INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N° 4 N° 012119052014-CHR04-LAAM-0 VERSION FINAL CÓDIGO: R-OPE-05/REV.0 REVISIÓN: 0 FECHA: 12-06-2017 PÁGINA Página 1 de 12 INFORME AUDITORIA TECNICA N°012119052014-CHR04-LAAM-0 VERSION FINAL INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N° 04 PROYECTO “NUEVA LINEA 2x220 kV LO AGUIRRE - ALTO MELIPILLA, CON UN CIRCUITO TENDIDO” CLIENTE: COODINADOR ELECTRICO NACIONAL EMITIDO POR REVISADO APROBADO JRR/AFR AGV PVV 12-06-2017 12-06-2017 12-06-2017

Upload: others

Post on 13-Jul-2020

12 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: INFORME DE CUMPLIMIENTO DE HITO RELEVANTE …...VERSION INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N 4 N 012119052014-CHR04-LAAM-0 FINAL CÓDIGO: R-OPE-05/REV.0 REVISIÓN: 0 FECHA:

INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N° 4

N° 012119052014-CHR04-LAAM-0 VERSION FINAL

CÓDIGO: R-OPE-05/REV.0

REVISIÓN: 0

FECHA: 12-06-2017

PÁGINA Página 1 de 12

INFORME AUDITORIA TECNICA N°012119052014-CHR04-LAAM-0

VERSION FINAL

INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N° 04

PROYECTO “NUEVA LINEA 2x220 kV LO AGUIRRE - ALTO MELIPILLA, CON UN CIRCUITO TENDIDO”

CLIENTE: COODINADOR ELECTRICO NACIONAL

EMITIDO POR REVISADO APROBADO

JRR/AFR AGV PVV

12-06-2017 12-06-2017 12-06-2017

Page 2: INFORME DE CUMPLIMIENTO DE HITO RELEVANTE …...VERSION INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N 4 N 012119052014-CHR04-LAAM-0 FINAL CÓDIGO: R-OPE-05/REV.0 REVISIÓN: 0 FECHA:

INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N° 4

N° 012119052014-CHR04-LAAM-0 VERSION FINAL

CÓDIGO: R-OPE-05/REV.0

REVISIÓN: 0

FECHA: 12-06-2017

PÁGINA Página 2 de 12

1. OBJETIVO

El presente documento tiene por objetivo informar las actividades de evaluación de conformidad

realizadas por el equipo auditor conducentes a constatar el cumplimiento del Hito Relevante N° 4,

contemplado en la carta Gantt presentada por la empresa ELETRANS II S.A. en su oferta técnica y de las

obligaciones emanadas del decreto de adjudicación para el proyecto “Nueva Línea 2x220 kV Lo Aguirre -

Alto Melipilla, con un Circuito Tendido”.

2. ALCANCE

El alcance del presente informe corresponde a constatar el cumplimiento del Hito Relevante N°4 del

proyecto “Nueva Línea 2x220 kV Lo Aguirre - Alto Melipilla, con un Circuito Tendido”, indicado en la carta

Gantt denominada “Documento 14: Cronograma Proyecto “Nueva Línea 2x220 kV Lo Aguirre - Alto

Melipilla, con un Circuito Tendido Rev 2”, presentada por la empresa ELETRANS II S.A. en su oferta técnica.

3. REFERENCIAS

Decreto Supremo N° 6T, “Fija empresa adjudicataria de los derechos de explotación y ej. Melipilla-

Rapel y Nueva Línea 2X220 kV Lo Aguirre-A. Melipilla, con un circuito tendido, en el Sistema de

Transmisión Troncal del Sistema Interconectado Central”, emitido el 9 de septiembre de 2013 por el

Ministerio de Energía y publicado el 16 de octubre de 2013 en el Diario Oficial de la República de Chile.

Resolución Exenta N°36 del 22 de enero de 2013, emitida por la Comisión Nacional de Energía.

Referencia: Modifica Resolución Exenta N° 277 de la Comisión Nacional de Energía, de fecha 30 de

abril de 2012, que Aprueba Bases de Licitación de las Obras Nuevas contempladas en el Decreto

Exento N°82 de 2012 que fija el Plan de Expansión Troncal para los doce meses siguientes y fija su

texto refundido.

Bases de Licitación para la adjudicación de las Auditorías Técnicas de los Proyectos “Nueva Línea 1x220

kV A. Melipilla – Rapel”, “Nueva Línea 2x220 kV Lo Aguirre – Alto Melipilla, con un Circuito Tendido”, y

“Segundo Transformador Ancoa 500/220 kV”, en el Sistema de Transmisión Troncal del Sistema

Interconectado Central (SIC) / 14-04-2014.

Circular Aclaratoria N°1 de la Licitación de Auditorías Técnicas para las Obras Nuevas contempladas en

el Decreto Exento N°82 de 2012 del Ministerio de Energía, emitida el 08 de mayo de 2014.

Circular Aclaratoria N°2 de la Licitación de Auditorías Técnicas para las Obras Nuevas contempladas en

el Decreto Exento N°82 de 2012 del Ministerio de Energía, emitida el 13 de mayo de 2014.

Documento 14: Cronograma Proyecto “Nueva Línea 1x220 kV Alto Melipilla - Rapel Rev 2”, adjunto por

la empresa ELETRANS II S.A. en su carta ST2 EEN/024 2015 del 19 de octubre de 2015, dirigida a Ancare

Energy.

Carta ST2 EEN/024 2015 del 19.10.2015, emitida por Eletrans II S.A., dirigida a Ancare Energy, que

incluye programa identificado como “Documento 14: Cronograma Proyecto “Nueva Línea 1x220 kV

Alto Melipilla - Rapel Rev 2”.

Page 3: INFORME DE CUMPLIMIENTO DE HITO RELEVANTE …...VERSION INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N 4 N 012119052014-CHR04-LAAM-0 FINAL CÓDIGO: R-OPE-05/REV.0 REVISIÓN: 0 FECHA:

INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N° 4

N° 012119052014-CHR04-LAAM-0 VERSION FINAL

CÓDIGO: R-OPE-05/REV.0

REVISIÓN: 0

FECHA: 12-06-2017

PÁGINA Página 3 de 12

Correo electrónico emitido por Acare Energy SpA el 06.10.2016 y dirigido a Eletrans II S.A. el cual

adjunta “Minuta N°1 AMRA – LAAM: Hito N°4”. Comentarios de Ancare Energy a protocolos de

pruebas FAT para Cumplimiento de Hito Relevante N°4.

Carta ST2 EEN012 2016 emitida por Eletrans II S.A. el 03.11.2016 y dirigida a Ancare Energy SpA, cuya

referencia indica “Proyectos “Nueva Línea 2x220 kV Lo Aguirre – Alto Melipilla, con un circuito

tendido” y “Nueva Línea 1x220 kV Alto Melipilla – Rapel”. Responde Minuta N°1 AMRA-LAAM: Hito

N°4.

Carta CO64322112016 emitida por Ancare Energy SpA el 22.11.2016 y dirigida a Eletrans II S.A., cuya

referencia indica “Proyectos “Nueva Línea 2x220 kV Lo Aguirre – Alto Melipilla, con un circuito

tendido” y “Nueva Línea 1x220 kV Alto Melipilla – Rapel”. Minuta N°2 AMRA – LAAM: Hito N°4,

Comentarios Protocolos Pruebas FAT Rev.1”

Carta ST2 EEN013 2016 emitida por Eletrans II S.A. el 14.12.2016 y dirigida a Ancare Energy SpA, cuya

referencia indica “Proyectos “Nueva Línea 2x220 kV Lo Aguirre – Alto Melipilla, con un circuito

tendido” y “Nueva Línea 1x220 kV Alto Melipilla – Rapel”. Minuta N°2 AMRA – LAAM: Hito N°4,

Comentarios Protocolos Pruebas FAT Rev.1”.

Carta ST2 EEN014 2016 emitida por Eletrans II S.A. el 28.12.2016 y dirigida a Ancare Energy SpA, cuya

referencia indica “Proyectos “Nueva Línea 2x220 kV Lo Aguirre – Alto Melipilla, con un circuito

tendido” y “Nueva Línea 1x220 kV Alto Melipilla – Rapel”. Solicita aclaración respecto de los

antecedentes presentados mediante carta ST2 EEN013 2016”.

Carta CO75706032017 emitida por Ancare Energy SpA el 06.03.2017 y dirigida a Eletrans II S.A., cuya

referencia indica “Proyectos “Nueva Línea 2x220 kV Lo Aguirre – Alto Melipilla, con un circuito

tendido” y “Nueva Línea 1x220 kV Alto Melipilla – Rapel”. Minuta N°3 AMRA – LAAM: Hito N°4,

Comentarios Protocolos Pruebas FAT Rev. 2”.

Carta ST2 EEN001 2017 emitida por Eletrans II S.A. el 07.04.2017 y dirigida a Ancare Energy SpA, cuya

referencia indica “Proyectos “Nueva Línea 2x220 kV Lo Aguirre – Alto Melipilla, con un circuito

tendido” y “Nueva Línea 1x220 kV Alto Melipilla – Rapel””. Envía antecedentes con respuesta a Minuta

N°3 “Comentarios de Ancare Energy a protocolos de pruebas FAT Rev.2 para Cumplimiento de Hito

Relevante N°4”.

Carta ST2 EEN002 2017 emitida por Eletrans II S.A. el 11.04.2017 y dirigida a Ancare Energy SpA, cuya

referencia indica “Proyectos “Nueva Línea 2x220 kV Lo Aguirre – Alto Melipilla, con un circuito

tendido” y “Nueva Línea 1x220 kV Alto Melipilla – Rapel””. Envía Antecedentes Complementarios a

Minuta N°3

Carta CO80627042017 emitida por Ancare Energy SpA el 27.04.2017 y dirigida a Eletrans II S.A., cuya

referencia indica “Proyectos “Nueva Línea 2x220 kV Lo Aguirre – Alto Melipilla, con un circuito

tendido” y “Nueva Línea 1x220 kV Alto Melipilla – Rapel”. Minuta N°4 AMRA – LAAM: Hito N°4,

Comentarios Protocolos Pruebas FAT Rev. 3”.

Carta GG-EII0038/2017 emitida por Eletrans II S.A. el 27.04.2017 y dirigida al Coordinador Eléctrico

Nacional, cuya referencia indica “Solicita aprobación del Hito Relevante N°4 “Prueba de Equipos” en

Proyectos “Nueva Línea 2x220 kV Lo Aguirre – Alto Melipilla, con un circuito tendido” y “Nueva Línea

1x220 kV Alto Melipilla – Rapel”. Hace entrega de antecedentes que dan cumplimiento del Hito

Relevante N°4.

Page 4: INFORME DE CUMPLIMIENTO DE HITO RELEVANTE …...VERSION INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N 4 N 012119052014-CHR04-LAAM-0 FINAL CÓDIGO: R-OPE-05/REV.0 REVISIÓN: 0 FECHA:

INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N° 4

N° 012119052014-CHR04-LAAM-0 VERSION FINAL

CÓDIGO: R-OPE-05/REV.0

REVISIÓN: 0

FECHA: 12-06-2017

PÁGINA Página 4 de 12

Carta N° DE 01929 - del 05 de mayo de 2017, emitida por el Coordinador Eléctrico Nacional y dirigida a

Ancare Energy, cuya referencia indica: Obras Nuevas contempladas en el Decreto Exento N°82 de

2012, del Ministerio de Energía. Informe de Cumplimiento Hito Relevante N°4.

4. DEFINICIONES

No Aplica

5. DESARROLLO DEL INFORME

5.1. Requerimientos establecidos:

De acuerdo a lo indicado en las Bases de Licitación para la Adjudicación de las Auditorías Técnicas de los

Proyectos “Nueva Línea 1x220 kV A. Melipilla – Rapel”, “Nueva Línea 2x220 kV Lo Aguirre – Alto Melipilla,

con un Circuito Tendido”, y “Segundo Transformador Ancoa 500/220 kV”, en el Sistema de Transmisión

Troncal del Sistema Interconectado Central (SIC) / 14-04-2014, y sus Circulares Aclaratorias N°1 y N°2, el

Hito Relevante N°4 establecido para el proyecto “Nueva Línea 2x220 kV Lo Aguirre - Alto Melipilla, con un

Circuito Tendido”, queda cumplido una vez que el Auditor del Proyecto verifique que las aprobaciones del

Adjudicatario del Proyecto a las pruebas en fábrica, protocolos e informes, se han realizado de manera

adecuada para garantizar la calidad de cada suministro. Esta verificación se realiza de acuerdo a lo

estipulado en el numeral 4.5.5 “Pruebas en Fábrica para Equipos y Elementos” de las mencionadas Bases

de Licitación.

Adicionalmente el Decreto Supremo N° 6T, indica “Este hito deberá cumplirse dentro de los 731 días

corridos siguientes, contados desde la publicación del presente Decreto de Adjudicación en el Diario

Oficial”.

5.2. Consideraciones para realizar la verificación de los documentos de cumplimento del Hito N°4

De acuerdo al Decreto Supremo N° 6T, emitido el 9 de Septiembre de 2013 por el Ministerio de Energía y a

las Bases de Licitación para la adjudicación de las Auditorías Técnicas de los Proyectos mencionados, se

comprueba el cumplimiento del Hito mediante la aprobación por parte del Auditor del Proyecto, de los

informes de los ensayos de los equipos, para lo cual definirá los tipos y cantidad de ensayos, sus normas y

laboratorios a considerar, así como la cantidad y equipos a ensayar de acuerdo a las características y

envergadura de cada uno de los proyectos.

• Equipos a ensayar en fábrica.

El equipo auditor considera que los equipos que deben ser sometidos a pruebas FAT son los siguientes

equipos de 220 kV adquiridos para el Proyecto “Nueva Línea 2x220 kV Lo Aguirre - Alto Melipilla, con un

Circuito Tendido”:

Page 5: INFORME DE CUMPLIMIENTO DE HITO RELEVANTE …...VERSION INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N 4 N 012119052014-CHR04-LAAM-0 FINAL CÓDIGO: R-OPE-05/REV.0 REVISIÓN: 0 FECHA:

INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N° 4

N° 012119052014-CHR04-LAAM-0 VERSION FINAL

CÓDIGO: R-OPE-05/REV.0

REVISIÓN: 0

FECHA: 12-06-2017

PÁGINA Página 5 de 12

A. Subestación Alto Melipilla:

o Una (1) Celda de 245 kV, aislada en gas SF6 (GIS) para paño de línea, fabricados por ABB (Suiza). N° de serie: 1HC500026491 (Celda 1100).

o Tres (3) pararrayos tipo EXLIM P192-GV245M, fabricados por ABB (Suecia). N° de serie: 75248157 a 75248159.

o Tres (3) transformadores de tensión capacitivos tipo CPB 245, fabricados por ABB (Suecia). N° de serie: 8850618 a 8850620.

o Una (1) trampas de onda tipo DLTC 2000/0.2 – 50 kA Standard, fabricadas por ABB (Suiza). N° de serie: HE575817/0.

B. Subestación Lo Aguirre

o Tres (3) Celdas de 245 kV, aisladas en gas SF6 (GIS), con interruptor, para paño de línea, fabricados por ALSTOM GRID (China). N° de serie: AN81 (Celda 01); AN81 (Celda 016), y AN81 (Celda 018). Además dos (2) Celdas de 245 kV, aisladas en gas SF6 (GIS), sin interruptor, para conexión “Tee Point” a líneas S/E Alto Melipilla. N° de serie: AN81 (Celda 02), y AN81 (Celda 017)

o Tres (3) pararrayos tipo SB 192/20.4-1, fabricados por TRIDELTA Überspannungsableiter GmbH (Alemania). N° de serie: 221499 – 221500 – 221501.

o Tres (3) trampas de onda tipo DLTC 2000/0.2 – 50 kA Standard, fabricadas por ABB (Suiza). N° de serie: HE575821/0; HE575822, y HE575823/0.

o Un (1) Condensador de acoplamiento tipo CCB 245, fabricada por ABB (Suecia). N° de serie 1HSE 8863998.

• Ensayos y normas.

El equipo auditor considera que, para dar cumplimiento a las exigencias y requisitos establecidos en la

normativa aplicable de acuerdo al proceso de licitación, y en particular los requerimientos de calidad y

seguridad estipulados en la Norma Técnica de Seguridad y Calidad de Servicio, las pruebas necesarias

requeridas para el cumplimiento del Hito N°4 son las Pruebas de Rutina definidas por las normas IEC

que aplican a cada equipo, además de todas las pruebas adicionales que se hayan definido en las

Especificaciones Técnicas como parte de las pruebas de rutina. El equipo auditor también considera

aplicables otras normas internacionales que complementan las ofrecidas, como la IEEE/ANSI, ASTM,

DIN/VDE, etc.

No se incluyen como pruebas FAT las pruebas tipo, por tratarse de pruebas de diseño, las que no se

ejecutan como parte de las pruebas de control de calidad realizadas al término de la fabricación de los

equipos adquiridos para estos proyectos (pruebas de rutina). No obstante lo anterior, la verificación de

los protocolos de las pruebas tipo, en particular las que tienen relación con la calificación sísmica de

los equipos, forman parte de las tareas desarrolladas por el equipo auditor en las etapas de ingeniería

y adquisición de los proyectos.

Page 6: INFORME DE CUMPLIMIENTO DE HITO RELEVANTE …...VERSION INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N 4 N 012119052014-CHR04-LAAM-0 FINAL CÓDIGO: R-OPE-05/REV.0 REVISIÓN: 0 FECHA:

INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N° 4

N° 012119052014-CHR04-LAAM-0 VERSION FINAL

CÓDIGO: R-OPE-05/REV.0

REVISIÓN: 0

FECHA: 12-06-2017

PÁGINA Página 6 de 12

Según las siguientes Especificaciones Técnicas elaboradas por ELETRANS II y acordadas con el

Proveedor ABB las pruebas requeridas para los equipos son las estipuladas en las siguientes normas:

A. Subestación Alto Melipilla:

o Doc. ST2-AMRA-S6-E-ET-001 Esp. Técnica Equipo GIS 220 kV. S/E Nueva Alto Melipilla.

IEC-62271-1: High-voltage switchgear and controlgear - Part 1: Common specifications.

IEC-62271-100: High-voltage switchgear and controlgear – Part 100: High-voltage alternating-current circuit-breakers.

IEC-62271-102: High-voltage switchgear and controlgear –. Part 102: Alternating current disconnectors.

IEC-62271-203: High-Voltage Switchgear and Controlgear, Part 203: Gas-Insulated

o Doc. ST2-AMRA-S6-E-ET-003 Esp. Técnica Pararrayos 220 kV. S/E Nueva Alto Melipilla

IEC-62155: Hollow Pressurized and Unpressurized Ceramic and Glass Insulators for Use in Electrical Equipment with Rated Voltages Greater than 1.000V.

IEC-60099-4: Surge Arresters – Part 4: Metal Oxide Surge Arresters Without Gaps for AC Systems

IEC-60815: Guide for the Selection of Insultors in Respect of Polluted Conditions

o Doc. ST2-AMRA-S6-E-ET-002 Esp. Técnica Transformador de potencial capacitivo 220 kV. S/E Nueva Alto Melipilla.

IEC-61869-5: Instrument transformers - Part 5: Additional requirements for capacitor voltage transformers

o Doc. ST2-AMRA-S6-E-ET-003-L001-00 Esp. Técnica Trampa de Onda. S/E Nueva Alto Melipilla

IEC-60353: Line traps for a.c. power systems

B. Subestación Lo Aguirre:

o Doc. ST2-LAAM-S5-E-ET-002 Validación Técnica GIS 220 kV y Ductos (Data sheet). S/E Lo Aguirre

IEC-62271-1: High-voltage switchgear and controlgear - Part 1: Common specifications.

IEC-62271-100: High-voltage switchgear and controlgear – Part 100: High-voltage alternating-current circuit-breakers.

IEC-62271-102: High-voltage switchgear and controlgear –. Part 102: Alternating current disconnectors.

IEC-62271-203: High-Voltage Switchgear and Controlgear, Part 203: Gas-Insulated

o Doc. ST2-LAAM-S5-E-ET-005 Esp. Técnica Pararrayos 220 kV. S/E Lo Aguirre

IEC-62155: Hollow Pressurized and Unpressurized Ceramic and Glass Insulators for Use in Electrical Equipment with Rated Voltages Greater than 1.000V.

IEC-60099-4: Surge Arresters – Part 4: Metal Oxide Surge Arresters Without Gaps for AC Systems

IEC-60815: Guide for the Selection of Insultors in Respect of Polluted Conditions

o Doc. 1KCL2000D203. Rev.0 del 13.02.2015. Esp. Técnica Trampa de Onda. S/E Lo Aguirre

IEC-60353: Line traps for a.c. power systems.

Page 7: INFORME DE CUMPLIMIENTO DE HITO RELEVANTE …...VERSION INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N 4 N 012119052014-CHR04-LAAM-0 FINAL CÓDIGO: R-OPE-05/REV.0 REVISIÓN: 0 FECHA:

INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N° 4

N° 012119052014-CHR04-LAAM-0 VERSION FINAL

CÓDIGO: R-OPE-05/REV.0

REVISIÓN: 0

FECHA: 12-06-2017

PÁGINA Página 7 de 12

o Doc. 1KCL200021D207. Rev.0 de oct/16. Esp. Técnica Condensador de acoplamiento 220 kV. S/E Lo

Aguirre

IEC-60358: Coupling Capacitors and Capacitors Dividers

IEC-60815: Guide for the Selection of Insultors in Respect of Polluted Conditions

IEC-62155: Hollow Pressurized and Unpressurized Ceramic and Glass Insulators for Use in Electrical Equipment with Rated Voltages Greater than 1.000V

ANSI C93.1: Power – Line Carrier Coupling Capacitors and Coupling Capacitors Voltage Transformers

• Laboratorios.

El equipo auditor, de acuerdo a la información recibida y a su mejor conocimiento del o los

laboratorios en que se efectuaron las pruebas FAT, considera acreditados todos los laboratorios de

pruebas de las fábricas proveedoras de los equipos adquiridos por ELETRANS II para el Proyecto.

• Cantidad de equipos.

El equipo auditor considera deben ser probados la totalidad de los equipos de 220 kV adquiridos para

el Proyecto y cuya lista se indica en la carta GG-EII0038/2017 del Adjudicatario.

• Protocolos de pruebas FAT

De acuerdo a lo establecido en la Serie de Preguntas y Respuestas N°1 de la licitación de la auditoría,

será “responsabilidad del equipo auditor verificar que las aprobaciones del Adjudicatario del Proyecto

a las pruebas en fábrica, protocolos e informes, se han realizado de manera adecuada para garantizar

la calidad de los suministros”.

5.3. Antecedentes verificados:

La empresa ELETRANS II S.A. a través de carta N° GG-EII0038/2017 emitida el 27 de abril de 2017, entregó al

Coordinador Eléctrico Nacional, con copia a Ancare Energy Ltda., los reportes de pruebas FAT (en versión 0) de

los equipos del Proyecto, dando por cumplido el Hito Relevante N°4.

El equipo auditor hace notar que los protocolos verificados en este informe habían sido enviados por el

Adjudicatario con anterioridad, en versiones preliminares, mediante cartas ST2-EEN007/2016 de fecha

01.08.2016; ST2-EEN012/2016 de fecha 03.11.2016; ST2-EEN013/2016 de fecha 14.12.2016; ST2-EEN014/2016

de fecha 28.12.2016; ST2-EEN001/2017 de fecha 07.04.2017, y ST2-EEN002/2017 de fecha 11.04.2017. Estos

envíos preliminares fueron revisados por el equipo auditor y comentados a través de las siguientes minutas de

Ancare Energy: Minuta N°1 AMRA-LAAM Hito N°4 de fecha 22.09.2016; Minuta N°2 AMRA-LAAM Hito N°4 de

fecha 21.11.2016; Minuta N°3 AMRA-LAAM Hito N°4 de fecha 03.03.2017, y Minuta N°4 AMRA-LAAM Hito N°4

de fecha 20.04.2017. Estas minutas se adjuntan como anexos al presente informe.

Page 8: INFORME DE CUMPLIMIENTO DE HITO RELEVANTE …...VERSION INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N 4 N 012119052014-CHR04-LAAM-0 FINAL CÓDIGO: R-OPE-05/REV.0 REVISIÓN: 0 FECHA:

INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N° 4

N° 012119052014-CHR04-LAAM-0 VERSION FINAL

CÓDIGO: R-OPE-05/REV.0

REVISIÓN: 0

FECHA: 12-06-2017

PÁGINA Página 8 de 12

Los protocolos finales recibidos con carta N° GG-EII0038/2017, y verificados por el equipo auditor, son los

siguientes:

A. Subestación Alto Melipilla

5.3.1. Subestación encapsulada GIS

5.3.1. Celdas 245 kV GIS, (unidades ensambladas)

Equipo : Celdas 245 kV GIS para paños de línea.

Fabricante : ABB (Suiza)

Tipo : ELK 14/245s

Cantidad : 1

N° de serie : 1HC500026491

Pruebas : De rutina según IEC 62271 – 100, IEC 62271 – 102 e IEC 62271 – 203.

Protocolos N° : 1HC500026491 (Celda 11001) de fecha 21.07.2015. Paño de línea.

Además los siguientes diez (10) Protocolos de las pruebas de rutina efectuadas a los

mecanismos de operación tipo HMB-3.7s de la totalidad de las celdas de la S/E Alto Melipilla.

Dado que se desconoce la relación biunívoca con las celdas, se incluyen los mecanismos de

los demás paños de línea a la S/E Alto Melipilla:

210003576337/1 - 210003576337/2 - 210003576337/3 - 210003576342/1 - 210003576342/2

- 210003576342/3 - 210003576343/1 - 210003576343/2 - 210003576343/3 y

210003576344/1.

5.3.2 Equipos 245 kV GIS, (unidades componentes de la celda)

5.3.2.1 Transformadores de corriente 245 kV GIS

Equipo : Transformadores de corriente 245 kV GIS para paño de línea.

Fabricante : PFIFFNER (Suiza)

Tipo : JK ELK CN14-840 y JK ELK CN14s

Cantidad : 3 unidades

N° de serie : S/N° - Pedido 17214 (Komm N° 2014.3628.01)

Pruebas : Rutina según IEC 61869 – 2

Protocolo N° : 1544836-PP-2014-3628-01-0-0

5.3.2.2 Bushings 245 kV GIS

Equipo : Bushings 245 kV, gas SF6 – aire, para las celdas GIS.

Fabricante : LAPP Insulators GmbH (Alemania)

Tipo : ELK-HB14/245-1050-8370

Cantidad : 3 unidades

N° de serie : 14KI-0289A; 14KI-0289B, y 14KI-0290ª.

Pruebas : Rutina según IEC 62271 – 203

Protocolo N° : DK.51.00.58.011

Page 9: INFORME DE CUMPLIMIENTO DE HITO RELEVANTE …...VERSION INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N 4 N 012119052014-CHR04-LAAM-0 FINAL CÓDIGO: R-OPE-05/REV.0 REVISIÓN: 0 FECHA:

INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N° 4

N° 012119052014-CHR04-LAAM-0 VERSION FINAL

CÓDIGO: R-OPE-05/REV.0

REVISIÓN: 0

FECHA: 12-06-2017

PÁGINA Página 9 de 12

5.3.3 Pararrayos de 220 kV, para exterior

Equipo : Pararrayos 220 kV

Fabricante : ABB (Suecia)

Tipo : EXLIM P192-GV245M

Cantidad : 3

N° de serie : 75248157 a 75248159

Pruebas : Rutina según IEC 60099 – 4

Protocolo N° : S/N° - Pedido A90001541-10 de fecha 20.10.2015

- Doc. HSA802 080-01 (Summary of Routine tests 13Q1960269_30 (A))

- Doc. Sseluv-p0016102406570 con Certificados de Conformidad, Ref. A90001541 y A90001542

de fecha 24.10.2016

5.3.4 Transformadores de potencial capacitivo, para exterior

Equipo : Transformador de tensión capacitivo 220 kV

Fabricante : ABB (Suecia)

Tipo : CPB 245

Cantidad : 3

N° de serie : 8850618 a 8850620

Pruebas : Rutina según IEC 61689 – 5

Protocolo N° : S/N° - Pedido N°E81000422-10 de fecha 07.09.2015

5.3.5 Trampas de onda

Equipo : Trampa de onda 220 kV

Fabricante : ABB (Suiza)

Tipo : DLTC 2000/0,2 - 50kA

Cantidad : 1

N° de serie : HE575817

Pruebas : Rutina según IEC 60353

Protocolo N° : S/N° - Pedido 600729 de fechas 20 a 22.04.2016

B. Subestación Lo Aguirre:

5.3.6 Subestación encapsulada GIS

5.3.6. Celdas 245 kV GIS, (unidades ensambladas)

Equipo : Celdas 245 kV GIS para paños de línea, y para conexión a instalación existente.

Fabricante : ALSTOM GRID (China)

Tipo : B105

Cantidad : 3 celdas con interruptor y 2 celdas de conexión “Tee Point”

N° de serie : AN81 (Celda 01); AN81 (Celda 016), y AN81 (Celda 018) con interruptor, y

AN81 (Celda 02), y AN81 (Celda 017) para conexión “Tee Point”

Pruebas : De rutina según IEC 62271 – 100, IEC 62271 – 102 e IEC 62271 – 203.

Page 10: INFORME DE CUMPLIMIENTO DE HITO RELEVANTE …...VERSION INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N 4 N 012119052014-CHR04-LAAM-0 FINAL CÓDIGO: R-OPE-05/REV.0 REVISIÓN: 0 FECHA:

INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N° 4

N° 012119052014-CHR04-LAAM-0 VERSION FINAL

CÓDIGO: R-OPE-05/REV.0

REVISIÓN: 0

FECHA: 12-06-2017

PÁGINA Página 10 de 12

Protocolos N° : - PV AN81 CB09 - CELDA 01 revB.

- PV AN81 CB10 – CELDA 16 revB.PDF

- PV AN81 CB11 – CELDA 18 revB.PDF

- PV AN81 TEE POINT ALTO MELIPILLA 1 - CELDA 02 revB.PDF

- PV AN81 TEE POINT ALTO MELIPILLA FUTURO 7 - CELDA 17 revB.PDF

Protocolo N° : S/N° - Pedido N°E81000423-10 de fecha 31.08.2015

5.3.7 Equipos 245 kV GIS, (unidades componentes de las celdas)

Se adjuntan además protocolos de pruebas de los siguientes equipos componente de las celdas:

5.3.7.1 Equipo : Interruptor.

Fabricante : ALSTOM GRID (China)

Tipo : B105 -6

5.3.7.2 Equipo : Transformadores de corriente.

Fabricante : ALSTOM GRID (China)

Tipo : B105 CT

5.3.7.3 Equipo : Transformador de tensión

Fabricante : ALSTOM GRID (China)

Tipo : B105 –VT6

5.3.7.4 Equipo : Bushings.

Fabricante : Jiangsu Shenma Electric Co., Ltd (China)

Tipo : FUW3-245/8T (O113315

5.3.8 Pararrayos de 220 kV

Equipo : Pararrayos 220 kV

Fabricante : TRIDELTA Überspannungsableiter GmbH

Tipo : SB 192/20.4-1

Cantidad : 3

N° de serie : 221499 – 221500 – 221501

Pruebas : Rutina según IEC 60099 – 4

Protocolo N° : 003305-1 de fecha 25.02.2015

5.3.9 Trampas de onda

Equipo : Trampa de onda 220 kV

Fabricante : ABB (Suiza)

Tipo : DLTC 2000/0,2 - 50kA

Cantidad : 3

N° de serie : HE575821/0; HE575822, y HE575823/0.

Page 11: INFORME DE CUMPLIMIENTO DE HITO RELEVANTE …...VERSION INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N 4 N 012119052014-CHR04-LAAM-0 FINAL CÓDIGO: R-OPE-05/REV.0 REVISIÓN: 0 FECHA:

INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N° 4

N° 012119052014-CHR04-LAAM-0 VERSION FINAL

CÓDIGO: R-OPE-05/REV.0

REVISIÓN: 0

FECHA: 12-06-2017

PÁGINA Página 11 de 12

Pruebas : Rutina según IEC 60353

Protocolo N° : S/N° - Pedido 600729 de fechas 20 a 22.04.2016

5.3.10 Condensador de acoplamiento

Equipo : Condensador de acoplamiento 220 kV

Fabricante : ABB (Suecia)

Tipo : CCB 245

Cantidad : 1

N° de serie : 1HSE 8863998.

Pruebas : Rutina según IEC 60358

Protocolo N° : S/N° - Pedido E81000537-10 de fecha 08.11.2016

El equipo auditor confirma que los ensayos correspondientes a las pruebas FAT de todos los equipos del

Proyecto “Nueva Línea 2x220 kV Lo Aguirre – Alto Melipilla, con un Circuito Tendido”, de acuerdo a lo indicado

en los protocolos recibidos, fueron efectuados en los Laboratorios de Pruebas de sus respectivas fábricas.

6. CONCLUSIÓN:

Considerando:

Los requerimientos para el cumplimiento del Hito N°4, establecidos en las Bases de Licitación para la

Adjudicación de las Auditorías Técnicas y sus Circulares Aclaratorias N°1 y N°2, descritos en el ítem 5.1

del presente informe.

Los registros de pruebas presentados por la empresa ELETRANS II S.A. a través de sus cartas N° ST2-

EEN007/2016 de fecha 01.08.2016; ST2-EEN012/2016 de fecha 03.11.2016; ST2-EEN013/2016 de

fecha 14.12.2016; ST2-EEN014/2016 de fecha 28.12.2016; ST2-EEN001/2017 de fecha 07.04.2017, y

ST2-EEN002/2017 de fecha 11.04.2017 y validados por esta empresa a través de su carta N° N° GG-

EII0038/2017 emitida el 27.04.2017.

La revisión de los protocolos, por parte del equipo auditor, considerando los equipos evaluados, los

tipos y cantidad de ensayos establecidos y los estándares definidos como marco regulatorio para la

evaluación de la conformidad de las pruebas ejecutadas.

Ancare Energy SpA. concluye que el Hito Relevante N°4 presentado por la empresa ELETRANS II S.A. para el

proyecto “Nueva Línea 2x220 kV Lo Aguirre – Alto Melipilla, con un Circuito Tendido”, se encuentra cumplido,

ya que los protocolos presentados reflejan el cumplimiento de los requerimientos técnicos establecidos.

Adicionalmente se concluye que este Hito se encuentra cumplido desde el 27 de abril de 2017, siendo esa

fecha concordante con el requerimiento de cumplimiento del Hito indicado en el Decreto Supremo N°6T,

respecto a que este evento debería acontecer dentro de los 731 días corridos desde la fecha de publicación del

Decreto de Adjudicación en el Diario Oficial.

Page 12: INFORME DE CUMPLIMIENTO DE HITO RELEVANTE …...VERSION INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N 4 N 012119052014-CHR04-LAAM-0 FINAL CÓDIGO: R-OPE-05/REV.0 REVISIÓN: 0 FECHA:

INFORME DE CUMPLIMIENTO DE HITO RELEVANTE N° 4

N° 012119052014-CHR04-LAAM-0 VERSION FINAL

CÓDIGO: R-OPE-05/REV.0

REVISIÓN: 0

FECHA: 12-06-2017

PÁGINA Página 12 de 12

7. CONTROL DE CAMBIOS

REVISION FECHA TIPO REVISIÓN DETALLE DE LA MODIFICACIÓN REALIZADA

PRE 29-05-2016 Creación Para aprobación de CDEC-SIC

0 12-06-2017 Final Se emite en versión final sin realizar modificaciones de acuerdo a correo electrónico emitido el 08-06-2017 por

el Coordinador Eléctrico Nacional.

8. ANEXOS

- Anexo 1 “Minuta N°1: Comentarios de Ancare Energy a Protocolos de Pruebas FAT”.

- Anexo 2 “Minuta N°2: Comentarios de Ancare Energy a Protocolos de Pruebas FAT Rev.1”.

- Anexo 3 “Minuta N°3: Comentarios de Ancare Energy a Protocolos de Pruebas FAT Rev.2”.

- Anexo 4 “Minuta N°4: Comentarios de Ancare Energy a Protocolos de Pruebas FAT Rev.3”.