Page 1: Trabajo de Planificacion Final

CRITERIODESCRIPCION UNIDAD METRADO RENDIMIENTO DIAS REQUERIDOS DIAS PROYECTO OPEXCAVACION M3 100 3 33.33 10 0CIMIENTO CORRIDO

Concreto f'c=180 M3 30 16 1.88 2 2Encofrado M2 60 12 5.00 5 1

ZAPATASCº 210 M3 10 14 0.71 1 2Encofrado M2 100 12 8.33 8 1Acero KG 1500 250 6.00 5 1

COLUMNASCº 210 M3 25 12 2.08 2 2Encofrado M2 200 10 20.00 10 1Acero KG 3000 250 12.00 6 1

VIGASCº 210 M3 40 12 3.33 2 2Encofrado M2 500 10 50.00 15 1Acero KG 6000 250 24.00 10 1

MUROSSoga M2 50 14 3.57 3 1Cabeza M2 200 8 25.00 12 1

195.24

Page 2: Trabajo de Planificacion Final

NUEVA CUADRILLAOF P FACTOR OP OF P0 1 3.33 0 0 3.333

2 6 0.94 1.875 1.875 5.6251 0 1.00 1 1 0

1 8 0.71 1.429 0.714 5.7141 0 1.04 1.042 1.042 01 0 1.20 1.2 1.2 0

1 8 1.04 2.083 1.042 8.3331 0 2.00 2 2 01 0 2.00 2 2 0

1 8 1.67 3.333 1.667 13.331 0 3.33 3.333 3.333 01 0 2.40 2.4 2.4 0

0 0.5 1.19 1.19 0 0.5950 0.5 2.08 2.083 0 1.042

Page 3: Trabajo de Planificacion Final

''MEJORAMIENTO DE VIAS VEHICULARES Y PEATONALES DE LAS CALLES 2, 4, 8, 9, 10, 11, 13. PROLONGACION. AV. VALLEJO SANTONI EN EL AA.HH. LUIS VALLEJO SANTONI. DISTRITO DE SANTIAGO - CUSCO - CUSCO''

INGENIERIA CIVIL 2015 PLANIFICACION

DESCRIPCION UNIDAD METRADO REND. OP OF P FACT.NUEVA CUADRILLA

OP OF POBRAS PROVISIONALES

CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M UND 1.00 1 1.00 1 1 0 4 1.00 1 0 4CONSTRUCCION DE CAMPAMENTO M2 48.00 20 2.40 3 0.5 1 3 0.80 0.40 0.80 2.40SEÑALES PREVENTIVAS DURANTE EL PROCESO CONSTRUCTIVO UND 6.00 3 2.00 2 0 0.5 3 1.00 0 0.50 3

OBRAS PRELIMINARESTRAZO, NIVELACION Y REPLANTEO PRELIMINAR M2 2,242.29 1,200 1.87 1 1 2 4 1.87 1.87 3.74 7.47LIMPIEZA PERMANENTE DE OBRA M2 2,242.29 300 7.47 6 0 0 6 1.25 0 0 7.47MOVILIZACION Y DESMOVILIZACION DE EQUIPOS GLB 1.00 1 1.00 1 0 0 0 1.00 0 0 0TRANSPORTE DE MATERIALES CUSCO-OBRA TON 1.00 1 1.00 1 0 0 0 1.00 0 0 0REPOSICION DE CONEXIONES DOMICILIARIAS UND 20.00 15 1.33 1 0 1 1 1.33 0 1.33 1.33

MOVIMIENTO DE TIERRASEXCAVACION EN EXPLANACIONES

CORTE EN MATERIAL COMPACTO CON MAQUINARIA M3 1,835.42 320 5.74 5 0.5 0 2 1.15 0.57 0 2.29ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=10 Km M3 2,250.10 360 6.25 6 0.5 1 0 1.04 0.52 1.04 0

PERFILADO Y COMPACTADO DE LA SUB RASANTETRAZO, NIVELACION Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO M2 2,132.17 600 3.55 3 1 1 3 1.18 1.18 1.18 3.55PERFILADO, RIEGO Y COMPACTADO DE SUB RASANTE M2 2,132.17 800 2.67 2 0.5 1 3 1.33 0.67 1.33 3.99782PRUEBA DE DENSIDAD DE CAMPO EN LA SUB RASANTE UND 7.00 1 7.00 7 0 0 0 1.00 0 0 0

BASESBASE DE 0.15m DE ESPESOR

TRAZO, NIVELACION Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO M2 2,242.29 600 3.74 3 1 1 3 1.25 1.25 1.25 3.74EXTRACCION Y APILAMIENTO DE CANTERA PARA BASE M3 511.70 360 1.42 2 0.5 1 2 0.71 0.36 0.71 1.42ZARANDEADO DE MATERIAL DE CANTERA M3 511.70 400 1.28 2 1 0 1 0.64 0.64 0 0.64CARGUIO Y TRANSPORTE DE MATERIAL PARA BASE D=12.95Km M3 690.79 300 2.30 2 0.5 1 0 1.15 0.58 1.15 0EXTENDIDO, BATIDO Y PERFILADO DE MATERIAL DE BASE M2 4,484.59 540 8.30 8 0.5 1 2 1.04 0.52 1.04 2.08RIEGO Y COMPACTADO DE BASE M2 4,484.59 1,000 4.48 4 0 1 1 1.12 0 1.12 1.12PRUEBA DE DENSIDAD DE CAMPO EN LA BASE UND 7.00 2 3.5 3 0 0 0 1.17 0 0 0

PAVIMENTOS

DIAS REQ.

DIAS PROY.

Page 4: Trabajo de Planificacion Final

''MEJORAMIENTO DE VIAS VEHICULARES Y PEATONALES DE LAS CALLES 2, 4, 8, 9, 10, 11, 13. PROLONGACION. AV. VALLEJO SANTONI EN EL AA.HH. LUIS VALLEJO SANTONI. DISTRITO DE SANTIAGO - CUSCO - CUSCO''

INGENIERIA CIVIL 2015 PLANIFICACION

SUPERFICIE DE RODADURA e=20cmTRAZO, NIVELACION Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO M2 2,132.17 600 3.55 3 1 1 3 1.18 1.18 1.18 3.55ENCOFRADO Y DESENCOFRADO EN PAVIMENTO RIGIDO M2 69.30 20 3.47 3 1 2 3 1.16 1.16 2.31 3.47LOSA DE CONCRETO Fc'=210 Kg/Cm2, e=20cm M2 426.43 21 20.31 20 1 5 3 1.02 1.02 5.08 3.05JUNTA LONGITUDIANAL Y ARTICULACION D=1/2" ACERO CORRUGADO M3 287.77 300 0.96 1 1 1 1 0.96 0.96 0.96 0.96JUNTA TRANSVERSAL DE CONTRACCION D=5/8" ACERO LISO KG 746.51 250 2.99 2 1 1 0 1.49 1.49 1.49 0JUNTAS DE DILATACION D=1" ACERO LISO KG 105.94 250 0.42 1 1 1 0 0.42 0.42 0.42 0ACERO GRADO 60 D=1/4" EN MALLA DE TEMPERATURA KG 528.78 300 1.76 2 1 1 0 0.88 0.88 0.88 0CURADO DEL CONCRETO EN LOSA DEL PAVIMENTO KG 2,132.17 120 17.77 17 0 1 1 1.05 0 1.05 1.05SELLADO DE JUNTAS EN VEREDAS M2 495.07 150 3.30 3 1 0 1 1.10 1.10 0 1.10SELLADO DE JUNTAS DE CONTRACCION M 719.70 150 4.80 4 1 0 1 1.20 1.20 0 1.20SELLADO DE JUNTA DE DILATACION M 60.30 150 0.40 1 1 0 1 0.40 0.40 0 0.40PRUEBA DE RESISTENCIA DEL CONCRETO M 189.00 2 94.5 2 0 0 0 47.25 0 0 0

OBRAS DE CONCRETOSARDINELES

TRAZO, NIVELACION Y REPLANTEO EN SARDINELES M2 15.90 600 0.03 1 1 2 3 0.03 0.03 0.05 0.0795EXCAVACION DE ZANJAS PARA SARDINEL M 106.00 2.5 42.40 41 0 0 1 1.03 0.00 0.00 1.03415ELIMINACION DE MATERIAL EXCEDENTE MANUAL D=40 m M3 3.18 7 0.45 1 0 0 1 0.45 0 0.00 0.45ENCOFRADO Y DESENCOFRADO DE SARDINELES M2 21.20 20 1.06 2 0 1 2 0.53 0.00 0.53 1.06CONCRETO f'c= 210 KG/CM2 PARA SARDINELES M3 3.18 21 0.15 1 0 2 3 0.15 0.00 0.30286 0.45CURADO DE CONCRETO EN SARDINELES M2 15.90 120 0.13 1 0 1 1 0.13 0.00 0.13 0.1325SELLADO DE JUNTAS EN SARDINELES M 35.33 150 0.24 1 1 0 1 0.24 0.24 0.00 0.23553

VEREDASTRAZO, NIVELACION Y REPLANTEO EN VEREDAS M2 90.10 600 0.15 1 1 2 3 0.15 0.15 0.30033 0.45PERFILADO Y COMPACTADO DE VEREDAS M2 90.10 150 0.60 1 0 1 2 0.60 0.00 0.60 1.20133ELIMINACION DE MATERIAL EXCEDENTE MANUAL D=40 m M3 13.52 7 1.93 2 0 0 1 0.97 0.00 0 0.97ENCOFRADO Y DESENCOFRADO DE VEREDAS M2 15.90 20 0.80 1 0 1 2 0.80 0.00 0.80 1.59EMPEDRADO DE DE VEREDAS e=12.5cm M2 15.90 60 0.27 1 0.5 1 2 0.27 0.13 0.265 0.53CONCRETO f'c= 210 KG/CM2 PARA VEREDAS e=7.5cm M3 6.76 21 0.32 1 0 3 4 0.32 0.00 0.97 1.28762BRUÑADO DE VEREDAS M 106.00 20 5.30 4 0 1 1 1.33 0.00 1.325 1.33CURADO DE CONCRETO EN VEREDAS M2 90.10 100 0.90 1 0 1 1 0.90 0.00 0.90 0.901SELLADO DE JUNTAS EN VEREDAS M 35.33 150 0.24 1 1 0 1 0.24 0.24 0 0.24

Page 5: Trabajo de Planificacion Final

''MEJORAMIENTO DE VIAS VEHICULARES Y PEATONALES DE LAS CALLES 2, 4, 8, 9, 10, 11, 13. PROLONGACION. AV. VALLEJO SANTONI EN EL AA.HH. LUIS VALLEJO SANTONI. DISTRITO DE SANTIAGO - CUSCO - CUSCO''

INGENIERIA CIVIL 2015 PLANIFICACION

REPARACION Y ENCIMADO DE BUZONES INCLUIDO TAPAENCOFRADO Y DESENCFRADO DE BUZONES M2 5.76 10 0.58 1 1 1 2 0.58 0.58 0.576 1.15CONCRETO f'c= 210 KG/CM2 EN BUZONES M3 1.73 21 0.08 1 1 4 3 0.08 0.08 0.32952 0.25COLOCACION DE TAPAS EN BUZONES UND 4.00 8 0.50 1 0 1 1 0.50 0.00 0.5 0.50

MUROS DE CONTENCIONTRAZO Y REPLANTEO DE OBRAS DE ARTE M2 214.18 350 0.61 1 1 2 3 0.61 0.61 1.22389 1.84EXCAVACION MANUAL DE ZANJAS M3 481.91 2.5 192.76 180 0 0 1 1.07 0.00 0 1.07ELIMINACION DE MATERIAL EXCEDENTE MANUAL D=40 m M3 702.78 7 100.40 80 0 0 1 1.25 0.00 0 1.25ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=10 Km M3 702.78 360 1.95 2 0.5 1 0 0.98 0.49 0.97608 0.00ENCOFRADO Y DESENCOFRADO DE MURO DE CONTENCION M2 642.54 20 32.13 30 1 2 3 1.07 1.07 2.1418 3.21CONCRETO f'c= 210 KG/CM2 +70% P.G. EN MURO DE CONTENCION M3 82.99 21 3.95 3 1 4 3 1.32 1.32 5.26921 3.95SUMINISTRO Y COLOCADO DE TUBERIA D=2" M 80.32 80 1.00 1 0 1 1 1.00 0.00 1.004 1.00CURADO DEL CONCRETO EN MURO DE CONTENCION M2 642.54 100 6.43 6 0 1 1 1.07 0.00 1.0709 1.07BARANDA METALICA CON TUBERIA F°G° D=2" M 251.18 8 31.40 30 1 1 0 1.05 1.05 1.04658 0.00

DRENAJE Y SISTEMA DE EVACUACION DE AGUAS PLUVIALESSUMIDERO TRANSVERSAL Y TUBERIA

TRAZO, NIVELACION Y REPLANTEO EN SUMIDERO M2 60.36 600 0.10 1 1 2 3 0.10 0.10 0.2012 0.30EXCAVACION DE ZANJAS H=1.40m (MANUAL) PARA TUBERIA M3 45.65 2.5 18.26 18 0 0 1 1.01 0.00 0 1.01PERFILADO Y COMPACTADO PARA FONDO DE SUMIDERO M2 2.81 150 0.02 1 0 1 2 0.02 0.00 0.01873 0.04CAMA DE ARENA PARA APOYO DE TUBERIA M3 2.55 10 0.26 1 0 1 1 0.26 0.00 0.255 0.26ELIMINACION DE MATERIAL EXCEDENTE MANUAL D=40 m M3 57.06 7 8.15 8 0 0 1 1.02 0.00 0 1.02ENCOFRADO Y DESENCOFRADO DE SUMIDEROS M2 41.28 20 2.06 2 1 2 3 1.03 1.03 2.064 3.10CONCRETO MEZCLA C:H 1:12, EN SOLADO M3 0.94 12 0.08 1 0.5 1 1 0.08 0.04 0.07833 0.08CONCRETO f'c= 210 KG/CM2 EN SUMIDEROS M3 1.01 9 0.11 1 1 4 3 0.11 0.11 0.44889 0.34ACERO GRADO 60 fy=4200 Kg/cm2 EN SUMIDEROS KG 38.83 300 0.13 1 0 1 1 0.13 0.00 0.12943 0.13CURADO DE CONCRETO EN SUMIDEROS M2 9.36 100 0.09 1 0.5 1 1 0.09 0.05 0.0936 0.09SUMIDERO PREPARADO Y COLOCADO CON PLATINAS DE 2"x1/2" M2 4.29 2 2.15 2 0 1 1 1.07 0.00 1.0725 1.07TUBERIA PVC SAL DE D=8" M 51.00 100 0.51 1 0 1 2 0.51 0.00 0.51 1.02RELLENO Y COMPACTADO EN ZANJAS CON MATERIAL PROPIO M3 55.46 150 0.37 1 0 1 2 0.37 0.00 0.36973 0.74

SEÑALIZACIONSEÑALES PREVENTIVAS UND 3.00 250 0.01 1 1 1 1 0.01 0.01 0.012 0.01SEÑALES REGULADORAS UND 3.00 250 0.01 1 1 1 1 0.01 0.01 0.012 0.01

Page 6: Trabajo de Planificacion Final

''MEJORAMIENTO DE VIAS VEHICULARES Y PEATONALES DE LAS CALLES 2, 4, 8, 9, 10, 11, 13. PROLONGACION. AV. VALLEJO SANTONI EN EL AA.HH. LUIS VALLEJO SANTONI. DISTRITO DE SANTIAGO - CUSCO - CUSCO''

INGENIERIA CIVIL 2015 PLANIFICACION

SEÑALES INFORMATIVAS UND 8.00 250 0.03 1 1 1 1 0.03 0.03 0.032 0.03MARCAS PERMANENTES EN EL PAVIMENTO M 1,485.21 300 4.95 4 1 0 3 1.24 1.24 0 3.71

MITIGACION DE IMPACTOSTALLERES DE INFORMACION GLB 1.00 5 0.20 1 0 0 0 0.20 0.00 0 0.00LIMPIEZA FINAL DE OBRA M2 2,242.29 200 11.21 10 0 0 2 1.12 0.00 0 2.24

Page 7: Trabajo de Planificacion Final

''MEJORAMIENTO DE VIAS VEHICULARES Y PEATONALES DE LAS CALLES 2, 4, 8, 9, 10, 11, 13. PROLONGACION. AV. VALLEJO SANTONI EN EL AA.HH. LUIS VALLEJO SANTONI. DISTRITO DE SANTIAGO - CUSCO - CUSCO''

INGENIERIA CIVIL 2015 PLANIFICACION DE OBRAS

DESCRIPCION UNIDAD METRADO REND. OP OF PHORAS HOMBRE

OP OF POBRAS PROVISIONALES

CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M UND 1.00 1 1.00 1 0 4 8 0 32CONSTRUCCION DE CAMPAMENTO M2 48.00 20 2.40 0.5 1 3 9.6 19.2 57.6SEÑALES PREVENTIVAS DURANTE EL PROCESO CONSTRUCTIVO UND 6.00 3 2.00 0 0.5 3 0 8 48

DIAS REQUERIDOS 17.6 27.2 137.62.2 3.4 17.2

1 2.2 3.4 17.25 0.44 0.68 3.44

OBRAS PRELIMINARESTRAZO, NIVELACION Y REPLANTEO PRELIMINAR M2 2,242.29 1,200 1.87 1 2 4 14.9486 29.8972 59.7944LIMPIEZA PERMANENTE DE OBRA M2 2,242.29 300 7.47 0 0 6 0 0 358.766MOVILIZACION Y DESMOVILIZACION DE EQUIPOS GLB 1.00 1 1.00 0 0 0 0 0 0TRANSPORTE DE MATERIALES CUSCO-OBRA TON 1.00 1 1.00 0 0 0 0 0 0REPOSICION DE CONEXIONES DOMICILIARIAS UND 20.00 15 1.33 0 1 1 0 10.6667 10.6667

DIAS REQUERIDOS 14.9486 40.5639 429.2271.86857 5.07048 53.6534

1 1.86857 5.07048 53.65346 0.31143 0.84508 8.94224

MOVIMIENTO DE TIERRASEXCAVACION EN EXPLANACIONES

CORTE EN MATERIAL COMPACTO CON MAQUINARIA M3 1,835.42 320 5.74 0.5 0 2 22.9428 0 91.771ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=10 Km M3 2,250.10 360 6.25 0.5 1 0 25.0011 50.0022 0

DIAS REQUERIDOS 47.94 50.00 91.775.99 6.25 11.47

2 3.00 3.13 5.749 0.3 0.3 0.6

DIAS REQ.

Page 8: Trabajo de Planificacion Final

''MEJORAMIENTO DE VIAS VEHICULARES Y PEATONALES DE LAS CALLES 2, 4, 8, 9, 10, 11, 13. PROLONGACION. AV. VALLEJO SANTONI EN EL AA.HH. LUIS VALLEJO SANTONI. DISTRITO DE SANTIAGO - CUSCO - CUSCO''

INGENIERIA CIVIL 2015 PLANIFICACION DE OBRAS

PERFILADO Y COMPACTADO DE LA SUB RASANTETRAZO, NIVELACION Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO M2 2,132.17 600 3.55 1 1 3 28.4289 28.4289 85.2868PERFILADO, RIEGO Y COMPACTADO DE SUB RASANTE M2 2,132.17 800 2.67 0.5 1 3 10.6609 21.3217 63.9651PRUEBA DE DENSIDAD DE CAMPO EN LA SUB RASANTE UND 7.00 1 7.00 0 0 0 0 0 0

DIAS REQUERIDOS 39.0898 49.7506 149.2524.88622 6.21883 18.6565

1 4.88622 6.21883 18.656510 0.48862 0.62188 1.86565

BASESBASE DE 0.15m DE ESPESOR

TRAZO, NIVELACION Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO M2 2,242.29 600 3.74 1 1 3 29.8972 29.8972 89.6916EXTRACCION Y APILAMIENTO DE CANTERA PARA BASE M3 511.70 360 1.42 0.5 1 2 5.68556 11.3711 22.7422ZARANDEADO DE MATERIAL DE CANTERA M3 511.70 400 1.28 1 0 1 10.234 0 10.234CARGUIO Y TRANSPORTE DE MATERIAL PARA BASE D=12.95Km M3 690.79 300 2.30 0.5 1 0 9.21053 18.4211 0EXTENDIDO, BATIDO Y PERFILADO DE MATERIAL DE BASE M2 4,484.59 540 8.30 0.5 1 2 33.2192 66.4384 132.877RIEGO Y COMPACTADO DE BASE M2 4,484.59 1,000 4.48 0 1 1 0 35.8767 35.8767PRUEBA DE DENSIDAD DE CAMPO EN LA BASE UND 7.00 2 3.5 0 0 0 0 0 0

DIAS REQUERIDOS 88.2465 162 291.42111.0308 20.2506 36.4277

17 0.64887 1.19121 2.142818 0.03605 0.06618 0.11904

PAVIMENTOSSUPERFICIE DE RODADURA e=20cm

TRAZO, NIVELACION Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO M2 2,132.17 600 3.55 1 1 3 28.4289 28.4289 85.2868ENCOFRADO Y DESENCOFRADO EN PAVIMENTO RIGIDO M2 69.30 20 3.47 1 2 3 27.72 55.44 83.16LOSA DE CONCRETO Fc'=210 Kg/Cm2, e=20cm M2 426.43 21 20.31 1 5 3 162.45 812.248 487.349JUNTA LONGITUDIANAL Y ARTICULACION D=1/2" ACERO CORRUGADO M3 287.77 300 0.96 1 1 1 7.67387 7.67387 7.67387JUNTA TRANSVERSAL DE CONTRACCION D=5/8" ACERO LISO KG 746.51 250 2.99 1 1 0 23.8883 23.8883 0JUNTAS DE DILATACION D=1" ACERO LISO KG 105.94 250 0.42 1 1 0 3.39008 3.39008 0

Page 9: Trabajo de Planificacion Final

''MEJORAMIENTO DE VIAS VEHICULARES Y PEATONALES DE LAS CALLES 2, 4, 8, 9, 10, 11, 13. PROLONGACION. AV. VALLEJO SANTONI EN EL AA.HH. LUIS VALLEJO SANTONI. DISTRITO DE SANTIAGO - CUSCO - CUSCO''

INGENIERIA CIVIL 2015 PLANIFICACION DE OBRAS

ACERO GRADO 60 D=1/4" EN MALLA DE TEMPERATURA KG 528.78 300 1.76 1 1 0 14.1008 14.1008 0CURADO DEL CONCRETO EN LOSA DEL PAVIMENTO KG 2,132.17 120 17.77 0 1 1 0 142.145 142.145SELLADO DE JUNTAS EN VEREDAS M2 495.07 150 3.30 1 0 1 26.4037 0 26.4037SELLADO DE JUNTAS DE CONTRACCION M 719.70 150 4.80 1 0 1 38.384 0 38.384SELLADO DE JUNTA DE DILATACION M 60.30 150 0.40 1 0 1 3.216 0 3.216PRUEBA DE RESISTENCIA DEL CONCRETO M 189.00 2 94.5 0 0 0 0 0 0

DIAS REQUERIDOS 335.655 1087.31 873.61841.9569 135.914 109.202

2 20.9785 67.9571 54.601140 0.52446 1.69893 1.36503

OBRAS DE CONCRETOSARDINELES

TRAZO, NIVELACION Y REPLANTEO EN SARDINELES M2 15.90 600 0.03 1 2 3 0.212 0.424 0.636EXCAVACION DE ZANJAS PARA SARDINEL M 106.00 2.5 42.40 0 0 1 0 0 339.2ELIMINACION DE MATERIAL EXCEDENTE MANUAL D=40 m M3 3.18 7 0.45 0 0 1 0 0 3.63429ENCOFRADO Y DESENCOFRADO DE SARDINELES M2 21.20 20 1.06 0 1 2 0 8.48 16.96CONCRETO f'c= 210 KG/CM2 PARA SARDINELES M3 3.18 21 0.15 0 2 3 0 2.42286 3.63429CURADO DE CONCRETO EN SARDINELES M2 15.90 120 0.13 0 1 1 0 1.06 1.06SELLADO DE JUNTAS EN SARDINELES M 35.33 150 0.24 1 0 1 1.88427 0 1.88427

DIAS REQUERIDOS 23.5992 82.0429 422.9752.9499 10.2554 52.8719

15 0.19666 0.68369 3.5247926 0.00756 0.0263 0.13557

VEREDASTRAZO, NIVELACION Y REPLANTEO EN VEREDAS M2 90.10 600 0.15 1 2 3 1.20133 2.40267 3.604PERFILADO Y COMPACTADO DE VEREDAS M2 90.10 150 0.60 0 1 2 0 4.80533 9.61067ELIMINACION DE MATERIAL EXCEDENTE MANUAL D=40 m M3 13.52 7 1.93 0 0 1 0 0 15.4514ENCOFRADO Y DESENCOFRADO DE VEREDAS M2 15.90 20 0.80 0 1 2 0 6.36 12.72EMPEDRADO DE DE VEREDAS e=12.5cm M2 15.90 60 0.27 0.5 1 2 1.06 2.12 4.24CONCRETO f'c= 210 KG/CM2 PARA VEREDAS e=7.5cm M3 6.76 21 0.32 0 3 4 0 7.72571 10.301

Page 10: Trabajo de Planificacion Final

''MEJORAMIENTO DE VIAS VEHICULARES Y PEATONALES DE LAS CALLES 2, 4, 8, 9, 10, 11, 13. PROLONGACION. AV. VALLEJO SANTONI EN EL AA.HH. LUIS VALLEJO SANTONI. DISTRITO DE SANTIAGO - CUSCO - CUSCO''

INGENIERIA CIVIL 2015 PLANIFICACION DE OBRAS

BRUÑADO DE VEREDAS M 106.00 20 5.30 0 1 1 0 42.4 42.4CURADO DE CONCRETO EN VEREDAS M2 90.10 100 0.90 0 1 1 0 7.208 7.208SELLADO DE JUNTAS EN VEREDAS M 35.33 150 0.24 1 0 1 1.88427 0 1.88427

DIAS REQUERIDOS 4.15316 73.048 107.5550.51915 9.131 13.4444

15 0.03461 0.60873 0.8962926 0.00133 0.02341 0.03447

REPARACION Y ENCIMADO DE BUZONES INCLUIDO TAPAENCOFRADO Y DESENCFRADO DE BUZONES M2 5.76 10 0.58 1 1 2 4.608 4.608 9.216CONCRETO f'c= 210 KG/CM2 EN BUZONES M3 1.73 21 0.08 1 4 3 0.65905 2.63619 1.97714COLOCACION DE TAPAS EN BUZONES UND 4.00 8 0.50 0 1 1 0 4 4

DIAS REQUERIDOS 11.8596 143.663 188.6151.48245 17.9579 23.5769

18 0.08236 0.99766 1.3098325 0.00329 0.03991 0.05239

MUROS DE CONTENCIONTRAZO Y REPLANTEO DE OBRAS DE ARTE M2 214.18 350 0.61 1 2 3 4.89554 9.79109 14.6866EXCAVACION MANUAL DE ZANJAS M3 481.91 2.5 192.76 0 0 1 0 0 1542.11ELIMINACION DE MATERIAL EXCEDENTE MANUAL D=40 m M3 702.78 7 100.40 0 0 1 0 0 803.177ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=10 Km M3 702.78 360 1.95 0.5 1 0 7.80867 15.6173 0ENCOFRADO Y DESENCOFRADO DE MURO DE CONTENCION M2 642.54 20 32.13 1 2 3 257.016 514.032 771.048CONCRETO f'c= 210 KG/CM2 +70% P.G. EN MURO DE CONTENCION M3 82.99 21 3.95 1 4 3 31.6152 126.461 94.8457SUMINISTRO Y COLOCADO DE TUBERIA D=2" M 80.32 80 1.00 0 1 1 0 8.032 8.032CURADO DEL CONCRETO EN MURO DE CONTENCION M2 642.54 100 6.43 0 1 1 0 51.4032 51.4032BARANDA METALICA CON TUBERIA F°G° D=2" M 251.18 8 31.40 1 1 0 251.18 251.18 0

DIAS REQUERIDOS 552.519 976.556 3285.3669.0648 122.07 410.67

4 17.2662 30.5174 102.66734 0.50783 0.89757 3.01963

Page 11: Trabajo de Planificacion Final

''MEJORAMIENTO DE VIAS VEHICULARES Y PEATONALES DE LAS CALLES 2, 4, 8, 9, 10, 11, 13. PROLONGACION. AV. VALLEJO SANTONI EN EL AA.HH. LUIS VALLEJO SANTONI. DISTRITO DE SANTIAGO - CUSCO - CUSCO''

INGENIERIA CIVIL 2015 PLANIFICACION DE OBRAS

DRENAJE Y SISTEMA DE EVACUACION DE AGUAS PLUVIALESSUMIDERO TRANSVERSAL Y TUBERIA

TRAZO, NIVELACION Y REPLANTEO EN SUMIDERO M2 60.36 600 0.10 1 2 3 0.8048 1.6096 2.4144EXCAVACION DE ZANJAS H=1.40m (MANUAL) PARA TUBERIA M3 45.65 2.5 18.26 0 0 1 0 0 146.08PERFILADO Y COMPACTADO PARA FONDO DE SUMIDERO M2 2.81 150 0.02 0 1 2 0 0.14987 0.29973CAMA DE ARENA PARA APOYO DE TUBERIA M3 2.55 10 0.26 0 1 1 0 2.04 2.04ELIMINACION DE MATERIAL EXCEDENTE MANUAL D=40 m M3 57.06 7 8.15 0 0 1 0 0 65.2114ENCOFRADO Y DESENCOFRADO DE SUMIDEROS M2 41.28 20 2.06 1 2 3 16.512 33.024 49.536CONCRETO MEZCLA C:H 1:12, EN SOLADO M3 0.94 12 0.08 0.5 1 1 0.31333 0.62667 0.62667CONCRETO f'c= 210 KG/CM2 EN SUMIDEROS M3 1.01 9 0.11 1 4 3 0.89778 3.59111 2.69333ACERO GRADO 60 fy=4200 Kg/cm2 EN SUMIDEROS KG 38.83 300 0.13 0 1 1 0 1.03547 1.03547CURADO DE CONCRETO EN SUMIDEROS M2 9.36 100 0.09 0.5 1 1 0.3744 0.7488 0.7488SUMIDERO PREPARADO Y COLOCADO CON PLATINAS DE 2"x1/2" M2 4.29 2 2.15 0 1 1 0 17.16 17.16TUBERIA PVC SAL DE D=8" M 51.00 100 0.51 0 1 2 0 4.08 8.16RELLENO Y COMPACTADO EN ZANJAS CON MATERIAL PROPIO M3 55.46 150 0.37 0 1 2 0 2.95787 5.91573

DIAS REQUERIDOS 18.0975 65.4138 299.5072.26219 8.17672 37.4384

28 0.08079 0.29203 1.3370936 0.00224 0.00811 0.03714

SEÑALIZACIONSEÑALES PREVENTIVAS UND 3.00 250 0.01 1 1 1 0.096 0.096 0.096SEÑALES REGULADORAS UND 3.00 250 0.01 1 1 1 0.096 0.096 0.096SEÑALES INFORMATIVAS UND 8.00 250 0.03 1 1 1 0.256 0.256 0.256MARCAS PERMANENTES EN EL PAVIMENTO M 1,485.21 300 4.95 1 0 3 39.6056 0 118.817

DIAS REQUERIDOS 60.4963 81.3765 471.667.56204 10.1721 58.9575

2 3.78102 5.08603 29.478810 0.3781 0.5086 2.94788

MITIGACION DE IMPACTOSTALLERES DE INFORMACION GLB 1.00 5 0.20 0 0 0 0 0 0

Page 12: Trabajo de Planificacion Final

''MEJORAMIENTO DE VIAS VEHICULARES Y PEATONALES DE LAS CALLES 2, 4, 8, 9, 10, 11, 13. PROLONGACION. AV. VALLEJO SANTONI EN EL AA.HH. LUIS VALLEJO SANTONI. DISTRITO DE SANTIAGO - CUSCO - CUSCO''

INGENIERIA CIVIL 2015 PLANIFICACION DE OBRAS

LIMPIEZA FINAL DE OBRA M2 2,242.29 200 11.21 0 0 2 0 0 179.383DIAS REQUERIDOS 112.271 97.5912 861.693

14.0339 12.1989 107.7125 2.80678 2.43978 21.5423

18 0.15593 0.13554 1.1968

Page 13: Trabajo de Planificacion Final

''MEJORAMIENTO DE VIAS VEHICULARES Y PEATONALES DE LAS CALLES 2, 4, 8, 9, 10, 11, 13. PROLONGACION. AV. VALLEJO SANTONI EN EL AA.HH. LUIS VALLEJO SANTONI. DISTRITO DE SANTIAGO - CUSCO - CUSCO''

INGENIERIA CIVIL 2015 PLANIFICACION DE OBRAS

Page 14: Trabajo de Planificacion Final

2020

4

9 34 87105 LEYENDARUTA CRITICA

918 10

00 55 1111 2139 5454 6969 115115

1 5 2 6 3 10 5 15 7 15 8 11FINAL

INICIO17 40 28 9797 18

2814 106

DESCRIPCCION 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115

OBRAS PROVISIONALES

OBRAS PRELIMINARES

EXCAVACION EN EXPLANACIONES

PERFILADO Y COMPACTADO DE LA SUB RASANTE

BASE

PAVIMENTOS

SARDINELES

MUROS DE CONTENCION

VEREDAS

REPARACION Y ENCIMADO DE BUZONES INCLUIDO TAPA

DRENAJE Y SISTEMA DE EVACUACION DE AGUAS PLUVIALES

SEÑALIZACION

MITIGACION DE IMPACTOS

DESCRIPCCION 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115

OBRAS PROVISIONALES

OBRAS PRELIMINARES

EXCAVACION EN EXPLANACIONES

PERFILADO Y COMPACTADO DE LA SUB RASANTE

BASE

PAVIMENTOS

SARDINELES

MUROS DE CONTENCION

VEREDAS

REPARACION Y ENCIMADO DE BUZONES INCLUIDO TAPA

DRENAJE Y SISTEMA DE EVACUACION DE AGUAS PLUVIALES

SEÑALIZACION

MITIGACION DE IMPACTOS

12

11

10

9

8

7

LEYENDA 6

OPERARIO 5

OFICIAL 4

PEON 3

2

1

0

SETIEMBRE - 1 OCTOBRE - 1 NOVIEMRE - 1 DICIEMBRE - 1DESCRIPCCION DURAC. S/. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

OBRAS PROVISIONALES 5 8,280.01

OBRAS PRELIMINARES 6 23,048.89

EXCAVACION EN EXPLANACIONES 9 58,845.14

PERFILADO Y COMPACTADO DE LA SUB RASANTE 10 16,117.59

BASE 17 689,233.15

PAVIMENTOS 40 201,105.05

SARDINELES 15 5,697.49

MUROS DE CONTENCION 34 120,604.29

VEREDAS 15 5,245.95

REPARACION Y ENCIMADO DE BUZONES INCLUIDO TAPA 18 1,389.31

DRENAJE Y SISTEMA DE EVACUACION DE AGUAS PLUVIALES 28 9,058.49

SEÑALIZACION 10 5,056.49

MITIGACION DE IMPACTOS 18 2,025.95

GASTOS DIRECTOS 1,145,707.80 851,564.75 245,715.96 48,761.34 5,989.65

GASTOS GENERALES 12% 137,484.94 102,187.77 29,485.92 5,851.36 718.76

UTILIDADES 7% 9,623.95 7,153.14 2,064.01 409.60 50.31

SUB TOTAL 1,292,816.68 960,905.66 277,265.89 55,022.29 6,758.72

I.G.V 18% 232,707.00 172,963.02 49,907.86 9,904.01 1,216.57

TOTAL 1,525,523.68 1,133,868.68 327,173.75 64,926.30 7,975.29

% MENSUAL 74.33 21.45 4.26 0.52

% ACUMULADO 74.33 95.77 100.03 100.55

SETIEMBRE - 1 OCTOBRE - 1 NOVIEMRE - 1 DICIEMBRE - 1DESCRIPCCION DURAC. S/. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

OBRAS PROVISIONALES 5 8,280.01

OBRAS PRELIMINARES 6 23,048.89

EXCAVACION EN EXPLANACIONES 9 58,845.14

PERFILADO Y COMPACTADO DE LA SUB RASANTE 10 16,117.59

BASE 17 689,233.15

PAVIMENTOS 40 201,105.05

SARDINELES 15 5,697.49

MUROS DE CONTENCION 34 120,604.29

VEREDAS 15 5,245.95

REPARACION Y ENCIMADO DE BUZONES INCLUIDO TAPA 18 1,389.31

DIAGRAMA DE FLECHAS

DIAGRAMA DE BARRAS5 dias

6 dias

34 dias

28 dias

18 dias

15 dias

O PROV O PRE

E EXP

PAV

PCSR SARD

BA

MC

V

REBIT

DSEAP

S

MI

9 dias

10 dias

17 dias

18 dias

15 dias

40 dias

10 dias

DIAGRAMA DE MANO DE OBRA5 dias

6 dias

34 dias

28 dias

18 dias

15 dias

9 dias

10 dias

17 dias

18 dias

15 dias

40 dias

10 dias

0 Op , 0 Of , 3 P

0 Op , 1 Of , 9 P

0 Op , 0 Of , 1 P

0 Op , 1 Of , 2 P

1 Op , 0 Of , 0 P

1 Op , 2 Of , 1 P

0 Op , 1 Of , 4 P

1 Op , 1 Of , 3 P

0 Op , 1 Of , 1 P

0 Op , 1 Of , 1 P

0 Op , 0 Of , 1 P

0 Op , 1 Of , 3 P

0 Op , 0 Of , 1 P

CAN

TIDA

D DE

PER

SONA

L

FLUJO DE CAJA (CRONOGRAMA VALORIZADO)

5

6

10

22

18

8

9

10

17

18

9

2

4

7 31

6

24

7

6

6

8,280.01

23,048.89

58,845.14

16,117.59

689,233.15

10,055.25

3,418.49

42,566.22

155,856.41

2,279.00

8,132.44

2,448.11 3,038.66

35,193.38

1,389.31

7,117.39

2,022.60

1,941.11

2,022.60

2,025.95

ASIGNACION DE RECURSO

3

9

3

5

1 1 1

2 2

7 8

4

2 1

2

2 2

4

1

0 1 1

2

4

2

4

3

2

3

Page 15: Trabajo de Planificacion Final

DRENAJE Y SISTEMA DE EVACUACION DE AGUAS PLUVIALES 28 9,058.49

SEÑALIZACION 10 5,056.49

MITIGACION DE IMPACTOS 18 2,025.95

MATERIALES UNIDAD INDICE

CEMENTO PORTLAND TIPO I BLS 21

AGREGADO GRUESO KG 05

EQUIPOS UNIDAD UNIDAD

MAQUINARIA Y EQUIPO NACIONAL HM 48

MAQUINARIA Y EQUIPO IMPORTADO HM 49

Page 16: Trabajo de Planificacion Final

OBRAS PROVISIONALES

OBRAS PRELIMINARESEXCAVACION EN EXPLANACIONESPERFILADO Y COMPACTADO DE LA SUB RASANTEBASESPAVIMENTOSSARDINELESVEREDASREPARACION Y ENCIMADO DE BUZONES INCLUIDO TAPAMUROS DE CONTENCIONDRENAJE Y SISTEMA DE EVACUACION DE AGUAS PLUVIALESSEÑALIZACIONMITIGACION DE IMPACTOS

Page 17: Trabajo de Planificacion Final

SIMBOLO DIAS OP OF P

O PROV 5 0 1 3 SETIEMBRE - 1O PRE 6 0 1 9 5EEXP 9 0 0 1 5PCSR 10 0 1 2 x1 =

BA 17 1 0 0

PAV 40 1 2 1 OCTOBRE - 1SARD 15 0 1 4 40

V 15 0 1 1 31REBIT 18 0 1 1 x1 =

MC 34 1 1 3

RDSEAP 28 0 0 1 NOVIEMRE - 1S 10 0 1 3 40

MI 18 0 0 1 7

x1 =

DICIEMBRE - 128

6

x1 =

Page 18: Trabajo de Planificacion Final

SETIEMBRE - 18,280.01 6 23,048.89 9 58,845.14 10

x1 6 x2 9 x3 10

8,280.01 x2 = 23,048.89 x3 = 58,845.14 x4 =

OCTOBRE - 1201,105.05 15 5,697.49 34 120,604.29 15

x1 6 x2 24 x3 7

155,856.41 x2 = 2,279.00 x3 = 85,132.44 x4 =

NOVIEMRE - 1201,105.05 15 5,697.49 18 1,389.31 28

x1 8 x2 18 x3 22

35,193.38 x2 = 3,038.66 x3 = 1,389.31 x4 =

DICIEMBRE - 19,058.49 15 5,056.49 18 2,025.95

x1 6 x2 18 x3

1,941.11 x2 = 2,022.60 x3 = 2,025.95

Page 19: Trabajo de Planificacion Final

16,117.59 17 689,233.15 40 201,105.05 15

x4 17 x5 2 x6 9

16,117.59 x5 = 689,233.15 x6 = 10,055.25 x7 =

5,245.95

x4

2,448.11

9,058.49 10 5,056.49

x4 4 x5

7,117.39 x5 = 2,022.60

Page 20: Trabajo de Planificacion Final

5,697.49 34 120,604.29

x7 12 x8

3,418.49 x8 = 42,566.22

Page 21: Trabajo de Planificacion Final
Page 22: Trabajo de Planificacion Final
Page 23: Trabajo de Planificacion Final
Page 24: Trabajo de Planificacion Final
Page 25: Trabajo de Planificacion Final
Page 26: Trabajo de Planificacion Final
Page 27: Trabajo de Planificacion Final

HORAS HOMBREDESCRIPCION UNIDAD METRADO RENDIMIENTO DIAS REQU OP OF P OP OFCIMIENTO CORRIDO

Concreto f'c=180 M3 30 16 1.88 2 2 6 30 30Encofrado M2 60 12 5.00 1 1 0 40 40

DIAS REQUERIDOS 70 708.75 8.75

3 2.9167 2.91675 1.75 1.75

ZAPATASCº 210 M3 10 14 0.71 2 1 8 11.429 16Encofrado M2 100 12 8.33 1 1 0 66.667 66.667Acero KG 1500 250 6.00 1 1 0 48 48

DIAS REQUERIDOS 114.67 114.6714.333 14.333

6 2.3889 2.38898 1.7917 1.7917

MUROSSoga M2 50 14 3.57 1 0 0.5 28.571 0Cabeza M2 200 8 25.00 1 0 0.5 200 0

DIAS REQUERIDOS 228.57 028.571 0

10 2.8571 012 2.381 0

Page 28: Trabajo de Planificacion Final

HORAS HOMBREP

900

90 HH11.25 DIAS3.75 PERSONAL

2.25 PERSONAL

6400

0 HH0 DIAS0 PERSONAL

0 PERSONAL

14.286100

114.29 HH14.286 DIAS1.4286 PERSONAL1.1905 PERSONAL