indicadores del valor ganado (spi, cpi)
Post on 20-Jul-2015
530 Views
Preview:
TRANSCRIPT
Proyecto: Fecha Inicio: Fecha Fin: Nmero de das: Horas del Proyecto (BAC): Horas Presupuestadas del Proyecto (BAC):
6/23/2008 7/31/200838
350 79,250.00
Semana
Fecha
PV
Datos a introducir EV
AC
Indicadores SPI CPI
1 2 3 4 5
6/30/2008 7/7/2008 7/14/2008 7/21/2008 7/28/2008
7,500.00 11,250.00 21,250.00 40,250.00 79,250.00
3,750.00 10,000.00 19,000.00 39,000.00 75,000.00
7,500.00 12,000.00 26,000.00 47,000.00 80,000.00
0.50 0.89 0.89 0.97 0.95
0.50 0.83 0.73 0.83 0.94
50,000.00
10,000.00 EV PV AC
20,000.00
30,000.00
40,000.00
60,000.00
70,000.00
80,000.00
90,000.00
0.00 6/30/20087/2/2008
7/4/2008 7/6/2008 7/8/2008 7/10/2008 7/12/2008 7/14/2008 7/16/20087/18/2008
7/20/2008 7/22/2008 7/24/2008 7/26/20087/28/2008