INFORME DE AVANCE DE OBRA INFORME DE AVANCE DE OBRA OFICINA MISION LIMA CENTRAL OFICINA MISION LIMA CENTRAL N° Proyecto 531 9781 CONTRATISTA CONTRATISTA : INOFUENTE CONTRATISTAS : INOFUENTE CONTRATISTAS SRL SRL SUPERVISOR SUPERVISOR : Arq. Irma Anabel CALLUPE : Arq. Irma Anabel CALLUPE CASTRO CASTRO RESIDENTE DE OBRA RESIDENTE DE OBRA : Ing. Fernando VARGAS MORENO : Ing. Fernando VARGAS MORENO FECHA FECHA : 15- ABRIL– 2015 : 15- ABRIL– 2015 ADMINISTRACION DE PROPIEDADES

Upload: lsu-sadsj-dsfsdjk

Post on 11-Nov-2015

220 views

Category:

Documents


5 download

DESCRIPTION

Informe

TRANSCRIPT

  • INFORME DE AVANCE DE OBRAOFICINA MISION LIMA CENTRALN Proyecto 531 9781 CONTRATISTA : INOFUENTE CONTRATISTAS SRL SUPERVISOR: Arq. Irma Anabel CALLUPE CASTRO RESIDENTE DE OBRA: Ing. Fernando VARGAS MORENO FECHA : 15- ABRIL 2015 ADMINISTRACION DE PROPIEDADES

  • Plazo de obra:90 das.Fecha de Inicio:09/03/2015Fecha de Trmino :06/06/2015Ampliacin de plazo:-------------Tiempo transcurrido:38/90 = 42.22%Avance RE-Programado :42.00 %Avance Fsico Real:41.00%Avance Financiero :43.90%Atraso en la Obra:1.0 DIAOrden de cambio: -------Multa a aplicar: 0 das.

    1.- CONTROL DE AVANCE DE OBRA:

  • Grfico1

    00042072

    7.77777777786642078

    25.5555555556272842094

    42.2222222222414242109

    58.8888888889421244212442124

    75.5555555556421394213942139

    93.3333333333421554215542155

    100421614216142161

    41.0%

    42.0%

    PLAZO

    FISICO

    RE_PROGRAMADO (Contrato)

    Tiempo

    Porcentaje

    datos

    CUADRO COMPARATIVO DE AVANCE DE OBRA (En %)

    FECHADURACION (das)PLAZOFISICOFINANCIERO (Valorizado)RE_PROGRAMADO (Contrato)

    9-Mar-1500.00.00.00.0

    15-Mar-1577.86.07.06.0

    31-Mar-152325.627.027.528.0

    15-Apr-153842.241.043.042.0

    30-Apr-155358.9

    15-May-156875.6

    31-May-158493.3

    6-Jun-1590100.0

    Graph

    GRAFICO COMPARATIVO DE AVANCE DE OBRA

    CUADRO COMPARATIVO DE AVANCE DE OBRA

    RINCONADA - Juliaca

    VALORES TIEMPOFISICOFINANCIEROPROGRAMADOPLAZO

    FECHADIAS%%%%

    9-Mar00.00.00.00.0

    31-Mar2327.027.528.00.0%

    30-Apr530.00.00.00.0%

    31-May840.00.00.00.0%

    31-Dec00.00.00.00.0%

    31-Dec00.00.00.00.0%

    31-Dec00.00.00.00.0%

    31-Dec00.00.00.00.0%

    31-Dec00.00.00.00.0%

    31-Dec00.00.00.00.0%

    31-Dec00.00.00.00.0%

    31-Dec00.00.00.00.0%

    31-Dec00.00.00.00.0%

    31-Dec00.00.00.00.0%

    &LSupervisor: &"Arial,Negrita"Ing Pedro Lavado Tafur

    Graph

    000042072

    7.777777777867642078

    25.55555555562727.52842094

    42.222222222241434242109

    58.888888888942124421244212442124

    75.555555555642139421394213942139

    93.333333333342155421554215542155

    10042161421614216142161

    10.00%

    100.00%

    PLAZO

    FISICO

    FINANCIERO (Valorizado)

    RE_PROGRAMADO (Contrato)

    Tiempo

    Porcentaje

    Reprog

    LA IGLESIA DEREPROGRAMACIN DE OBRA

    JESUCRISTO

    DE LOS SANTOSDEPARTAMENTO DE ADMINISTRACIN DE PROYECTOSMODELO

    DE LOS LTIMOS DASAREA SUD AMRICA OESTE96 - S - 230E

    Proyecto :RINCONADA520 - 9463 - 76JULIACA

    Contratista :JANSA Contratistas Grles.Fecha Inicio Obra:37781.0

    Residente:Ing.Antonio Lopez YslaPlazo:180

    Supervisor:Ing.Pedro Lavado TafurEntrega Obra:37961.0

    DESCRIPCINFECHAAVANCE PROGRAMADOFECHACOEFICIENTEAVANCE PROGRAMADO PONDERADO

    INICIO15-Jun30-Jun15-Jul31-Jul15-Aug31-Aug15-Sep30-Sep15-Oct31-Oct15-Nov6-DecCONCLUSIN15-Jun30-Jun15-Jul31-Jul15-Aug31-Aug15-Sep30-Sep15-Oct31-Oct15-Nov6-Dec

    1Requisitos GeneralesP9-Jun-033.2%11.9%20.5%29.6%38.2%47.4%56.0%64.6%73.2%82.4%91.0%100.0%30-Nov-030.017800.000580.002110.003640.005270.006810.008440.009970.011500.013030.014670.016200.01780

    2Trazo y ReplanteoP9-Jun-033.3%11.9%20.6%29.8%38.5%47.7%56.3%65.0%73.6%82.9%91.5%100.0%29-Nov-030.002740.000090.000330.000560.000820.001050.001310.001540.001780.002020.002270.002510.00274

    3Excavacin, relleno y nivelacinP9-Jun-0323.2%84.8%100.0%100.0%100.0%100.0%100.0%100.0%100.0%100.0%100.0%100.0%3-Jul-030.024900.005790.021110.024900.024900.024900.024900.024900.024900.024900.024900.024900.02490

    4HormignP29-Jun-030.0%1.4%33.1%66.8%98.5%100.0%100.0%100.0%100.0%100.0%100.0%100.0%15-Aug-030.063660.000000.000900.021050.042550.062710.063660.063660.063660.063660.063660.063660.06366

    5AlbaileraP22-Jul-030.0%0.0%0.0%8.0%22.0%36.8%50.8%64.7%78.6%93.5%100.0%100.0%7-Nov-030.016310.000000.000000.000000.001310.003590.006010.008280.010550.012830.015250.016310.01631

    6MetalesP11-Jul-030.0%0.0%3.6%18.0%31.5%45.9%59.5%73.0%86.5%100.0%100.0%100.0%30-Oct-030.081710.000000.000000.002940.014720.025760.037540.048580.059620.070670.081710.081710.08171

    7Carpintera y ebanisteraP8-Aug-030.0%0.0%0.0%0.0%10.3%33.8%55.9%77.9%100.0%100.0%100.0%100.0%15-Oct-030.035210.000000.000000.000000.000000.003620.011910.019680.027440.035210.035210.035210.03521

    8Techos y aislamientosP27-Aug-030.0%0.0%0.0%0.0%0.0%9.1%43.2%77.3%100.0%100.0%100.0%100.0%10-Oct-030.071510.000000.000000.000000.000000.000000.006500.030880.055260.071510.071510.071510.07151

    9Puertas y ventanasP14-Aug-030.0%0.0%0.0%0.0%1.0%16.7%31.4%46.1%60.8%76.5%91.2%100.0%24-Nov-030.120210.000000.000000.000000.000000.001180.020030.037710.055390.073070.091930.109600.12021

    10RevestimientosP3-Aug-030.0%0.0%0.0%0.0%30.4%72.1%100.0%100.0%100.0%100.0%100.0%100.0%10-Sep-030.010390.000000.000000.000000.000000.003160.007490.010390.010390.010390.010390.010390.01039

    11Mosaico y cermicaP17-Sep-030.0%0.0%0.0%0.0%0.0%0.0%0.0%20.0%43.1%67.7%90.8%100.0%21-Nov-030.039570.000000.000000.000000.000000.000000.000000.000000.007910.017050.026790.035920.03957

    12AcsticosP15-Nov-030.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%100.0%2-Dec-030.043850.000000.000000.000000.000000.000000.000000.000000.000000.000000.000000.000000.04385

    13PisosP9-Aug-030.0%0.0%0.0%0.0%7.3%28.0%47.4%66.8%86.2%100.0%100.0%100.0%25-Oct-030.042020.000000.000000.000000.000000.003080.011770.019910.028060.036200.042020.042020.04202

    14PinturaP31-Oct-030.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%46.7%100.0%1-Dec-030.031680.000000.000000.000000.000000.000000.000000.000000.000000.000000.000000.014810.03168

    15Items especialesP14-Nov-030.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%19.8%100.0%17-Nov-030.051800.000000.000000.000000.000000.000000.000000.000000.000000.000000.000000.010230.05180

    16Instalaciones mecnicasP2-Nov-030.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%100.0%100.0%13-Nov-030.008600.000000.000000.000000.000000.000000.000000.000000.000000.000000.000000.008600.00860

    17PlomeraP5-Jul-030.0%0.0%6.8%18.0%28.6%39.8%50.3%60.9%71.4%82.6%93.2%100.0%24-Nov-030.022400.000000.000000.001520.004040.006400.008910.011270.013630.015990.018510.020870.02240

    18Electricidad, iluminacin y sonidoP5-Jul-030.0%0.0%6.5%17.4%27.5%38.4%48.5%58.7%68.8%79.7%89.8%100.0%30-Nov-030.113030.000000.000000.007400.019650.031130.043380.054860.066340.077820.090070.101550.11303

    19Mobiliario y equipamientoP30-Oct-030.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%3.2%51.6%100.0%30-Nov-030.039250.000000.000000.000000.000000.000000.000000.000000.000000.000000.001270.020260.03925

    20Mejoras en el sitioP15-Jun-030.0%9.8%19.6%30.1%39.9%50.3%60.1%69.9%79.7%90.2%100.0%100.0%15-Nov-030.156780.000000.015370.030740.047140.062510.078900.094280.109650.125020.141410.156780.15678

    21Mejoras fuera de sitioP27-Oct-030.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%21.1%100.0%100.0%15-Nov-030.003390.000000.000000.000000.000000.000000.000000.000000.000000.000000.000710.003390.00339

    22JardineraP5-Oct-030.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%24.4%63.4%100.0%100.0%15-Nov-030.003180.000000.000000.000000.000000.000000.000000.000000.000000.000780.002020.003180.00318

    1.000000.006460.039810.092760.160400.235890.330750.435910.546090.650140.734280.849611.00000

    AVANCE PROGRAMADOP9-Jun-030.6%4.0%9.3%16.0%23.6%33.1%43.6%54.6%65.0%73.4%85.0%100.0%06-Dec-2003

    RELACION DE TIEMPO/PLAZOT/P0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%

    AVANCE IDEALI4.0%14.0%22.0%30.0%39.0%48.0%58.0%68.0%77.0%87.0%97.0%100.0%

    Prog

    LA IGLESIA DEPROGRAMACIN DE OBRA

    JESUCRISTO

    DE LOS SANTOSDEPARTAMENTO DE ADMINISTRACIN DE PROYECTOSMODELO

    DE LOS LTIMOS DASAREA SUD AMRICA OESTE96 - S - 230E

    Proyecto :RINCONADA520 - 9463 - 76JULIACA

    Contratista :JANSA Contratistas Grles.Fecha Inicio Obra:37781.0

    Residente:Ing.Antonio Lopez YslaPlazo:180

    Supervisor:Ing.Pedro Lavado TafurEntrega Obra:37961.0

    DESCRIPCINFECHAAVANCE PROGRAMADOFECHACOEFICIENTEAVANCE PROGRAMADO PONDERADO

    INICIO15-Jun30-Jun15-Jul31-Jul15-Aug31-Aug15-Sep30-Sep15-Oct31-Oct15-Nov6-DecCONCLUSIN15-Jun30-Jun15-Jul31-Jul15-Aug31-Aug15-Sep30-Sep15-Oct31-Oct15-Nov6-Dec

    1Requisitos GeneralesP9-Jun-033.2%11.9%20.5%29.6%38.2%47.4%56.0%64.6%73.2%82.4%91.0%100.0%30-Nov-030.017800.000580.002110.003640.005270.006810.008440.009970.011500.013030.014670.016200.01780

    2Trazo y ReplanteoP9-Jun-033.3%11.9%20.6%29.8%38.5%47.7%56.3%65.0%73.6%82.9%91.5%100.0%29-Nov-030.002740.000090.000330.000560.000820.001050.001310.001540.001780.002020.002270.002510.00274

    3Excavacin, relleno y nivelacinP9-Jun-0323.2%84.8%100.0%100.0%100.0%100.0%100.0%100.0%100.0%100.0%100.0%100.0%3-Jul-030.024900.005790.021110.024900.024900.024900.024900.024900.024900.024900.024900.024900.02490

    4HormignP29-Jun-030.0%1.4%33.1%66.8%98.5%100.0%100.0%100.0%100.0%100.0%100.0%100.0%15-Aug-030.063660.000000.000900.021050.042550.062710.063660.063660.063660.063660.063660.063660.06366

    5AlbaileraP22-Jul-030.0%0.0%0.0%7.5%20.5%34.4%47.4%60.4%73.4%87.3%100.0%100.0%14-Nov-030.016310.000000.000000.000000.001230.003350.005610.007730.009850.011970.014230.016310.01631

    6MetalesP1-Jul-030.0%0.0%12.1%26.2%39.4%53.5%66.7%80.0%93.2%100.0%100.0%100.0%22-Oct-030.081710.000000.000000.009850.021380.032190.043720.054530.065340.076150.081710.081710.08171

    7Carpintera y ebanisteraP27-Jul-030.0%0.0%0.0%5.3%26.9%50.0%71.6%93.2%100.0%100.0%100.0%100.0%4-Oct-030.035210.000000.000000.000000.001860.009470.017590.025210.032820.035210.035210.035210.03521

    8Techos y aislamientosP11-Jul-030.0%0.0%8.3%44.3%78.1%100.0%100.0%100.0%100.0%100.0%100.0%100.0%24-Aug-030.071510.000000.000000.005910.031690.055870.071510.071510.071510.071510.071510.071510.07151

    9Puertas y ventanasP5-Oct-030.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%21.8%57.8%91.6%100.0%18-Nov-030.120210.000000.000000.000000.000000.000000.000000.000000.000000.026190.069530.110160.12021

    10RevestimientosP3-Aug-030.0%0.0%0.0%0.0%30.4%72.1%100.0%100.0%100.0%100.0%100.0%100.0%10-Sep-030.010390.000000.000000.000000.000000.003160.007490.010390.010390.010390.010390.010390.01039

    11Mosaico y cermicaP5-Oct-030.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%20.4%54.2%85.8%100.0%21-Nov-030.039570.000000.000000.000000.000000.000000.000000.000000.000000.008080.021440.033970.03957

    12AcsticosP15-Nov-030.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%100.0%2-Dec-030.043850.000000.000000.000000.000000.000000.000000.000000.000000.000000.000000.000000.04385

    13PisosP9-Aug-030.0%0.0%0.0%0.0%7.3%28.0%47.4%66.8%86.2%100.0%100.0%100.0%25-Oct-030.042020.000000.000000.000000.000000.003080.011770.019910.028060.036200.042020.042020.04202

    14PinturaP31-Oct-030.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%46.7%100.0%1-Dec-030.031680.000000.000000.000000.000000.000000.000000.000000.000000.000000.000000.014810.03168

    15Items especialesP14-Nov-030.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%19.8%100.0%17-Nov-030.051800.000000.000000.000000.000000.000000.000000.000000.000000.000000.000000.010230.05180

    16Instalaciones mecnicasP2-Nov-030.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%100.0%100.0%13-Nov-030.008600.000000.000000.000000.000000.000000.000000.000000.000000.000000.000000.008600.00860

    17PlomeraP5-Jul-030.0%0.0%6.8%18.0%28.6%39.8%50.3%60.9%71.4%82.6%93.2%100.0%24-Nov-030.022400.000000.000000.001520.004040.006400.008910.011270.013630.015990.018510.020870.02240

    18Electricidad, iluminacin y sonidoP5-Jul-030.0%0.0%6.3%16.7%26.5%36.9%46.7%56.5%66.3%76.7%86.5%100.0%5-Dec-030.113030.000000.000000.007120.018920.029970.041760.052820.063870.074920.086720.097770.11303

    19Mobiliario y equipamientoP5-Oct-030.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%28.1%74.7%100.0%100.0%8-Nov-030.039250.000000.000000.000000.000000.000000.000000.000000.000000.011040.029310.039250.03925

    20Mejoras en el sitioP18-Jul-030.0%0.0%0.0%9.9%21.7%34.3%46.1%57.8%69.6%82.2%93.9%100.0%22-Nov-030.156780.000000.000000.000000.015590.034050.053750.072210.090680.109140.128830.147300.15678

    21Mejoras fuera de sitioP17-Nov-030.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%100.0%24-Nov-030.003390.000000.000000.000000.000000.000000.000000.000000.000000.000000.000000.000000.00339

    22JardineraP26-Oct-030.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%15.9%67.0%100.0%24-Nov-030.003180.000000.000000.000000.000000.000000.000000.000000.000000.000000.000510.002130.00318

    1.000000.006460.024440.074560.168250.273000.360420.425650.487990.590400.715400.849511.00000

    AVANCE PROGRAMADOP9-Jun-030.6%2.4%7.5%16.8%27.3%36.0%42.6%48.8%59.0%71.5%85.0%100.0%06-Dec-2003

    RELACION DE TIEMPO/PLAZOT/P0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%0.0%

    AVANCE IDEALI4.0%14.0%22.0%30.0%39.0%48.0%58.0%68.0%77.0%87.0%97.0%100.0%

    Programa

    PROGRAMACIN ORIGINAL DE OBRA

    Proyecto: Capilla "Casa Blanca" N 550-0818-07-76Contratista:EQQUS SA

    IdDescripcinDuracinFecha InicioFecha FinINICIOFIN

    CASA BLANCA180 das9-Jun-035-Dec-03

    CAPILLA180 das9-Jun-035-Dec-03

    INICIO 10 das9-Jun-039-Jun-03

    REQUISITOS GENERALES175 das9-Jun-0330-Nov-03REQUISITOS GENERALES9-Jun-0330-Nov-03

    EXCAVACION EN GRAN SUPERFICIE14 das9-Jun-0322-Jun-03EXCAVACION,RELLENO9-Jun-033-Jul-03

    ELIMINACION DE DESMONTE12 das11-Jun-0322-Jun-03

    TRAZO Y REPLANTEO174 das9-Jun-0329-Nov-03TRAZO Y REPLANTEO9-Jun-0329-Nov-03

    RELLENO Y COMPACTACION CAPILLA6 das23-Jun-0328-Jun-03

    SOLADO CAPILLA3 das29-Jun-031-Jul-03HORMIGON29-Jun-0315-Aug-03

    EXCAVACION CIMIENTO4 das30-Jun-033-Jul-03ALBAILERIA22-Jul-0314-Nov-03

    LOSA/VIGA DE CIMENTACION Y HABILITADO10 das6-Jul-0315-Jul-03

    COLUMNAS15 das16-Jul-0330-Jul-03

    LOSA ESCENARIO y ROSTRUM4 das21-Jul-0324-Jul-03

    SOBRECIMIENTO4 das25-Jul-0328-Jul-03

    MURO DE LADRILLO9 das22-Jul-0330-Jul-03

    VIGA / LOSAS16 das31-Jul-0315-Aug-03

    CISTERNA8 das1-Aug-038-Aug-03

    PICADO DE TARRAJEO EN MUROS6 das3-Aug-038-Aug-03REVESTIMIENTOS3-Aug-0310-Sep-03

    PICADO DE PISO6 das9-Aug-0314-Aug-03

    TARRAJEO MURO/ VIGA Y COLUMNA26 das16-Aug-0310-Sep-03

    METALES ESPECIALES30 das23-Sep-0322-Oct-03METALES1-Jul-0322-Oct-03

    CARPINTERIA METALICA90 das1-Jul-0328-Sep-03

    DESMONTAJE DE COBERTURA EXIST.8 das11-Jul-0318-Jul-03

    PINTADO DE ESTRUCTURA DE COB. EXIST.15 das19-Jul-032-Aug-03

    INSTALACION DE ESTRUCTURA DE COBERTURA14 das3-Aug-0316-Aug-03

    COBERTURA DE CALAMINON45 das11-Jul-0324-Aug-03COBERTURA11-Jul-0324-Aug-03

    CONTRAPISO15 das2-Sep-0316-Sep-03PISOS9-Aug-0325-Oct-03

    ENCHAPE DE CERAMICA EN PISO14 das17-Sep-0330-Sep-03MOSAICO Y CERAMICA5-Oct-0321-Nov-03

    PISO DE PARQUET25 das1-Oct-0325-Oct-03

    ZOCALO DE CERAMICO21 das5-Oct-0325-Oct-03

    TABIQUERIA DRYWALL20 das26-Oct-0314-Nov-03

    ZOCALO DE VINILICO22 das31-Oct-0321-Nov-03

    PINTURA32 das31-Oct-031-Dec-03PINTURA31-Oct-031-Dec-03

    FALSO TECHO AMSTRONG18 das15-Nov-032-Dec-03ACUSTICOS15-Nov-032-Dec-03

    INSTALACIONES ELECTRICAS120 das5-Jul-031-Nov-03INSTALACIONES ELECTRICAS5-Jul-035-Dec-03

    INSTAL. DE ARTEFACTOS ELECTRICOS10 das25-Nov-034-Dec-03

    INSTALACIONES SANITARIAS120 das5-Jul-031-Nov-03INSTALACIONES SANITARIAS5-Jul-0324-Nov-03

    INSTALACIONES MECANICAS12 das2-Nov-0313-Nov-03

    ITEMS ESPECIALES4 das14-Nov-0317-Nov-03ITEMS ESPECIALES14-Nov-0317-Nov-03

    INST. APARATOS SANITARIOS7 das18-Nov-0324-Nov-03

    INST. SONIDO8 das28-Nov-035-Dec-03

    CARPINTERIA Y EBANISTERIA70 das27-Jul-034-Oct-03CARPINTERIA Y EBANISTERIA27-Jul-034-Oct-03

    INST. DE PUERTAS Y VENTANAS30 das5-Oct-033-Nov-03PUERTAS Y VENTANAS5-Oct-0318-Nov-03

    CERRAJERIA15 das4-Nov-0318-Nov-03

    MOBILIARIO Y EQUIPAMIENTO35 das5-Oct-038-Nov-03MOBILIARIO Y EQUIPAMIENTO5-Oct-038-Nov-03

    EXTERIOR A LA CAPILLA130 das18-Jul-0324-Nov-03

    CORTE MASIVO A MAQUINA10 das18-Jul-0327-Jul-03MEJORAS EN EL SITIO18-Jul-0322-Nov-03

    DEMOL. CIMIENTO MURO DE CERCO12 das18-Jul-0329-Jul-03

    ELIMINACION DE EXCEDENTE12 das18-Jul-0329-Jul-03

    EXCAVACION DE ZANJA DE CERCO42 das2-Aug-0312-Sep-03

    CALZADURA20 das2-Aug-0321-Aug-03

    ELIMINACION DE EXCEDENTE42 das2-Aug-0312-Sep-03

    PICADO DE CIMIENTO P/ ANCLAJE DE COLUM.7 das2-Aug-038-Aug-03

    DEMOLICION DE VIGA EXISTENTE6 das9-Aug-0314-Aug-03

    CIMIENTO /ZAPATA15 das31-Aug-0314-Sep-03

    SOBRECIMIENTO20 das8-Sep-0327-Sep-03

    MURO DE LADRILLO18 das15-Sep-032-Oct-03

    COLUMNA C/MOLDURA25 das20-Sep-0314-Oct-03

    VIGA14 das25-Sep-038-Oct-03

    REVESTIMIENTO19 das9-Oct-0327-Oct-03

    REJAS DE CERCO20 das21-Oct-039-Nov-03

    PINTURA EXTERIOR13 das10-Nov-0322-Nov-03

    CASETA CUSTODIO35 das10-Sep-0314-Oct-03

    RELLENO Y COMPACTACION8 das28-Sep-035-Oct-03

    JARDINERA DE CONCRETO8 das6-Oct-0313-Oct-03

    LOSA Y VEREDAS14 das14-Oct-0327-Oct-03

    CANAL DE CONCRETO11 das19-Oct-0329-Oct-03

    LOSA DE ESTACIONAMIENTO18 das30-Oct-0316-Nov-03

    VEREDA (Fuera de Sitio)8 das17-Nov-0324-Nov-03MEJORAS FUERA DE SITIO17-Nov-0324-Nov-03

    JARDINERIA30 das26-Oct-0324-Nov-03JARDINES26-Oct-0324-Nov-03

    FIN0 das5-Dec-035-Dec-03

    &R&P/&N

    Ponde

    PARTIDAPARCIALParcial+GG+UUIncidencia

    10.5%

    Requisitos Generales26,500.0029,282.500.018

    0.000.000.018

    Trazo y Replanteo4,075.744,503.690.003

    0.003

    Excavacin, relleno y nivelacin37,062.4240,953.970.025

    0.000.025

    Hormign94,763.32104,713.470.064

    0.000.064

    Albailera24,279.1626,828.470.016

    0.000.016

    Metales121,624.67134,395.260.082

    0.000.082

    Carpintera y ebanistera52,410.3457,913.420.035

    0.000.035

    Techos y aislamientos106,445.95117,622.770.072

    0.000.072

    Puertas y ventanas178,936.26197,724.570.120

    0.000.120

    Revestimientos15,462.9317,086.530.010

    0.010

    Mosaico y cermica58,908.2165,093.570.040

    0.040

    Acsticos65,267.3072,120.360.044

    0.044

    Pisos62,540.8269,107.610.042

    0.042

    Pintura47,163.5052,115.660.032

    0.000.032

    Items especiales77,104.9385,200.950.052

    0.052

    Instalaciones mecnicas12,805.8614,150.480.009

    0.000.009

    Plomera33,339.5236,840.170.022

    0.000.022

    Electricidad, iluminacin y sonido168,250.33185,916.610.113

    0.113

    Mobiliario y equipamiento58,430.7564,565.980.039

    0.000.039

    Mejoras en el sitio233,378.34257,883.060.157

    0.157

    Mejoras fuera de sitio5,040.995,570.290.003

    0.000.003

    Jardinera4,740.725,238.500.003

    0.000.003

    TOTAL1,488,532.031,644,827.892.000

    30,978.51

    131,646.73

    162,625.24

    Hoja1

  • 2.- PERSONAL Y EQUIPO EN OBRA:

    NDESCRIPCINESPECIFICACIN1Empresa INOFUENTE CONTRATISTAS SRL(Trabajadores que tienen que estar en planilla)01 Residente : Seguridad01 Maestro + 01 Almacenero+ 01 Guardin Nocturno = 04 PLANTAOPERARIOS , CIVILES 01, ELECTRICO 01, Sanitario 01, ESTRUCTURAS DRYWALL 02, Estructuras Cobertura 02OFICIALES CIVILES 01, DRYWALL 02 PEONES 204 PLANTA + 14 PERSONAL = 16 TOTAL2SubcontratistasINSTALACIONES SANITARIAS Y ELECTRICAS, DRYWALL3Equiposdel contratistaHerramientas manuales, martillo,

  • 3.- TRABAJOS EN OFICINA

    NDESCRIPCINESPECIFICACIN.OFICINA

    Requisitos Generales Oficinas, Almacenes 85% Trazo y Replanteo Preliminar y Durante la Obra 80%Concreto Simple Solado 100%, Concreto Armado Losa aligerada 100% , SS HHMuros y Tabiques Albailera Muros cabeza y Soga 95%, Muros drywall 80% Estructuras Metlicas Drywall Tijerales 100%, Viguetas 100%, Acabado pintura , Sujecin de Lana de Vidrio, Techos y coberturas 80%, Instalaciones Elctrica Redes Elctricas 50% y Canalizacin Instalaciones Sanitarias Tendido de Redes 50%

  • 4.- CONTROL DE CALIDAD.-

    NPRUEBASRESULTADO7.-Control de humedad en MUROS Y MADERACONTROL DE HUMEDADCONTROL DE HUMEDAD DE LA MADERA EN OBRA8.- Calidad de desempeo del personal: CHARLAS DE SEGURIDAD.PLAN DE SEGURIDAD, CHARLAS DE ACUERDO A UN CRONOGRAMA ESTABLECIDO.SE ESTABLECE CHARLAS DIARIAS Y UNA MAS PROLONGADA UNA VEZ POR SEMANA

  • VISITA DE PRESIDENTE DE MISION Y ELDERES

  • VISITA DE PRESIDENTE DE MISION Y ELDERES

  • VISTA DE INETRIOR DE OFICINAS

  • MEDICION DE POZO A TIERRA EXISTENTE

  • ENCHAPE DE PISO CON PORCELANATO

  • PRUEBAS DE PRESION ..SS.HH

  • INICIO DE COLOCACION DE COBERTURA- TERMOTECHO

  • VISTA DE COLOCACION DE COBERTURA - TERMOTECHO

  • VISTA FRONTAL DE OFICINAL

  • VISTA FRONTAL DE OFICINAS

    *****