'' @ 200 m m 972.9 46,000.00$ 44,753,400.00$

    Lleno zanja con material sobrante de

    excavacin m3423211.5

    5,000.00$ 2,116,057,500.00$

    Conformacin de orilla (Terraplenes) m3 1769900 5,296.50$ 9,374,273,655.12$

    33,208,369,780.62$

    Valor Total

    Adecuacin caos

    TOTAL

    CantidadComponente o Categora del

    GastoRelacin de Actividades Unidades Valor Unitario

  • 7/31/2019 FICHAS ADECUACIN CAOS_0.3

    12/17

    Excavacin lateral cauce m3 657839.6 5,600.00$ 3,683,901,648.00$

    Dragado fondo cauce m3 695417.9 10,000.00$ 6,954,178,500.00$

    Descapote (20 cm espesor) m2 2548291 1,200.00$ 3,057,948,684.00$

    Excavacin de material comn de prestmo

    para conformacin de zanjas m3

    477969.3

    3,895.00$ 1,861,690,423.50$Colocacin geotextil no tejido en zanja de

    prestmo m2439222.7

    4,184.00$ 1,837,707,567.60$

    Riego de liga con emulsin asfaltica m2 439222.7 1,031.00$ 452,838,552.15$

    Descargas en PVC 4'' @ 200 m m 1098.78 46,000.00$ 50,543,880.00$

    Lleno zanja con material sobrante de

    excavacin m3477969.3

    5,000.00$ 2,389,846,500.00$

    Conformacin de orilla (Terraplenes) m3 796176 5,296.50$ 4,216,946,184.00$

    24,505,601,939.25$

    Valor Total

    Adecuacin caos

    TOTAL

    CantidadComponente o Categora del

    GastoRelacin de Actividades Unidades Valor Unitario

  • 7/31/2019 FICHAS ADECUACIN CAOS_0.3

    13/17

    Excavacin lateral cauce m3 186247.4 5,600.00$ 1,042,985,160.00$

    Dragado fondo cauce m3 114480.7 10,000.00$ 1,144,807,200.00$

    Descapote (20 cm espesor) m2 557612.5 1,200.00$ 669,134,952.00$

    Excavacin de material comn de prestmo

    para conformacin de zanjas m3

    132444.5

    3,895.00$ 515,871,132.75$Colocacin geotextil no tejido en zanja de

    prestmo m2121707.8

    4,184.00$ 509,225,477.04$

    Riego de liga con emulsin asfaltica m2 121707.8 1,031.00$ 125,480,752.11$

    Descargas en PVC 4'' @ 200 m m 304.47 46,000.00$ 14,005,620.00$

    Lleno zanja con material sobrante de

    excavacin m3132444.5

    5,000.00$ 662,222,250.00$

    Conformacin de orilla (Terraplenes) m3 146361.8 5,296.50$ 775,205,167.77$

    5,458,937,711.67$

    Valor Total

    Adecuacin caos

    TOTAL

    CantidadComponente o Categora del

    GastoRelacin de Actividades Unidades Valor Unitario

  • 7/31/2019 FICHAS ADECUACIN CAOS_0.3

    14/17

    Excavacin lateral cauce m3 2905697 5,600.00$ 16,271,901,744.00$

    Dragado fondo cauce m3 1787699 10,000.00$ 17,876,990,400.00$

    Descapote (20 cm espesor) m2 4584575 1,200.00$ 5,501,489,940.00$

    Excavacin de material comn de prestmo

    para conformacin de zanjas m3

    657459

    3,895.00$ 2,560,802,805.00$Colocacin geotextil no tejido en zanja de

    prestmo m2604162

    4,184.00$ 2,527,813,766.16$

    Riego de liga con emulsin asfaltica m2 604162 1,031.00$ 622,891,011.69$

    Descargas en PVC 4'' @ 200 m m 1511.4 46,000.00$ 69,524,400.00$

    Lleno zanja con material sobrante de

    excavacin m3657459

    5,000.00$ 3,287,295,000.00$

    Conformacin de orilla (Terraplenes) m3 3927116 5,296.50$ 20,799,969,629.18$

    69,518,678,696.03$

    Valor Total

    Adecuacin caos

    TOTAL

    CantidadComponente o Categora del

    GastoRelacin de Actividades Unidades Valor Unitario

  • 7/31/2019 FICHAS ADECUACIN CAOS_0.3

    15/17

    Excavacin lateral cauce m3 288283.1 5,600.00$ 1,614,385,248.00$

    Dragado fondo cauce m3 516901.5 10,000.00$ 5,169,015,000.00$

    Descapote (20 cm espesor) m2 1440874 1,200.00$ 1,729,048,788.00$

    Excavacin de material comn de prestmo

    para conformacin de zanjas m3

    512016.8

    3,895.00$ 1,994,305,241.25$Colocacin geotextil no tejido en zanja de

    prestmo m2470510

    4,184.00$ 1,968,614,007.36$

    Riego de liga con emulsin asfaltica m2 470510 1,031.00$ 485,095,851.24$

    Descargas en PVC 4'' @ 200 m m 1177.05 46,000.00$ 54,144,300.00$

    Lleno zanja con material sobrante de

    excavacin m3512016.8

    5,000.00$ 2,560,083,750.00$

    Conformacin de orilla (Terraplenes) m3 208420.2 5,296.50$ 1,103,897,748.20$

    16,678,589,934.05$

    Valor Total

    Adecuacin caos

    TOTAL

    CantidadComponente o Categora del

    GastoRelacin de Actividades Unidades Valor Unitario

  • 7/31/2019 FICHAS ADECUACIN CAOS_0.3

    16/17

    Excavacin lateral cauce m3 63137.61 5,600.00$ 353,570,616.00$

    Dragado fondo cauce m3 59843.16 10,000.00$ 598,431,600.00$

    Descapote (20 cm espesor) m2 205029.5 1,200.00$ 246,035,448.00$

    Excavacin de material comn de prestmo

    para conformacin de zanjas m3

    61824.39

    3,895.00$ 240,805,999.05$Colocacin geotextil no tejido en zanja de

    prestmo m256812.56

    4,184.00$ 237,703,751.04$

    Riego de liga con emulsin asfaltica m2 56812.56 1,031.00$ 58,573,749.36$

    Descargas en PVC 4'' @ 200 m m 142.14 46,000.00$ 6,538,440.00$

    Lleno zanja con material sobrante de

    excavacin m361824.39

    5,000.00$ 309,121,950.00$

    Conformacin de orilla (Terraplenes) m3 40690.38 5,296.50$ 215,516,597.67$

    2,266,298,151.12$

    Valor Total

    Adecuacin caos

    TOTAL

    CantidadComponente o Categora del

    GastoRelacin de Actividades Unidades Valor Unitario

  • 7/31/2019 FICHAS ADECUACIN CAOS_0.3

    17/17

    Excavacin lateral cauce m3 343400.1 5,600.00$ 1,923,040,560.00$

    Dragado fondo cauce m3 305691.5 10,000.00$ 3,056,914,500.00$

    Descapote (20 cm espesor) m2 1091324 1,200.00$ 1,309,589,100.00$

    Excavacin de material comn de prestmo

    para conformacin de zanjas m3

    312443.1

    3,895.00$ 1,216,965,874.50$Colocacin geotextil no tejido en zanja de

    prestmo m2287114.9

    4,184.00$ 1,201,288,532.40$

    Riego de liga con emulsin asfaltica m2 287114.9 1,031.00$ 296,015,410.35$

    Descargas en PVC 4'' @ 200 m m 718.26 46,000.00$ 33,039,960.00$

    Lleno zanja con material sobrante de

    excavacin m3312443.1

    5,000.00$ 1,562,215,500.00$

    Conformacin de orilla (Terraplenes) m3 233219 5,296.50$ 1,235,244,486.47$

    11,834,313,923.72$

    Valor Total

    Adecuacin caos

    TOTAL

    CantidadComponente o Categora del

    GastoRelacin de Actividades Unidades Valor Unitario