PRESUPUESTO DE MANO DE OBRA POR ACTIVIDADSISTEMA DE AGUA IQUIACAbolivianos Tipo de Cambio 5.03

CdigoEspecialidadHoras HombrePrecio UnitarioPrecio Total

1 REPLANTEO EN GENERAL

PEO001PEON 1.19 3.471 4.12TOP001TOPOGRAFO 0.59 13.350 7.92Subtotal Mano de Obra 12.05

2 LIMPIEZA Y DESBROCE

PEO001PEON 7.12 3.471 24.72Subtotal Mano de Obra 24.72

3 EXCAVACION COMUN PARA ESTRUCTURA

PEO001PEON 17.15 3.471 59.53Subtotal Mano de Obra 59.53

4 EMPEDRADO Y CONTRAPISO

ALB001ALBAIL 14.85 3.521 52.29AYU001AYUDANTE 14.85 3.471 51.54Subtotal Mano de Obra 103.83

5 PISO DE CEMENTO ENLUCIDO FINO

ALB001ALBAIL 9.90 3.521 34.86AYU001AYUDANTE 9.90 3.471 34.36Subtotal Mano de Obra 69.22

6 HORMIGON CICLOPEO CON 50% DE PIEDRA DESPLAZADORA 1:2:3

ALB001ALBAIL 34.30 3.521 120.77PEO001PEON 34.30 3.471 119.06Subtotal Mano de Obra 239.83

7 SOBRECIMIENTO DE HO CO

ALB001ALBAIL 9.54 3.521 33.59AYU004AYUDANTE ENCOFRADOR 6.36 3.471 22.08PEO001PEON 9.54 3.471 33.11Subtotal Mano de Obra 88.78

8 MURO DE LADRILLO 6H E=0.15 MTS

ALB001ALBAIL 25.56 3.521 90.00PEO001PEON 10.22 3.471 35.49Subtotal Mano de Obra 125.48

9 REVOQUE INTERIOR DE ESTUCO SOBRE MURO DE LADRILLO

ALB002ALBAIL DE PRIMERA 33.23 3.521 117.00PEO001PEON 35.78 3.471 124.21Subtotal Mano de Obra 241.20

10 CUBIERTA DE CALAMINA N. 28 INCLUYE MADERAMEN

ALB002ALBAIL DE PRIMERA 38.13 3.521 134.24AYU001AYUDANTE 54.90 3.471 190.56Subtotal Mano de Obra 324.80

11 PUERTA DE METAL CON MALLA OLIMPICA

AYU001AYUDANTE 2.10 3.471 7.29ESP001ESPECIALISTA 4.20 4.326 18.17Subtotal Mano de Obra 25.46

12 CERCO DE MALLA OLIMPICA 6" X 6" # 8

AYU001AYUDANTE 52.98 3.471 183.89ESP001ESPECIALISTA 105.96 4.326 458.38Subtotal Mano de Obra 642.28

13 ALAMBRE DE PUAS

ESP001ESPECIALISTA 19.44 4.326 84.10PEO001PEON 19.44 3.471 67.48Subtotal Mano de Obra 151.57

14 CELOSIA DE CERAMICA

ALB001ALBAIL 3.16 3.521 11.11PEO001PEON 1.58 3.471 5.48Subtotal Mano de Obra 16.59

16 QUINCALLERIA (IQUIACA)

SOL001SOLDADOR 0.60 6.891 4.13Subtotal Mano de Obra 4.13

17 INSTALACION DE ACOMETIDA ELECTRICA

AYU003AYUDANTE ELECTRICISTA 7.50 3.471 26.03ELE001ELECTRICISTA 7.50 4.326 32.45Subtotal Mano de Obra 58.48

18 INSTALACION DE BOMBA Y ACCESORIOS

AYU003AYUDANTE ELECTRICISTA 3.70 3.471 12.84ELE001ELECTRICISTA 3.70 4.326 16.01Subtotal Mano de Obra 28.85

19 REPLANTEO Y TRAZADO DE TUBERIAS

ALA001ALARIFE 73.63 4.054 298.50TOP001TOPOGRAFO 18.41 13.350 245.75Subtotal Mano de Obra 544.25

20 EXCAVACION DE ZANJAS 0-2 M SUELO SEMIDURO (MANUAL)

PEO001PEON 2,254.98 3.471 7,827.04Subtotal Mano de Obra 7,827.04

21 TUBERIA PVC E-40 2 " UNION FLEXIBLE

AYU008AYUDANTE PLOMERO 147.26 3.471 511.15PLO001PLOMERO 36.82 4.326 159.27Subtotal Mano de Obra 670.42

22 DESINFECCION DE LA RED DE 0 - 4"

PEO001PEON 36.82 3.471 127.79Subtotal Mano de Obra 127.79

23 PRUEBA HIDRAULICA DE TUB. 1/2" A 4"

PEO001PEON 34.98 3.471 121.40Subtotal Mano de Obra 121.40

24 CAMA DE TIERRA CERNIDA

ALB001ALBAIL 138.06 3.521 486.11PEO001PEON 690.30 3.471 2,396.03Subtotal Mano de Obra 2,882.14

25 RELLENO Y COMPACTADO CON TIERRA COMUN

PEO001PEON 920.40 3.471 3,194.71Subtotal Mano de Obra 3,194.71

26 REPLANTEO EN GENERAL

AYU001AYUDANTE 0.22 3.471 0.76PEO001PEON 0.44 3.471 1.51TOP001TOPOGRAFO 0.22 13.350 2.91Subtotal Mano de Obra 5.18

27 EXCAVACION COMUN PARA ESTRUCTURA

PEO001PEON 56.46 3.471 195.96Subtotal Mano de Obra 195.96

28 HORMIGON ARMADO H35 INCL.ARMADURA

ALB001ALBAIL 215.44 3.521 758.56ARM001ARMADOR 403.95 4.326 1,747.49AYU001AYUDANTE 26.93 3.471 93.47ENC001ENCOFRADOR 188.51 4.326 815.49PEO001PEON 538.60 3.471 1,869.48Subtotal Mano de Obra 5,284.50

29 REVOQUE DE CEMENTO

ALB001ALBAIL 129.60 3.521 456.32PEO001PEON 57.60 3.471 199.93Subtotal Mano de Obra 656.25

30 ENLUCIDO DE MORTERO IMPERMEABLE (1:3) C/SIKA 1

ALB001ALBAIL 43.20 3.521 152.11PEO001PEON 43.20 3.471 149.95Subtotal Mano de Obra 302.05

31 DESINFECCION DE TANQUES

PEO001PEON 1.00 3.471 3.47Subtotal Mano de Obra 3.47

32 CAMARA DE VALVULAS DE HO CO 70 X 7O X 70 CM

ALB001ALBAIL 5.00 3.521 17.61PEO001PEON 5.00 3.471 17.36Subtotal Mano de Obra 34.96

33 ACCESORIOS TANQUE DE ELEVADO

AYU001AYUDANTE 20.60 3.471 71.50PLO001PLOMERO 13.60 4.326 58.83Subtotal Mano de Obra 130.34

34 BARANDA FG 2"

ALB002ALBAIL DE PRIMERA 7.26 3.521 25.56ESP001ESPECIALISTA 59.29 4.326 256.49PEO001PEON 7.26 3.471 25.20Subtotal Mano de Obra 307.25

35 ESCALERA METALICA FG 1"

AYU001AYUDANTE 6.00 3.471 20.83SOL001SOLDADOR 4.50 6.891 31.01Subtotal Mano de Obra 51.84

36 ESCALERA METALICA CON GUARDACUERPO EXTERIOR

PEO001PEON 33.48 3.471 116.22SOL001SOLDADOR 33.48 6.891 230.74Subtotal Mano de Obra 346.96

37 REPLANTEO Y TRAZADO DE TUBERIAS

ALA001ALARIFE 433.41 4.054 1,757.05TOP001TOPOGRAFO 108.35 13.350 1,446.51Subtotal Mano de Obra 3,203.57

38 EXCAVACION DE ZANJAS 0-2 M SUELO SEMIDURO (MANUAL)

PEO001PEON 9,101.64 3.471 31,591.81Subtotal Mano de Obra 31,591.81

39 TUBERIA PVC C-15 3/4" UNION FLEXIBLE

AYU008AYUDANTE PLOMERO 133.77 3.471 464.31PLO001PLOMERO 44.59 4.326 192.89Subtotal Mano de Obra 657.20

40 TUBERIA PVC C-15 1 " UNION FLEXIBLE

AYU008AYUDANTE PLOMERO 123.38 3.471 428.27PLO001PLOMERO 61.69 4.326 266.88Subtotal Mano de Obra 695.15

41 TUBERIA PVC C-15 1 1/2" UNION FLEXIBLE

AYU008AYUDANTE PLOMERO 67.47 3.471 234.20PLO001PLOMERO 16.39 4.326 70.89Subtotal Mano de Obra 305.09

42 TUBERIA PVC C-15 2 " UNION FLEXIBLE

AYU008AYUDANTE PLOMERO 103.97 3.471 360.90PLO001PLOMERO 25.99 4.326 112.45Subtotal Mano de Obra 473.34

43 PRUEBA HIDRAULICA DE TUB. 1/2" A 4"

PEO001PEON 205.87 3.471 714.58PLO001PLOMERO 65.01 4.326 281.24Subtotal Mano de Obra 995.82

44 DESINFECCION DE LA RED DE 0 - 4"

PEO001PEON 216.71 3.471 752.19Subtotal Mano de Obra 752.19

45 CAMA DE TIERRA CERNIDA

ALB001ALBAIL 650.12 3.521 2,289.07PEO001PEON 3,250.60 3.471 11,282.83Subtotal Mano de Obra 13,571.91

46 RELLENO Y COMPACTADO CON TIERRA COMUN

PEO001PEON 3,250.60 3.471 11,282.83Subtotal Mano de Obra 11,282.83

47 CAMARA DE VALVULAS DE HO CO 7O X 7O X 70 CM

ALB001ALBAIL 25.00 3.521 88.03PEO001PEON 25.00 3.471 86.78Subtotal Mano de Obra 174.80

48 CAMARA DE PURGA DE HO CO 70 X 7O X 70 CM

ALB001ALBAIL 20.00 3.521 70.42PEO001PEON 20.00 3.471 69.42Subtotal Mano de Obra 139.84

49 PASO DE QUEBRADA L = 10 M

ALB001ALBAIL 6.00 3.521 21.13PEO001PEON 6.00 3.471 20.83Subtotal Mano de Obra 41.95

50 ACCESORIOS RED DE DISTRIBUCION (PUCARANI)

AYU008AYUDANTE PLOMERO 8.00 3.471 27.77PLO001PLOMERO 7.00 4.326 30.28Subtotal Mano de Obra 58.05

51 EXCAVACION DE ZANJAS 0-2 M SUELO SEMIDURO (MANUAL)

PEO001PEON 1,016.40 3.471 3,527.92Subtotal Mano de Obra 3,527.92

52 HORMIGON SIMPLE 1:2:3 FCK=210 KG/CM2

ALB002ALBAIL DE PRIMERA 28.80 3.521 101.40ALB003ALBAIL DE SEGUNDA 19.20 3.420 65.66ENC001ENCOFRADOR 33.60 4.326 145.35PEO001PEON 86.40 3.471 299.89Subtotal Mano de Obra 612.32

53 ACCESORIOS CONEXION DOMICILIARIA PUCARANI

AYU001AYUDANTE 150.00 3.471 520.65PEO001PEON 750.00 3.471 2,603.25PLO001PLOMERO 150.00 4.326 648.90Subtotal Mano de Obra 3,772.80

TOTAL GENERAL 96,759.87