CRONOGRAMA DE AVANCE FISICO VALORIZADO ITEM DESCRIPCION UND METRADO MES01 MES02 MES03 MES04 MES05 MES06 MES07 MES08 01 OBRAS PRELIMINARES 141,175.82 01.01 CAMPAMENTO MOVIL CON TRIPLAY Y TECHO DE CALAMINA m2 200.00 15,622.00 15,622.00 100% 01.02 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m u 1.00 1,201.22 1201.22 100% 01.03 MEJORAMIENTO DE CAMINOS DE ACCESO EXISTENTES km 2.00 6,029.70 6,029.70 100% 01.04 FLETE TERRESTRE glb 1.00 118,322.90 23,664.6 23,664.6 23,664.6 23,664.6 23,664.6 20% 20% 20% 20% 20% 02 CONTROL DE CALIDAD DEL CONCRETO 2,850.00 02.01 ELABORACION Y ROTURA DE TESTIGOS DE CONCRETO CADA 25 m3 ensy 45.00 1,800.00 1,800.00 100% 02.02 CONTROL DE SLUMP (AASHTO T-119) ensy 15.00 600.00 600.00 100% 02.03 ENSAYOS DE GRANULOMETRIA ensy 15.00 450.00 450.00 100% 03 CONSTRUCCION DE RESERVORIO GEOMEBRANA 277,752.63 03.01 LIMPIEZA DE TERRENO MANUAL m2 1,925.76 1,213.23 1213.23 100% 03.02 TRAZO Y REPLANTEO m2 1,925.76 5,199.55 5199.55 100% 03.03 EXCAVACION EN TIERRA SUELTA m3 3,895.10 66,567.26 57414.26 86% 03.04 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 708.72 26,711.66 18276.92 68% 03.05 ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 3,982.97 40,666.12 26305.9 65% 03.06 REFINE, Y PERFILADO DE TALUD m2 525.03 1,428.08 03.07 NIVELADO DE PENDIENTE FONDO m2 1,500.00 2,685.00 03.08 TARRAJEO CON BARRO TALUDES Y PISO m2 2,114.77 12,752.06 03.09 GEOMEMBRANA E=1.5MM, INCLUIDO INSTALACION m2 2,330.29 91,463.88 03.10 ENCOFRADO Y DESENCOFRADO DE MUROS CARAVISTA m2 27.53 1,137.81 1137.81 100% 03.11 CONCRETO f'c=175 kg/cm2 m3 15.27 6,183.43 6183.43 100% 03.12 TARRAJEO MEZCLA 1:3 m2 101.45 1,631.32 1631.32 100% 03.13 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-5 D=10" m 24.00 2,627.52 03.14 SUMINISTRO Y COLOCACION DE TUBERIA PVC-UF/S-25 D=200 mm m 36.00 3,106.08 03.15 SUMINISTRO E INSTALACION DE CODOS PVC DE 90° SAP D=10" UND 4.00 355.00 03.16 SUMINISTRO Y COLOCACION DE VALVULAS DE COMPUERTA. UND 1.00 5,093.56 03.17 SUMINISTRO Y COLOCACION COMPUERTA TIPO I UND 1.00 793.56 793.56 100% 03.18 SUMINISTRO Y COLOCACION DE REJILLA METALICA UND 1.00 443.56 443.56 100% 03.19 CERCO PERIMETRICO CON ALAMBRE PUA m 221.60 7,693.95 04 MEDIDOR DE CAUDAL 438.95 04.01 EXCAVACION EN TIERRA SUELTA m3 0.45 7.69 7.69 100% 04.02 CONCRETO f'c=175 kg/cm2 m3 0.35 141.73 141.73 100% 04.03 ENCOFRADO Y DESENCOFRADO DE MUROS CARAVISTA m2 0.47 19.43 19.43 1 04.04 LIMNIMETRO METALICO GRADUADO u 1.00 256.48 256.48 1 04.05 SOLAQUEO DE MUROS YPISO m2 1.35 13.23 13.23 100% 04.06 CURADO DE ESTRUCTURA VACIADO m2 1.35 0.39 0.39 100% 05 CANAL DE CONDUCCION SECCION TRAPEZOIDAL 1,201,243.55 05.01 TRABAJOS PRELIMINARES 55,489.33 05.01.01 LIMPIEZA DE TERRENO MANUAL m2 7,878.60 4,963.52 1735.08 1117.33 1,160.30 950.8 COSTO PARCIAL S/.

Upload: frederick-cole

Post on 15-Jan-2016

11 views

Category:

Documents


0 download

DESCRIPTION

programación de obra

TRANSCRIPT

Page 1: Programacion de Obra

CRONOGRAMA DE AVANCE FISICO VALORIZADOITEM DESCRIPCION UND METRADO MES01 MES02 MES03 MES04 MES05 MES06 MES07 MES08 MES 09

01 OBRAS PRELIMINARES 141,175.82

01.01 CAMPAMENTO MOVIL CON TRIPLAY Y TECHO DE CALAMINA m2 200.00 15,622.00 15,622.00

100%

01.02 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m u 1.00 1,201.22 1201.22

100%

01.03 MEJORAMIENTO DE CAMINOS DE ACCESO EXISTENTES km 2.00 6,029.70 6,029.70

100%

01.04 FLETE TERRESTRE glb 1.00 118,322.90 23,664.6 23,664.6 23,664.6 23,664.6 23,664.6

20% 20% 20% 20% 20%

02 CONTROL DE CALIDAD DEL CONCRETO 2,850.00

02.01 ELABORACION Y ROTURA DE TESTIGOS DE CONCRETO CADA 25 m3 ensy 45.00 1,800.00 1,800.00

100%

02.02 CONTROL DE SLUMP (AASHTO T-119) ensy 15.00 600.00 600.00

100%

02.03 ENSAYOS DE GRANULOMETRIA ensy 15.00 450.00 450.00

100%

03 CONSTRUCCION DE RESERVORIO GEOMEBRANA 277,752.63

03.01 LIMPIEZA DE TERRENO MANUAL m2 1,925.76 1,213.23 1213.23

100%

03.02 TRAZO Y REPLANTEO m2 1,925.76 5,199.55 5199.55

100%

03.03 EXCAVACION EN TIERRA SUELTA m3 3,895.10 66,567.26 57414.26 9153

86% 14%

03.04 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 708.72 26,711.66 18276.92 8434.74

68% 32%

03.05 ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3 3,982.97 40,666.12 26305.9 14360.22

65% 35%

03.06 REFINE, Y PERFILADO DE TALUD m2 525.03 1,428.08 1428.08

100%

03.07 NIVELADO DE PENDIENTE FONDO m2 1,500.00 2,685.00 2685

100%

03.08 TARRAJEO CON BARRO TALUDES Y PISO m2 2,114.77 12,752.06 12752.06

100%

03.09 GEOMEMBRANA E=1.5MM, INCLUIDO INSTALACION m2 2,330.29 91,463.88 91463.88

100%

03.10 ENCOFRADO Y DESENCOFRADO DE MUROS CARAVISTA m2 27.53 1,137.81 1137.81

100%

03.11 CONCRETO f'c=175 kg/cm2 m3 15.27 6,183.43 6183.43

100%

03.12 TARRAJEO MEZCLA 1:3 m2 101.45 1,631.32 1631.32

100%

03.13 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-5 D=10" m 24.00 2,627.52 2627.52

100%

03.14 SUMINISTRO Y COLOCACION DE TUBERIA PVC-UF/S-25 D=200 mm m 36.00 3,106.08 3106.08

100%

03.15 SUMINISTRO E INSTALACION DE CODOS PVC DE 90° SAP D=10" UND 4.00 355.00 355

100%

03.16 SUMINISTRO Y COLOCACION DE VALVULAS DE COMPUERTA. UND 1.00 5,093.56 5093.56

100%

03.17 SUMINISTRO Y COLOCACION COMPUERTA TIPO I UND 1.00 793.56 793.56

100%

03.18 SUMINISTRO Y COLOCACION DE REJILLA METALICA UND 1.00 443.56 443.56

100%

03.19 CERCO PERIMETRICO CON ALAMBRE PUA m 221.60 7,693.95 7693.95

100%

04 MEDIDOR DE CAUDAL 438.95

04.01 EXCAVACION EN TIERRA SUELTA m3 0.45 7.69 7.69

100%

04.02 CONCRETO f'c=175 kg/cm2 m3 0.35 141.73 141.73

100%

04.03 ENCOFRADO Y DESENCOFRADO DE MUROS CARAVISTA m2 0.47 19.43 19.43

1

04.04 LIMNIMETRO METALICO GRADUADO u 1.00 256.48 256.48

1

04.05 SOLAQUEO DE MUROS YPISO m2 1.35 13.23 13.23

100%

04.06 CURADO DE ESTRUCTURA VACIADO m2 1.35 0.39 0.39

100%

05 CANAL DE CONDUCCION SECCION TRAPEZOIDAL 1,201,243.55

05.01 TRABAJOS PRELIMINARES 55,489.33

05.01.01 LIMPIEZA DE TERRENO MANUAL m2 7,878.60 4,963.52 1735.08 1117.33 1,160.30 950.8

COSTO PARCIALS/.

Page 2: Programacion de Obra

CRONOGRAMA DE AVANCE FISICO VALORIZADOITEM DESCRIPCION UND METRADO MES01 MES02 MES03 MES04 MES05 MES06 MES07 MES08 MES 09COSTO PARCIAL

S/.

35% 23% 23% 19%

05.01.02 TRAZO Y REPLANTEO EN CANALES km 7.88 10,973.69 4202.9 2312.52 2401.46 2056.81

38% 21% 22% 19%

Page 3: Programacion de Obra

CRONOGRAMA DE AVANCE FISICO VALORIZADOITEM DESCRIPCION UND METRADO MES01 MES02 MES03 MES04 MES05 MES06 MES07 MES08 MES 09COSTO PARCIAL

S/.

05.01.03 CONTROL TOPOGRAFICO mes 9.00 39,552.12 5,261.8 5,710.5 5,930.1 5,490.9 5,930.1 5,710.5 5,518.3

13% 14% 15% 14% 15% 14% 14%

05.02 MOVIMIENTO DE TIERRAS 435,355.64

05.02.01 EXCAVACION DE PLATAFORMA EN TIERRA (LAMPA Y PICO) m3 3,426.50 58,558.89 7,767.2 8,458.5 8,783.8 8,133.2 8,783.8 8,458.5 8,173.9

13% 14% 15% 14% 15% 14% 14%

05.02.02 EXCAVACION DE PLATAFORMA EN ROCA SUELTA ( A MANO ) m3 2,975.09 84,760.31 11242.51 12243.16 12714.05 11772.27 12714.05 12243.16 11831.13

13% 14% 15% 14% 15% 14% 14%

05.02.03 EXCAVACION DE PLATAFORMA EN ROCA FIJA m3 4,265.36 183,922.32 116,855.1 11,168.9 11,598.5 10,739.4 11,598.5 11,168.9 10,793.0

63.54% 6.07% 6.31% 5.84% 6.31% 6.07% 5.87%

05.02.04 EXCAVACION CAJA CANAL MATERIAL SUELTO A MANO m3 1,394.50 23,832.01 3,161.1 3,442.4 3,574.8 3,310.0 3,574.8 3,442.4 3,326.6

13.3% 14.4% 15.0% 13.9% 15.0% 14.4% 14.0%

05.02.05 EXCAVACION CAJA CANAL ROCA SUELTA A MANO m3 677.12 19,291.15 2,558.8 2,786.5 2,893.7 2,679.3 2,893.7 2,786.5 2,692.7

13% 14% 15% 14% 15% 14% 14%

05.02.06 EXCAVACION CAJA CANAL ROCA FIJA m3 769.68 26,600.14 15,022.0 1,928.2 2,002.3 1,854.0 2,002.3 1,928.2 1,863.3

56% 7% 8% 7% 8% 7% 7%

05.02.07 ENROCADO DE TALUD DE CAJA CANAL m2 1,425.00 13,238.25 2151.22 11,087.03

16% 84%

05.02.08 RELLENO COMPACTADO m3 600.00 5,850.00 1618.45 4,231.55

28% 72%

05.02.09 REFINE, NIVELACION Y COMPACTACION m2 7,878.60 19,302.57 2,560.3 2,788.2 2,895.4 2,680.9 2,895.4 2,788.2 2,694.3

13% 14% 15% 14% 15% 14% 14%

05.03 OBRAS DE CONCRETO 710,398.58

05.03.01 ACARREO DE MATERIAL AGREGADO CON CARRETILLAS m3 1,061.57 17,643.29 2,340.2 2,548.5 2,646.5 2,450.5 2,646.5 2,548.5 2,462.7

13% 14% 15% 14% 15% 14% 14%

05.03.02 ACARREO DE MATERIAL CEMENTO UND 12,417.00 17,259.63 2,289.3 2,493.1 2,588.9 2,397.2 2,588.9 2,493.1 2,409.2

13% 14% 15% 14% 15% 14% 14%

05.03.03 CONFECCION DE CERCHAS DE MADERA TORNILLO INCLUIDO JUNTAS u 120.00 5,202.00 5,202.00

100%

05.03.04 COLOCACION DE CERCHAS DE MADERA TORNILLO u 3,813.00 11,629.65 1,542.5 1,679.8 1,744.5 1,615.2 1,744.5 1,679.8 1,623.3

13% 14% 15% 14% 15% 14% 14%

05.03.05 CONCRETO f'c=175 kg/cm2 m3 1,061.57 429,872.16 61,410.3 61,410.3 61,410.3 61,410.3 61,410.3 61,410.3 61,410.3

14% 14% 14% 14% 14% 14% 14%

05.03.06 TARRAJEO MEZCLA 1:3 m2 10,621.66 170,796.29 24,399.5 24,399.5 24,399.5 24,399.5 24,399.5 24,399.5 24,399.5

14.286% 14.286% 14.286% 14.286% 14.286% 14.286% 14.286%

05.03.07 JUNTAS ASFALTICAS m 5,270.18 54,915.28 39726.58 6255.94 6255.94 2676.82

72% 11% 11% 5%

05.03.08 CURADO DE LA ESTRUCTURA VACIADA m2 10,621.66 3,080.28 458.3 431.1 447.7 414.5 447.7 431.1 431.2 18.65

15% 14% 15% 13% 15% 14% 14% 0.6%

06 POZA DISIPADORA + TRANSICIONES 25,523.07

06.01 TRAZO Y REPLANTEO m2 83.41 225.21 225.21

100%

06.02 EXCAVACION EN TIERRA SUELTA m3 65.10 1,112.56 287.41 825.15

26% 74%

06.03 REFINE, NIVELACION Y COMPACTACION m2 83.41 204.35 204.35

100%

06.04 ENCOFRADO Y DESENCOFRADO DE MUROS CARAVISTA m2 153.66 6,350.77 6350.77

100%

06.05 CONCRETO f'c=175 kg/cm2 m3 34.45 13,950.18 13141.69 808.49

94% 6%

06.06 CURADO DE LA ESTRUCTURA VACIADA m2 229.67 66.60 19.35 47.25

29% 71%

06.07 SOLAQUEO DE MUROS YPISO m2 229.67 2,250.77 2093.78 156.99

93% 7%

06.08 JUNTAS WATER STOP 6" m 38.70 556.12 556.12

100%

06.09 JUNTAS ASFALTICAS m 77.40 806.51 806.51

100%

07 PASARELA (06 UND) 3,449.28

07.01 TRAZO Y REPLANTEO m2 49.14 132.68 132.68

100%

07.02 EXCAVACION ROCA SUELTA A MANO m3 2.20 46.99 46.99

100%

07.03 ENCOFRADO Y DESENCOFRADO DE MUROS CARAVISTA m2 19.04 786.92 786.92

100%

07.04 CONCRETO f'c=210 kg/cm2 m3 2.21 932.53 932.53

100%

07.05 CONCRETO CICLOPEO f'c=140 kg/cm2 + 30 % PM. m3 2.31 766.32 766.32

100%

07.06 ACERO FY= 4200 KG/CM2 kg 100.69 557.82 557.82

100%

07.07 SOLAQUEO DE MUROS YPISO m2 22.40 219.52 219.52

Page 4: Programacion de Obra

CRONOGRAMA DE AVANCE FISICO VALORIZADOITEM DESCRIPCION UND METRADO MES01 MES02 MES03 MES04 MES05 MES06 MES07 MES08 MES 09COSTO PARCIAL

S/.

100%

07.08 CURADO DE LA ESTRUCTURA VACIADA m2 22.40 6.50 6.5

100%

Page 5: Programacion de Obra

CRONOGRAMA DE AVANCE FISICO VALORIZADOITEM DESCRIPCION UND METRADO MES01 MES02 MES03 MES04 MES05 MES06 MES07 MES08 MES 09COSTO PARCIAL

S/.

08 PASE VEHICULAR (01 UND) 5,393.01

08.01 TRAZO Y REPLANTEO m2 22.50 60.75 60.75

100%

08.02 EXCAVACION EN TIERRA SUELTA m3 9.56 163.38 163.38

100%

08.03 ENCOFRADO Y DESENCOFRADO DE MUROS CARAVISTA m2 23.36 965.47 965.47

100%

08.04 CONCRETO f'c=210 kg/cm2 m3 1.32 556.99 556.99

100%

08.05 CONCRETO SIMPLE f'c=140 kg/cm2 m3 5.78 2,216.80 2216.8

100%

08.06 ACERO FY= 4200 KG/CM2 kg 246.07 1,363.23 1363.23

100%

08.07 SOLAQUEO DE MUROS YPISO m2 6.58 64.48 64.48

100%

08.08 CURADO DE LA ESTRUCTURA VACIADA m2 6.58 1.91 1.91

100%

09 TOMAS LATERALES (48 UND) 21,809.07

09.01 TRAZO Y REPLANTEO m2 121.03 326.78 326.78

100%

09.02 EXCAVACION ROCA SUELTA A MANO m3 15.03 321.04 321.04

100%

09.03 ENCOFRADO Y DESENCOFRADO DE MUROS CARAVISTA m2 46.94 1,940.03 1940.03

100%

09.04 CONCRETO f'c=175 kg/cm2 m3 21.41 8,669.77 8648.83 20.94

100% 0.2%

09.05 ACERO FY= 4200 KG/CM2 kg 97.06 537.71 537.71

100%

09.06 SOLAQUEO DE MUROS YPISO m2 176.54 1,730.09 1706.13 23.96

99% 1%

09.07 JUNTAS ASFALTICAS m 10.50 109.41 109.41

100%

09.08 CURADO DE LA ESTRUCTURA VACIADA m2 176.54 51.20 38.02 13.18

74% 26%

09.09 COMPUERTA METALICA TIPO II u 48.00 8,123.04 8108.62 14.42

99.8% 0.18%

10 MITIGACION AMBIENTAL 12,522.62

10.01 INSTALACION DE LETRINA SANITARIA TEMPORAL UND 12.00 2,400.00 2,400.00

100%

10.02 REFORESTACION DEL AREA DE TRABAJO ha 2.00 6,308.74 6308.74

100.0%

10.03 INSTALACION DE CARTELES AMBIENTALES DE 1.2MX0.8M UND 9.00 3,413.88 3413.88

100.0%

10.04 SUMINISTRO DE CONTENEDOR PARA RESIDUOS UND 5.00 400.00 400.00

100%

11 CAPACITACION 27,900.00

11.01 OPERACION Y MANTENIMIENTO DE INFRAESTRUCTURA DE RIEGO Y FORTALECIMI TALLER 6.00 9,300.00 9,300.00

100%

11.02 MANEJO EFICIENTE DE AGUA Y TECNICAS DE RIEGO TALLER 6.00 9,300.00 9,300.00

100%

11.03 PLAN DE CULTIVO Y RIEGO (PCR) TALLER 6.00 9,300.00 9,300.00

100%

COSTO DIRECTO 1,720,058.00 320,615.19 168,582.98 170,856.36 166,019.25 216,321.18 161,326.78 193,695.06 163,306.32 159,335.00

GASTOS GENERALES 221,698.0 41,324.0 21,728.6 22,021.6 21,398.2 27,881.6 20,793.4 24,965.3 21,048.5 20,536.7

SUPERVISION 55,601.0 10,363.9 5,449.5 5,522.9 5,366.6 6,992.6 5,214.9 6,261.2 5,278.9 5,150.5

PRESUPUESTO TOTAL 1,997,357.0 372,303.1 195,761.1 198,401.0 192,784.0 251,195.4 187,335.1 224,921.6 189,633.7 185,022.2

EXPEDIENTE TECNICO

PORCENTAJE DE AVANCE % 18.6% 9.8% 9.9% 9.7% 12.6% 9.4% 11.3% 9.5% 9.3%