li presentation

Post on 22-Jul-2016

24 Views

Category:

Documents

4 Downloads

Preview:

Click to see full reader

DESCRIPTION

industia

TRANSCRIPT

LATIHAN INDUSTRI (INTERNSHIP) SESI DIS 2012

NAME : VIVIEN LAI MEI YEN

COURSE: CIVIL ENGINEERING MATRIC NO. : 01DKA10F1005

8/3/2013

LECTURER’S NAME :PN FARIDAH BT MOHD ZINPN HANIZA BT MOHAMED

COMPANY PROFILEGAINTREND SDN BHD

MANAGEMENT TEAM Mr. Nelson Tan ( Managing Director)

Mr. Yap Biaw Thiang (General Manager/ Project Head)

Ms. Tan BH (Accounts Department/ Human Resource Department Manager)

Ms. Lee LL (QSM Manager)

Mr. Abdul Rahman Ismail (Site Supervisor)

Mr. Mohd Najib B. Halim (Ass. Site Supervisor)

COMPLETED PROJECTProject Cadangan Membina Rumah Teres

3 Tingkat ( 4 Unit) & Rumah Teres 2 Tingkat ( 25Unit) Di Atas Lot 319, Sek. 1, Bandar Jelutong, DTL, Jalan Jelutong, Pulau Pinang.

Name of Architect/Consultant

Jurucita Consultant Sdn Bhd

Date of Start 2 August 2011Date of Completed 27 Jun 2012

CURRENT PROJECTProject Commencement Date Completion

DateCadangan Skim Perumahan Di Atas Lot 144, 1418, 1419, 1420 Dan 1421 Mk14, S.P.T, Di Jalan Kota Permai, Bukit Mertajam, Pulau Pinang For Messers Pacific Treasure Land Sdn. Bhd.

-Structural, Masonry, Ceiling and Metal Works-

17/6/2012 16/6/2013

Organization Chart on siteGaintrend Sdn Bhd

Project Head

Mr. Yap Biaw Tiang

Contract

Mr. Loh P.G

Ms Sow A.T

Site Head

Mr. Mohd Fauzi Shari

Site Supervisor

Mr. Abdul Rahman Ismail

Asst. Site Supervisor

Mr. Mohd Najib B. Halim

PRO (FAC)

Mr Teoh S.C

Site Safety Supervisor

Mr. Mohd Hazri B. Hashim

CONSTRUCTION PROGRESSOF

DOUBLE STOREY SEMI-DETACH(DSSD)

BUILDING ELEMENTS OF DSSD Foundation Ground Beam Ground Floor Slab (non suspended) Ground Columns 1st Floor Slab & Beam 1st Floor Column Staircase Roof beam & T-beam

FOUNDATION

Foundation is the most important part of the building.

(a)Distribute the load from the structure to soil evenly and safely.

(b)To anchor the building to the ground so that under lateral loads building will not move.

(c) Prevents the building from overtuning due to lateral forces.

(d)Gives level surface for the construction of super structure.

GROUND BEAM

1) Erection of formwork

2) Reinforcement works are in progress.

3) At last, Concrete Casting is carried out.

GROUND FLOOR SLAB (NON-SUSPENDED)

-Slabs are important components of a building.

-Classified on two types of slab:(a)One-way slab(b)Two-way slab

GROUND FLOOR COLUMNS

Transfer load of structure vertically downwards .

1ST FLOOR SLAB&BEAM

1ST FLOOR COLUMN

STAIRCASE

All steps shall have nonskid covering, and skid resistant edging can be fastened at the forefront of the steps.

The forefront of the steps can also be marked with a color edging.

ROOF BEAM & T-BEAM

T-Beam

LASTLY….

top related