rdo 10- os 123895 - c&f - 07.08.2014 - ducto de transferencia payamino - gacela-est coca

18
SISTEMA DE GESTION DE CALIDAD CONTRATO No.: N/A CONTRATISTA: CYFOIL CIA. LTDA. PROYECTO: # OT/OS: OS 123895 REG. No.: 07B020-05-RGT-024-01-010 LOCACION: BLOQUE 7 - PAYAMINO FECHA DE EMISIÓN: 8/7/2014 FECHA DE EJECUCIÓN FECHA DE OTQ 10 CONDICIONES CLIMÁTICAS FECHA DE INICIO 29-Jul-2014 NUBLADO 07:00-12:00 FECHA FINAL 30-Sep-2014 SOLEADO 13:00-18:00 FECHA REPORTE 7-Aug-2014 LLUVIOSO PROGRESO GENERAL TABLA DE PORCENTAJES DE AVANCE PROGRAMADO Err:502 REPROGRAMADO TIPO DE INCIDENTE SIGNIFICATIVO : EJECUTADO 4.08% IMPORTANTE : STAND BY : DIFERENCIA Err:502 MENOR : HORAS PERDIDAS : DESCRIPCION DE ACTIVIDADES % PLANEADO ACTIVIDADES DIARIAS Err:502 4.08% 4.08% Predoblado de tubería A INGENIERÍA 87.50% 21.00% 21.00% 0.00% Balizado demarcarcatorio del eje de la tubería 87.50% 21.00% 0.00% 21.00% Desfile o regado de tubería B CONSTRUCCIÓN DE DERECHO DE VÍA 0.00% 71.10% 71.10% 0.00% Prueba OTDR 1 Topografía y replanteo 0.00% 56.25% 1.04% 55.21% 2 Desbroce manual y mecánico 0.00% 87.88% 1.52% 86.36% Err:502 3.02% 3.02% 0.00% 1 Desfile o Regado de tubería Err:502 61.13% 5.26% 55.88% 2 Doblado de tubería Err:502 0.00% 0.00% 0.00% 3 Soldadura de Tubería Err:502 0.00% 0.00% 0.00% 4 Instalación de scotch Kote 323 en juntas soldadas Err:502 0.00% 0.00% 0.00% 5 Prueba de holiday Err:502 0.00% 0.00% 0.00% 6 Reparación del revestimiento externo Err:502 0.00% 0.00% 0.00% 7 Instalación de marcos H 0.00% 0.00% 0.00% 0.00% 8 Zanjado Err:502 0.00% 0.00% 0.00% ACTIVIDADES PROGRAMADAS 9 Bajado de tubería Err:502 0.00% 0.00% 0.00% Predoblado de tubería 10 Tapado (Incluye reconformación) Err:502 0.00% 0.00% 0.00% Topografía del eje de la tubería 11 Conexionado de lingadas de tubería soldada (Tie-ins) 0.00% 0.00% 0.00% 0.00% 12 Cruces de vía y plataforma 0.00% 0.00% 0.00% 0.00% Err:502 0.00% 0.00% 0.00% Err:502 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Err:502 0.00% 0.00% 0.00% Err:502 0.00% 0.00% 0.00% Err:502 0.00% 0.00% 0.00% 5 Soportes tubería, incluye cimentación y soportería Err:502 0.00% 0.00% 0.00% 6 Prueba Hidrostática de baja presión <= 3000 psi Err:502 0.00% 0.00% 0.00% Err:502 0.00% 0.00% 0.00% Err:502 0.00% 0.00% 0.00% REPORTE DIARIO DE OBRA (RDO) 05-RGT-024-01 SERVICIOS ESPECIALIZADOS PARA LA CONSTRUCCIÓN DE DUCTO DE TRANSFERENCIA DE 8” DE 800 METROS, DESDE ESTACIÓN PAYAMINO HACIA DUCTO DE 12” GACELA - EST. COCA – BLOQUE 7 DE PAM EP % REAL % AVANCE REAL DIARIO % AVANCE REAL ACUMULADO ANTERIOR SERVICIOS ESPECIALIZADOS PARA LA CONSTRUCCIÓN DE DUCTO DE TRANSFERENCIA DE 8” DE 800 METROS, DESDE ESTACIÓN PAYAMINO HACIA DUCTO DE 12” GACELA - EST. COCA – BLOQUE 7 DE PAM EP 1 Ingeniería: incluye validación, planos de detalle, levantamiento AS BUILT de la línea de flujo. C CONSTRUCCION: DUCTO DE TRANSFERENCIA DE 8” DE 800 METROS, DESDE ESTACIÓN PAYAMINO HACIA DUCTO DE 12” GACELA - EST. COCA. 13 Limpieza de tubería, marraneado y prueba hidrostática (Incluye costo de contratación de empresa verificadora) D CONSTRUCCION, SOLDADURA, MONTAJE Y PINTURA DE INTERCONEXIÓN DE 6" 1 Soldadura de Tubería de acero al carbono A-106, Grado B, de acuerdo a normas ASME B31.3 o similar. 2 Montaje e instalación de ¨spools¨ prefabricados de tubería de acero al carbono A-106, Grado B, de acuerdo a normas ASME B31.3 o similar. 3 Instalación de elementos bridados ANSI 300# tales como válvulas, filtros, equipos de medición, filtros en Y, de diámetros mayores a 4 pulgadas y de hasta 12 pulgadas de diámetro nominal 4 Soldadura de juntas de campo para tubería de acero al carbono A-106, Grado B, de acuerdo a normas ASME B31.3 o similar. 7 Sandbalsting y aplicación de primer en tuberías de acero al carbono (inorgánico de zinc) 8 Sandbalsting para anclaje de pintura y aplicación de la segunda y tercera capa de revestimiento epóxico y poliuretano en tuberías de acero al carbono

Upload: fernando-quinonez

Post on 26-Dec-2015

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Rdo 10- Os 123895 - c&f - 07.08.2014 - Ducto de Transferencia Payamino - Gacela-est Coca

SISTEMA DE GESTION DE CALIDAD

CONTRATO No.: N/A CONTRATISTA: CYFOIL CIA. LTDA.

PROYECTO: # OT/OS: OS 123895

REG. No.: 07B020-05-RGT-024-01-010 LOCACION: BLOQUE 7 - PAYAMINO

FECHA DE EMISIÓN: 8/7/2014

FECHA DE EJECUCIÓN FECHA DE OTQ

10CONDICIONES CLIMÁTICAS

FECHA DE INICIO 29-Jul-2014 NUBLADO 07:00-12:00 5hFECHA FINAL 30-Sep-2014 SOLEADO 13:00-18:00 5hFECHA REPORTE 7-Aug-2014 LLUVIOSO

PROGRESO GENERAL TABLA DE PORCENTAJES DE AVANCEPROGRAMADO Err:502REPROGRAMADO

TIPO DE INCIDENTE

SIGNIFICATIVO :

EJECUTADO 4.08% IMPORTANTE : STAND BY :

DIFERENCIA Err:502 MENOR : HORAS PERDIDAS :

DESCRIPCION DE ACTIVIDADES % PLANEADO ACTIVIDADES DIARIAS

Err:502 4.08% 4.08% Predoblado de tubería

A INGENIERÍA 87.50% 21.00% 21.00% 0.00% Balizado demarcarcatorio del eje de la tubería

87.50% 21.00% 0.00% 21.00% Desfile o regado de tubería

B CONSTRUCCIÓN DE DERECHO DE VÍA 0.00% 71.10% 71.10% 0.00% Prueba OTDR

1 Topografía y replanteo 0.00% 56.25% 1.04% 55.21%

2 Desbroce manual y mecánico 0.00% 87.88% 1.52% 86.36%

Err:502 3.02% 3.02% 0.00%

1 Desfile o Regado de tubería Err:502 61.13% 5.25% 55.88%

2 Doblado de tubería Err:502 0.00% 0.00% 0.00%

3 Soldadura de Tubería Err:502 0.00% 0.00% 0.00%

4 Instalación de scotch Kote 323 en juntas soldadas Err:502 0.00% 0.00% 0.00%

5 Prueba de holiday Err:502 0.00% 0.00% 0.00%

6 Reparación del revestimiento externo Err:502 0.00% 0.00% 0.00%

7 Instalación de marcos H 0.00% 0.00% 0.00% 0.00%

8 Zanjado Err:502 0.00% 0.00% 0.00% ACTIVIDADES PROGRAMADAS

9 Bajado de tubería Err:502 0.00% 0.00% 0.00% Predoblado de tubería

10 Tapado (Incluye reconformación) Err:502 0.00% 0.00% 0.00% Topografía del eje de la tubería

11 Conexionado de lingadas de tubería soldada (Tie-ins) 0.00% 0.00% 0.00% 0.00%

12 Cruces de vía y plataforma 0.00% 0.00% 0.00% 0.00%

Err:502 0.00% 0.00% 0.00%

Err:502 0.00% 0.00% 0.00%

0.00% 0.00% 0.00% 0.00%

Err:502 0.00% 0.00% 0.00%

Err:502 0.00% 0.00% 0.00%

Err:502 0.00% 0.00% 0.00%

5 Soportes tubería, incluye cimentación y soportería Err:502 0.00% 0.00% 0.00%

6 Prueba Hidrostática de baja presión <= 3000 psi Err:502 0.00% 0.00% 0.00%

Err:502 0.00% 0.00% 0.00%

Err:502 0.00% 0.00% 0.00%

REPORTE DIARIO DE OBRA (RDO)05-RGT-024-01

SERVICIOS ESPECIALIZADOS PARA LA CONSTRUCCIÓN DE DUCTO DE TRANSFERENCIA DE 8” DE 800 METROS, DESDE ESTACIÓN PAYAMINO HACIA DUCTO

DE 12” GACELA - EST. COCA – BLOQUE 7 DE PAM EP

% REAL

%AVANCE REAL

DIARIO

%AVANCE REAL

ACUMULADO ANTERIOR

SERVICIOS ESPECIALIZADOS PARA LA CONSTRUCCIÓN DE DUCTO DE TRANSFERENCIA DE 8” DE 800 METROS, DESDE ESTACIÓN PAYAMINO HACIA DUCTO DE 12” GACELA - EST. COCA – BLOQUE 7 DE PAM EP

1 Ingeniería: incluye validación, planos de detalle, levantamiento AS BUILT de la línea de flujo.

C CONSTRUCCION: DUCTO DE TRANSFERENCIA DE 8” DE 800 METROS, DESDE ESTACIÓN PAYAMINO HACIA DUCTO DE 12” GACELA - EST. COCA.

13 Limpieza de tubería, marraneado y prueba hidrostática (Incluye costo de contratación de empresa verificadora)

D CONSTRUCCION, SOLDADURA, MONTAJE Y PINTURA DE INTERCONEXIÓN DE 6"

1 Soldadura de Tubería de acero al carbono A-106, Grado B, de acuerdo a normas ASME B31.3 o similar.

2 Montaje e instalación de ¨spools¨ prefabricados de tubería de acero al carbono A-106, Grado B, de acuerdo a normas ASME B31.3 o similar.

3 Instalación de elementos bridados ANSI 300# tales como válvulas, filtros, equipos de medición, filtros en Y, de diámetros mayores a 4 pulgadas y de hasta 12 pulgadas de diámetro nominal

4 Soldadura de juntas de campo para tubería de acero al carbono A-106, Grado B, de acuerdo a normas ASME B31.3 o similar.

7 Sandbalsting y aplicación de primer en tuberías de acero al carbono (inorgánico de zinc)

8 Sandbalsting para anclaje de pintura y aplicación de la segunda y tercera capa de revestimiento epóxico y poliuretano en tuberías de acero al carbono

Page 2: Rdo 10- Os 123895 - c&f - 07.08.2014 - Ducto de Transferencia Payamino - Gacela-est Coca

SISTEMA DE GESTION DE CALIDAD

CONTRATO No.: N/A CONTRATISTA: CYFOIL CIA. LTDA.

PROYECTO: # OT/OS: OS 123895

REG. No.: 07B020-05-RGT-024-01-010 LOCACION: BLOQUE 7 - PAYAMINO

FECHA DE EMISIÓN: 8/7/2014

FECHA DE EJECUCIÓN FECHA DE OTQ

10CONDICIONES CLIMÁTICAS

FECHA DE INICIO 29-Jul-2014 NUBLADO 07:00-12:00 5hFECHA FINAL 30-Sep-2014 SOLEADO 13:00-18:00 5hFECHA REPORTE 7-Aug-2014 LLUVIOSO

REPORTE DIARIO DE OBRA (RDO)05-RGT-024-01

SERVICIOS ESPECIALIZADOS PARA LA CONSTRUCCIÓN DE DUCTO DE TRANSFERENCIA DE 8” DE 800 METROS, DESDE ESTACIÓN PAYAMINO HACIA DUCTO

DE 12” GACELA - EST. COCA – BLOQUE 7 DE PAM EP

Err:502 1.95% 1.95% 0.00%

0.00% 0.00% 0.00% 0.00%

Err:502 0.00% 0.00% 0.00%

Err:502 0.00% 0.00% 0.00% OBSERVACIONES C&F OBSERVACIONES FISCALIZACIÓN

4 Instalación de biducto (incluye cama de arena en el área de plataforma) Err:502 0.00% 0.00% 0.00%

5 Instalación de fibra óptica en biducto (dos corridas) Err:502 0.00% 0.00% 0.00%

Err:502 0.00% 0.00% 0.00%

7 Empalmes (splices) de cable fibra óptica (24 fibras) Err:502 0.00% 0.00% 0.00%

8 Instalación de terminaciones de cable de fibra óptica en ODF´s Err:502 0.00% 0.00% 0.00%

9 Prueba OTDR bidireccional y de potencia para cable de hasta 24 hilos Err:502 33.33% 0.00% 33.33%

10 Instalación de panel comunicaciones COMM Err:502 0.00% 0.00% 0.00%

F SISTEMA DE PROTECCION CATODICA Err:502 0.00% 0.00% 0.00%

Err:502 0.00% 0.00% 0.00%

REPORTE PROGRAMADO & EJECUTADO REPORTE FOTOGRAFICO

PERSONAL EQUIPOS

DESCRIPCIÓN CANTIDADCANTIDADES

DESCRIPCIÓN CANTIDADCANTIDADES

AYER (H) HOY (H) ACUMULADO (H) AYER (H) HOY (H) ACUMULADO(H)

Superintendente 1 90 10 100 Camioneta 4X4 1 100 10 110

Control de Proyectos 1 90 10 100 Buseta 0 0 0 0

Asistente de Control de Proyectos 0 0 0 0 Bus 0 0 0 0

Control de Documentos 0 0 0 0 Excavadora 1 40 10 50

Supervisor Civil 0 0 0 0 Retroexcavadora 0 0 0 0

Supervisor Mecánico 0 0 0 0 Tractor 0 0 0 0

Supervisor Eléctrico 2 180 20 200 Concretera 0 0 0 0

Ingeniero de Diseño 2 180 20 200 Volqueta 0 0 0 0

Supervisor QA/QC Civil 0 0 0 0 Motosoldadora a diesel 0 0 0 0

Supervisor QA/QC Mecánico 1 90 10 100 Equipo de oxicorte 0 0 0 0

Supervisor QA/QC Eléctrico 0 0 0 0 Cama alta de 2 ejes 1 20 10 30

Supervisor QA/QC Instrumentación 0 0 0 0 Cama baja de 3 ejes 0 0 0 0

Supervisor HES (SSA) 1 90 10 100 Camión con equipo de suelda 0 0 0 0

Paramédico 1 90 10 100 Camion Grúa 1 40 10 50

Topógrafo 1 40 10 50 Bomba de agua 0 0 0 0

Cadenero 2 80 20 100 Estación Total 1 30 10 40

Bodeguero-Adm 1 90 10 100 Nivel automático 0 0 0 0

Operador 1 40 10 50 Grúa de castillo 0 0 0 0

Chofer 2 130 20 150 Martillo de Pilotaje 0 0 0 0

Ayudante Equipo Pesado 1 40 10 50 Rodillo Compactador 0 0 0 0

Soldador API 0 0 0 0 Tanquero de agua 0 0 0 0

Soldador ASME 0 0 0 0 Camión Grua 5 ton. 0 0 0 0

Capataz 1 40 10 50 Vibroapisonador 0 0 0 0

Fierrero 0 0 0 0 Vibrador manual de Plancha 0 0 0 0

Carpintero 0 0 0 0 Tanquero de combustible 0 0 0 0

Albañil 0 0 0 0 Medidor de Densidades 0 0 0 0

Ayudante Civil 0 0 0 0

Soldador estructural AWS 0 0 0 0

Esmerilador 0 0 0 0

Ayudante de soldador 0 0 0 0

Eléctrico A 0 0 0 0

Eléctrico B 0 0 0 0

Doblador 2 40 20 60

Instrumentista A 0 0 0 0

Instrumentista B 0 0 0 0

Ayudante de Instrumentación 0 0 0 0

Guardia 0 0 0 0

Obreros 6 240 60 300

Médico 0 0 0 0 0

Total Personal 26 1550 260 1810 Total Equipo y Herramientas 5 230 50 280

ELABORADO POR (CONTRATISTA DE CONSTRUCCIÓN) APROBADO POR (FISCALIZACIÓN) RECIBIDO POR (FACILIDADES PAM EP)

Nombre: LUIS CÁRDENAS/FERNANDO COELLO Nombre: EDWIN GUAMANQUISPE / CARLOS JIMENEZ Nombre: MILTON VILLACIS / RAÚL CARRASCO

E INSTALACION DE CABLE DE FIBRA OPTICA DESDE ESTACION PAYAMINO HACIA DDV GACELA - COCA

1 Construcción de cajas de hormigón armado (f’c= 210 Kg/cm2), incluye tapa metálica

2 Instalación de tubería de PVC de 4" en el area de plataforma (incluye cama de arena)

3 Ingreso de cable de fibra óptica hacia cuarto del operador incluye instalación de bandejas y soportes

6 Instalación de PVC de 4" para protección de biducto en cruces especiales, plataformas, pantanos y esteros (para cruces de vía se instalará casing 3 1/2")

1 Instalación de SPC: (incluye ingeniería, procura de materiales, señalética y comisionado y puesta en marcha).

29-Ju

l

31-Ju

l

2-Au

g

4-Au

g

6-Au

g

8-Au

g

10-A

ug

12-A

ug

14-A

ug

16-A

ug

18-A

ug

20-A

ug

22-A

ug

24-A

ug

26-A

ug

28-A

ug

30-A

ug

1-Se

p

3-Se

p

5-Se

p

7-Se

p

9-Se

p

11-S

ep

13-S

ep

15-S

ep

17-S

ep

19-S

ep

21-S

ep

23-S

ep

25-S

ep

27-S

ep

29-S

ep

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

Programado Real

1-oc

t

Predoblado de tubería Predoblado de tuberíaRegado, desfile de tubería

Page 3: Rdo 10- Os 123895 - c&f - 07.08.2014 - Ducto de Transferencia Payamino - Gacela-est Coca

SISTEMA DE GESTION DE CALIDAD

CONTRATO No.: N/A CONTRATISTA: CYFOIL CIA. LTDA.

PROYECTO: # OT/OS: OS 123895

REG. No.: 07B020-05-RGT-024-01-010 LOCACION: BLOQUE 7 - PAYAMINO

FECHA DE EMISIÓN: 8/7/2014

FECHA DE EJECUCIÓN FECHA DE OTQ

10CONDICIONES CLIMÁTICAS

FECHA DE INICIO 29-Jul-2014 NUBLADO 07:00-12:00 5hFECHA FINAL 30-Sep-2014 SOLEADO 13:00-18:00 5hFECHA REPORTE 7-Aug-2014 LLUVIOSO

REPORTE DIARIO DE OBRA (RDO)05-RGT-024-01

SERVICIOS ESPECIALIZADOS PARA LA CONSTRUCCIÓN DE DUCTO DE TRANSFERENCIA DE 8” DE 800 METROS, DESDE ESTACIÓN PAYAMINO HACIA DUCTO

DE 12” GACELA - EST. COCA – BLOQUE 7 DE PAM EP

Cargo: SUPERVISOR DE CONSTRUCCIONES Cargo: FISCALIZADOR Cargo: SUPERVISOR PAM EP

Fecha: 7-Aug-14 Fecha: 7-Aug-14 Fecha: 7-Aug-14

Page 4: Rdo 10- Os 123895 - c&f - 07.08.2014 - Ducto de Transferencia Payamino - Gacela-est Coca

REPORTE DIARIO DE OBRA

### ###

CLIENTE: PETROAMAZONAS EP FECHA INICIAL: 29-Jul-14 PROGRESO CLIMA HOY ACUM REPORTE

CONTRATO / OTQ / OS: 123895 FECHA FINAL: 30-Sep-14 PROGRAMADO Err:502 ###SOLEADO 5 55

10CONTRATISTA: CYFOIL CIA. LTDA. SALDO DÍAS: 54 EJECUTADO 4.08% ###LLUVIOSO 5 45

FECHA: Thursday, August 7, 2014 COSTO OS: $ 483,326.87 DIFERENCIA Err:502 TOTAL 10 100

PESO GLOBAL AVANCE ANTERIOR AVANCE DIARIO AVANCE ACUMULADO

ITEM DESCRIPCIÓN U/M CANT. EST. CANT CANT (%) HOY CANT Inc. Total

100.00% 0.00% 0.00% 4.08% 4.08%

A INGENIERÍA 2.18% 0.00% 0.00% 21.00% 0.46%

1.0 GLB 1.00 2.18% 0.21 21.00% 0.00 0.00% 0.00% 0.21 21.00% 0.46%

B CONSTRUCCIÓN DE DERECHO DE VÍA 0.71% 1.27% 0.01% 71.10% 0.51%

1.0 Topografía y replanteo Ha 0.48 0.38% 0.27 55.21% 0.01 1.04% 0.00% 0.27 56.25% 0.21%

2.0 Desbroce manual y mecánico Ha 0.33 0.33% 0.29 86.36% 0.01 1.52% 0.01% 0.29 87.88% 0.29%

C 57.40% 0.26% 0.15% 3.02% 1.73%

1.0 Desfile o Regado de tubería Pulg – m 6,400.00 2.83% 3576.00 55.88% 336.00 5.25% 0.15% 3912.00 61.13% 1.73%

2.0 Doblado de tubería Pulg – m 6,400.00 3.11% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

3.0 Soldadura de Tubería Pulg – m 6,400.00 13.40% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

4.0 Instalación de scotch Kote 323 en juntas soldadas m2 16.00 0.54% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

5.0 Prueba de holiday Pulg – m 6,400.00 1.79% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

6.0 Reparación del revestimiento externo Pulg – m 6,400.00 1.68% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

7.0 Instalación de marcos H Tons 1.50 1.43% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

8.0 Zanjado Pulg – m 4,400.00 1.42% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

9.0 Bajado de tubería Pulg – m 4,400.00 2.08% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

10.0 Tapado (Incluye reconformación) Pulg – m 4,400.00 1.62% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

11.0 Conexionado de lingadas de tubería soldada (Tie-ins) Pulg – Diametral 88.00 1.84% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

12.0 Cruces de vía y plataforma Pulg – m 2,000.00 22.58% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

13.0 Pulg – m 6,400.00 3.09% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

D CONSTRUCCION, SOLDADURA, MONTAJE Y PINTURA DE INTERCONEXIÓN 12.64% 0.00% 0.00% 0.00% 0.00%

1.0 Pulg - Diametral 288.00 5.66% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

2.0 Pulg – m 360.00 1.15% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

3.0 Pulg - Diametral 84.00 0.98% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

4.0 Pulg - Diametral 90.00 1.88% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

5.0 Soportes tubería, incluye cimentación y soportería GLB 1.00 1.73% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

6.0 Prueba Hidrostática de baja presión <= 3000 psi Pulg – m 240.00 0.58% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

7.0 m2 24.00 0.29% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

8.0 m2 24.00 0.37% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

E INSTALACION DE CABLE DE FIBRA OPTICA DESDE ESTACION PAYAMINO 71.10% 0.00% 0.00% 1.95% 1.39%

1.0 m3 7.00 2.18% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

2.0 m 68.00 0.54% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

3.0 m 20.00 0.22% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

4.0 Instalación de biducto (incluye cama de arena en el área de plataforma) m 750.00 1.82% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

5.0 Instalación de fibra óptica en biducto (dos corridas) m 1,800.00 4.20% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

6.0 m 20.00 0.17% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

7.0 Empalmes (splices) de cable fibra óptica (24 fibras) u 2.00 1.45% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

8.0 Instalación de terminaciones de cable de fibra óptica en ODF´s u 2.00 2.64% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

9.0 Prueba OTDR bidireccional y de potencia para cable de hasta 24 hilos u 3.00 2.79% 1.00 33.33% 0.00 0.00% 0.00% 1.00 33.33% 0.93%

10.0 Instalación de panel comunicaciones COMM u 1.00 1.81% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

F SISTEMA DE PROTECCION CATODICA 71.10% 0.00% 0.00% 0.00% 0.00%

1.0 GLB 1.00 9.26% 0.00 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%

100.00% 0.00% 0.46%

CURVA DE AVANCE PORCENTUAL DE LA OBRA CURVA DE AVANCE ECONOMICO DE LA OBRA

SERVICIOS ESPECIALIZADOS PARA LA CONSTRUCCIÓN DE DUCTO DE TRANSFERENCIA DE 8” DE 800 METROS, DESDE ESTACIÓN PAYAMINO HACIA DUCTO DE 12” GACELA - EST. COCA – BLOQUE 7 DE PAM EP

PONDERADO

(%) sobre incidencia

(%) sobre incidencia

(%) sobre incidencia

SERVICIOS ESPECIALIZADOS PARA LA CONSTRUCCIÓN DE DUCTO DE TRANSFERENCIA DE 8” DE 800 METROS, DESDE ESTACIÓN PAYAMINO HACIA DUCTO DE 12” GACELA - EST. COCA – BLOQUE 7 DE PAM EP

Ingeniería: incluye validación, planos de detalle, levantamiento AS BUILT de la línea de flujo.

CONSTRUCCION: DUCTO DE TRANSFERENCIA DE 8” DE 800 METROS, DESDE ESTACIÓN PAYAMINO HACIA DUCTO DE 12” GACELA - EST. COCA.

Limpieza de tubería, marraneado y prueba hidrostática (Incluye costo de contratación de empresa verificadora)

Soldadura de Tubería de acero al carbono A-106, Grado B, de acuerdo a normas ASME B31.3 o similar.

Montaje e instalación de ¨spools¨ prefabricados de tubería de acero al carbono A-106, Grado B, de acuerdo a normas ASME B31.3 o similar.

Instalación de elementos bridados ANSI 300# tales como válvulas, filtros, equipos de medición, filtros en Y, de diámetros mayores a 4 pulgadas y de hasta 12 pulgadas de diámetro nominal

Soldadura de juntas de campo para tubería de acero al carbono A-106, Grado B, de acuerdo a normas ASME B31.3 o similar.

Sandbalsting y aplicación de primer en tuberías de acero al carbono (inorgánico de zinc)

Sandbalsting para anclaje de pintura y aplicación de la segunda y tercera capa de revestimiento epóxico y poliuretano en tuberías de acero al carbono

Construcción de cajas de hormigón armado (f’c= 210 Kg/cm2), incluye tapa metálica

Instalación de tubería de PVC de 4" en el area de plataforma (incluye cama de arena)

Ingreso de cable de fibra óptica hacia cuarto del operador incluye instalación de bandejas y soportes

Instalación de PVC de 4" para protección de biducto en cruces especiales, plataformas, pantanos y esteros (para cruces de vía se instalará casing 3 1/2")

Instalación de SPC: (incluye ingeniería, procura de materiales, señalética y comisionado y puesta en marcha).

29-Ju

l31

-Jul

2-Au

g4-

Aug

6-Au

g8-

Aug

10-A

ug12

-Aug

14-A

ug16

-Aug

18-A

ug20

-Aug

22-A

ug24

-Aug

26-A

ug28

-Aug

30-A

ug1-

Sep

3-Se

p5-

Sep

7-Se

p9-

Sep

11-S

ep13

-Sep

15-S

ep17

-Sep

19-S

ep21

-Sep

23-S

ep25

-Sep

27-S

ep29

-Sep

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

Programado

Real

29-Ju

l31

-Jul

2-Au

g4-

Aug

6-Au

g8-

Aug

10-A

ug12

-Aug

14-A

ug16

-Aug

18-A

ug20

-Aug

22-A

ug24

-Aug

26-A

ug28

-Aug

30-A

ug1-

Sep

3-Se

p5-

Sep

7-Se

p9-

Sep

11-S

ep13

-Sep

15-S

ep17

-Sep

19-S

ep21

-Sep

23-S

ep25

-Sep

27-S

ep29

-Sep

0

100000

200000

300000

400000

500000

Programado

Real

14-n

ov --

14-n

ov-

Page 5: Rdo 10- Os 123895 - c&f - 07.08.2014 - Ducto de Transferencia Payamino - Gacela-est Coca

REPORTE DIARIO DE OBRA

### ###

CLIENTE: PETROAMAZONAS EP FECHA INICIAL: 29-Jul-14 PROGRESO CLIMA HOY ACUM REPORTE

CONTRATO / OTQ / OS: 123895 FECHA FINAL: 30-Sep-14 PROGRAMADO Err:502 ###SOLEADO 5 55

10CONTRATISTA: CYFOIL CIA. LTDA. SALDO DÍAS: 54 EJECUTADO 4.08% ###LLUVIOSO 5 45

FECHA: Thursday, August 7, 2014 COSTO OS: $ 483,326.87 DIFERENCIA Err:502 TOTAL 10 100

SERVICIOS ESPECIALIZADOS PARA LA CONSTRUCCIÓN DE DUCTO DE TRANSFERENCIA DE 8” DE 800 METROS, DESDE ESTACIÓN PAYAMINO HACIA DUCTO DE 12” GACELA - EST. COCA – BLOQUE 7 DE PAM EP

ACTIVIDADES DEL DIA ACTIVIDADES PROGRAMADAS

1 Predoblado de tubería 1 Predoblado de tubería

2 Balizado demarcarcatorio del eje de la tubería 2 Topografía del eje de la tubería

3 Desfile o regado de tubería 3

4 4

5 5

6 6

Firma: Firma: Firma:

Nombre: LUIS CÁRDENAS/FERNANDO COELLO Nombre: EDWIN GUAMANQUISPE / CARLOS JIMENEZ Nombre: MILTON VILLACIS / RAÚL CARRASCO

REPRESENTANTE DE CYFOIL FISCALIZADOR PAM EP SUPERVISOR PAM EP

Page 6: Rdo 10- Os 123895 - c&f - 07.08.2014 - Ducto de Transferencia Payamino - Gacela-est Coca

REPORTE DIARIO DE OBRA

### ###

CLIENTE: PETROAMAZONAS EP FECHA INICIAL: 29-Jul-14 PROGRESO CLIMA HOY ACUM REPORTE

CONTRATO / OTQ / OS: 123895 FECHA FINAL: 30-Sep-14 PROGRAMADO Err:502 ###SOLEADO 5 55

10CONTRATISTA: CYFOIL CIA. LTDA. SALDO DÍAS: 54 EJECUTADO 4.08% ###LLUVIOSO 5 45

FECHA: Thursday, August 7, 2014 COSTO OS: $ 483,326.87 DIFERENCIA Err:502 TOTAL 10 100

SERVICIOS ESPECIALIZADOS PARA LA CONSTRUCCIÓN DE DUCTO DE TRANSFERENCIA DE 8” DE 800 METROS, DESDE ESTACIÓN PAYAMINO HACIA DUCTO DE 12” GACELA - EST. COCA – BLOQUE 7 DE PAM EP

Descripción Hoy Acumulado Observaciones Capacitación de seguridad

Accidentes - - Tema Charla Tiempo T. Acumulado

Incidentes - - El manejo de extintores 15 minutos 150 minutos

Días perdidos - -

PERSONAL EQUIPOS

DESCRIPCIÓN / CARGO Cant. DESCRIPCIÓN Cantidad

Superintendente 1 10 90 100 Camioneta 4X4 1 10 100 110

Control de Proyectos 1 10 90 100 Buseta 0 0 0 0

Asistente de Control de Proyectos 0 0 0 0 Bus 0 0 0 0

Control de Documentos 0 0 0 0 Excavadora 1 10 40 50

Supervisor Civil 0 0 0 0 Retroexcavadora 0 0 0 0

Supervisor Mecánico 0 0 0 0 Tractor 0 0 0 0

Supervisor Eléctrico 2 20 180 200 Concretera 0 0 0 0

Ingeniero de Diseño 2 20 180 200 Volqueta 0 0 0 0

Supervisor QA/QC Civil 0 0 0 0 Motosoldadora a diesel 0 0 0 0

Supervisor QA/QC Mecánico 1 10 90 100 Equipo de oxicorte 0 0 0 0

Supervisor QA/QC Eléctrico 0 0 0 0 Cama alta de 2 ejes 1 10 20 30

Supervisor QA/QC Instrumentación 0 0 0 0 Cama baja de 3 ejes 0 0 0 0

Supervisor HES (SSA) 1 10 90 100 Camión con equipo de suelda 0 0 0 0

Paramédico 1 10 90 100 Camion Grúa 1 10 40 50

Topógrafo 1 10 40 50 Bomba de agua 0 0 0 0

Cadenero 2 20 80 100 Estación Total 1 10 30 40

Bodeguero-Adm 1 10 90 100 Nivel automático 0 0 0 0

Operador 1 10 40 50 Grúa de castillo 0 0 0 0

Chofer 2 20 130 150 Martillo de Pilotaje 0 0 0 0

Ayudante Equipo Pesado 1 10 40 50 Rodillo Compactador 0 0 0 0

Soldador API 0 0 0 0 Tanquero de agua 0 0 0 0

Soldador ASME 0 0 0 0 Camión Grua 5 ton. 0 0 0 0

Capataz 1 10 40 50 Vibroapisonador 0 0 0 0

Fierrero 0 0 0 0 Vibrador manual de Plancha 0 0 0 0

Carpintero 0 0 0 0 Tanquero de combustible 0 0 0 0

Albañil 0 0 0 0 Medidor de Densidades 0 0 0 0

Ayudante Civil 0 0 0 0

Soldador estructural AWS 0 0 0 0

Esmerilador 0 0 0 0

Ayudante de soldador 0 0 0 0

Eléctrico A 0 0 0 0

Eléctrico B 0 0 0 0

Doblador 2 20 40 60

Instrumentista A 0 0 0 0

Instrumentista B 0 0 0 0

Ayudante de Instrumentación 0 0 0 0

Guardia 0 0 0 0

Obreros 6 60 240 300

Médico 0 0 0 0

TOTAL 26 260 1,550 1,810 TOTAL 5 50 230 280

NOVEDADES DEL DIA

CYFOIL:

Petroamazonas EP:

FOTOGRAFÍAS

Firma: Firma:

Nombre: LUIS CÁRDENAS/FERNANDO COELLO EDWIN GUAMANQUISPE / CARLOS JIMENEZ Nombre: MILTON VILLACIS / RAÚL CARRASCO

REPRESENTANTE DE CYFOIL SUPERVISOR PAM EP

Horas DíaHoy

Horas díaAyer

Horas día Acumulado

Horas DíaHoy

Horas día Ayer

Horas día Acumulado

Page 7: Rdo 10- Os 123895 - c&f - 07.08.2014 - Ducto de Transferencia Payamino - Gacela-est Coca

FECHA DE REPORTE 7 de agosto de 2014

No. DE REPORTE 10

REPORTE DE PROGRESO DEL PROYECTO

PROGRESO EJECUTADO PLANIFICACIÓN TASAS

ÍTEM DESCRIPCION UNIDAD ADICIONALUnidad/día %

Err:502 Err:502

A INGENIERÍA

1 1.00 0.21 0.00 0.21 0.79 8/1/2014 8/8/2014 0.27% 2.18% 0.46%

B CONSTRUCCIÓN DE DERECHO DE VÍA

1 0.48 0.27 0.01 0.27 0.21 8/9/2014 8/15/2014 0.05% 0.38% 0.21%

2 0.33 0.29 0.01 0.29 0.04 8/9/2014 8/15/2014 0.05% 0.33% 0.29%

C CONSTRUCCION: DUCTO DE TRANSFERENCIA DE 8” DE 800 METROS, DESDE ESTACIÓN PAYAMINO HACIA DUCTO DE 12” GACELA - EST. COCA.

1 6,400.00 3576.00 336.00 3912.00 2488.00 Err:502 Err:502 0.94% 2.83% 1.73%

2 6,400.00 0.00 0.00 0.00 6400.00 Err:502 Err:502 0.21% 3.11% 0.00%

3 6,400.00 0.00 0.00 0.00 6400.00 Err:502 Err:502 0.61% 13.40% 0.00%

4 m2 16.00 0.00 0.00 0.00 16.00 Err:502 Err:502 0.02% 0.54% 0.00%

5 6,400.00 0.00 0.00 0.00 6400.00 Err:502 Err:502 0.08% 1.79% 0.00%

6 6,400.00 0.00 0.00 0.00 6400.00 Err:502 Err:502 0.07% 1.68% 0.00%

7 1.50 0.00 0.00 0.00 1.50 9/8/2014 9/9/2014 0.71% 1.43% 0.00%

8 4,400.00 0.00 0.00 0.00 4400.00 Err:502 Err:502 0.06% 1.42% 0.00%

9 4,400.00 0.00 0.00 0.00 4400.00 Err:502 Err:502 0.09% 2.08% 0.00%

10 4,400.00 0.00 0.00 0.00 4400.00 Err:502 Err:502 0.07% 1.62% 0.00%

11 88.00 0.00 0.00 0.00 88.00 9/10/2014 9/14/2014 0.37% 1.84% 0.00%

12 2,000.00 0.00 0.00 0.00 2000.00 9/10/2014 9/14/2014 4.52% 22.58% 0.00%

13 6,400.00 0.00 0.00 0.00 6400.00 Err:502 Err:502 1.03% 3.09% 0.00%

D CONSTRUCCION, SOLDADURA, MONTAJE Y PINTURA DE INTERCONEXIÓN DE 6"

1 288.00 0.00 0.00 0.00 288.00 9/10/2014 9/14/2014 1.13% 5.66% 0.00%

2 360.00 0.00 0.00 0.00 360.00 Err:502 Err:502 0.38% 1.15% 0.00%

3 84.00 0.00 0.00 0.00 84.00 Err:502 Err:502 0.33% 0.98% 0.00%

4 90.00 0.00 0.00 0.00 90.00 Err:502 Err:502 0.63% 1.88% 0.00%

5 1.00 0.00 0.00 0.00 1.00 Err:502 Err:502 0.35% 1.73% 0.00%

6 240.00 0.00 0.00 0.00 240.00 Err:502 Err:502 0.10% 0.58% 0.00%

7 m2 24.00 0.00 0.00 0.00 24.00 Err:502 Err:502 0.14% 0.29% 0.00%

8 m2 24.00 0.00 0.00 0.00 24.00 Err:502 Err:502 0.19% 0.37% 0.00%

E INSTALACION DE CABLE DE FIBRA OPTICA DESDE ESTACION PAYAMINO HACIA DDV GACELA - COCA

1 m3 7.00 0.00 0.00 0.00 7.00 8/9/2014 8/23/2014 0.15% 2.18% 0.00%

2 68.00 0.00 0.00 0.00 68.00 Err:502 Err:502 0.02% 0.54% 0.00%

3 20.00 0.00 0.00 0.00 20.00 Err:502 Err:502 0.04% 0.22% 0.00%

4 750.00 0.00 0.00 0.00 750.00 Err:502 Err:502 0.08% 1.82% 0.00%

5 1,800.00 0.00 0.00 0.00 1800.00 Err:502 Err:502 0.17% 4.20% 0.00%

6 20.00 0.00 0.00 0.00 20.00 Err:502 Err:502 0.01% 0.17% 0.00%

7 2.00 0.00 0.00 0.00 2.00 Err:502 Err:502 1.45% 1.45% 0.00%

8 2.00 0.00 0.00 0.00 2.00 Err:502 Err:502 2.64% 2.64% 0.00%

9 3.00 1.00 0.00 1.00 2.00 Err:502 Err:502 2.79% 2.79% 0.93%

10 1.00 0.00 0.00 0.00 1.00 Err:502 Err:502 0.36% 1.81% 0.00%

F SISTEMA DE PROTECCION CATODICA

1 1.00 0.00 0.00 0.00 1.00 Err:502 Err:502 0.21% 9.26% 0.00%

100.00%

REPRESENTANTE CONTRATISTA: REPRESENTANTE FISCALIZACIÓN: REPRESENTANTE PAM:

SERVICIOS ESPECIALIZADOS PARA LA CONSTRUCCIÓN DE DUCTO DE TRANSFERENCIA DE 8” DE 800 METROS, DESDE ESTACIÓN PAYAMINO HACIA

DUCTO DE 12” GACELA - EST. COCA – BLOQUE 7 DE PAM EP

CANTIDAD ESTIMADA

AVANCE ANTERIOR

AVANCE DIARIO

AVANCE ACUMULADO

CANTIDAD POR

COMPLETAR

FECHA INICIO

FECHA FINAL

TASA REQUERIDA

PESO ACTIVIDAD PROGRESO

TOTAL

SERVICIOS ESPECIALIZADOS PARA LA CONSTRUCCIÓN DE DUCTO DE TRANSFERENCIA DE 8” DE 800 METROS, DESDE ESTACIÓN PAYAMINO HACIA DUCTO DE 12” GACELA - EST. COCA – BLOQUE 7 DE PAM EP

Ingeniería: incluye validación, planos de detalle, levantamiento AS BUILT de la línea de flujo. GLB

Topografía y replanteo Ha

Desbroce manual y mecánico Ha

Desfile o Regado de tubería Pulg – m

Doblado de tubería Pulg – m

Soldadura de Tubería Pulg – m

Instalación de scotch Kote 323 en juntas soldadas

Prueba de holiday Pulg – m

Reparación del revestimiento externo Pulg – m

Instalación de marcos H Tons

Zanjado Pulg – m

Bajado de tubería Pulg – m

Tapado (Incluye reconformación) Pulg – m

Conexionado de lingadas de tubería soldada (Tie-ins) Pulg – Diametral

Cruces de vía y plataforma Pulg – m

Limpieza de tubería, marraneado y prueba hidrostática (Incluye costo de contratación de empresa verificadora) Pulg – m

Soldadura de Tubería de acero al carbono A-106, Grado B, de acuerdo a normas ASME B31.3 o similar.

Pulg - Diametral

Montaje e instalación de ¨spools¨ prefabricados de tubería de acero al carbono A-106, Grado B, de acuerdo a normas ASME B31.3 o similar.

Pulg – m

Instalación de elementos bridados ANSI 300# tales como válvulas, filtros, equipos de medición, filtros en Y, de diámetros mayores a 4 pulgadas y de hasta 12 pulgadas de diámetro nominal

Pulg - Diametral

Soldadura de juntas de campo para tubería de acero al carbono A-106, Grado B, de acuerdo a normas ASME B31.3 o similar.

Pulg - Diametral

Soportes tubería, incluye cimentación y soportería GLB

Prueba Hidrostática de baja presión <= 3000 psi Pulg – m

Sandbalsting y aplicación de primer en tuberías de acero al carbono (inorgánico de zinc)

Sandbalsting para anclaje de pintura y aplicación de la segunda y tercera capa de revestimiento epóxico y poliuretano en tuberías de acero al carbono

Construcción de cajas de hormigón armado (f’c= 210 Kg/cm2), incluye tapa metálica

Instalación de tubería de PVC de 4" en el area de plataforma (incluye cama de arena) m

Ingreso de cable de fibra óptica hacia cuarto del operador incluye instalación de bandejas y soportes m

Instalación de biducto (incluye cama de arena en el área de plataforma) m

Instalación de fibra óptica en biducto (dos corridas) m

Instalación de PVC de 4" para protección de biducto en cruces especiales, plataformas, pantanos y esteros (para cruces de vía se instalará casing 3 1/2")

m

Empalmes (splices) de cable fibra óptica (24 fibras) u

Instalación de terminaciones de cable de fibra óptica en ODF´s u

Prueba OTDR bidireccional y de potencia para cable de hasta 24 hilos u

Instalación de panel comunicaciones COMM u

Instalación de SPC: (incluye ingeniería, procura de materiales, señalética y comisionado y puesta en marcha). GLB

Page 8: Rdo 10- Os 123895 - c&f - 07.08.2014 - Ducto de Transferencia Payamino - Gacela-est Coca

8/7/2014 Err:502 7/29/2014 7/29/2014 0 0.27%

29-J

ul

30-J

ul

31-J

ul

1-A

ug

2-A

ug

3-A

ug

483326.87

TOTAL INC. % No. DIAS FECHA INICIOPESO DIARIO Programado Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

% Real

$ 483,326.87 100.00% Err:502 7/29/2014 Err:502 Err:502 100.00% Err:502

$ 10,518.13 2.18% 8 01/08/2014 8/1/2014 8/8/2014 2.18% 87.50%

$ 10,518.13 $ 10,518.13 2.18% 8 01/08/2014 8/1/2014 8/8/2014 0.27% 87.50% 0.27% 0.27% 0.27%

$ 3,439.42 0.71% 7 09/08/2014 8/9/2014 8/15/2014 0.71% 0.00%

$ 3,800.41 $ 1,824.20 0.38% 7 09/08/2014 8/9/2014 8/15/2014 0.05% 0.00%

$ 4,894.61 $ 1,615.22 0.33% 7 09/08/2014 8/9/2014 8/15/2014 0.05% 0.00%

$ 277,446.80 57.40% Err:502 Err:502 Err:502 Err:502 57.40% Err:502

$ 2.14 $ 13,696.00 2.83% 3 Err:502 Err:502 Err:502 0.94% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 $ 2.35 $ 15,040.00 3.11% 15 Err:502 Err:502 Err:502 0.21% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 $ 10.12 $ 64,768.00 13.40% 22 Err:502 Err:502 Err:502 0.61% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 $ 163.79 $ 2,620.64 0.54% 23 Err:502 Err:502 Err:502 0.02% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 $ 1.35 $ 8,640.00 1.79% 23 Err:502 Err:502 Err:502 0.08% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 $ 1.27 $ 8,128.00 1.68% 23 Err:502 Err:502 Err:502 0.07% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 $ 4,605.28 $ 6,907.92 1.43% 2 08/09/2014 9/8/2014 9/9/2014 0.71% 0.00%

$ 1.56 $ 6,864.00 1.42% 24 Err:502 Err:502 Err:502 0.06% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 $ 2.28 $ 10,032.00 2.08% 24 Err:502 Err:502 Err:502 0.09% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 $ 1.78 $ 7,832.00 1.62% 24 Err:502 Err:502 Err:502 0.07% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

$ 100.98 $ 8,886.24 1.84% 5 10/09/2014 9/10/2014 9/14/2014 0.37% 0.00%

$ 54.56 $ 109,120.00 22.58% 5 10/09/2014 9/10/2014 9/14/2014 4.52% 0.00%

$ 2.33 $ 14,912.00 3.09% 3 Err:502 Err:502 Err:502 1.03% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

$ 61,084.89 12.64% Err:502 10/09/2014 Err:502 Err:502 12.64% Err:502

$ 95.06 $ 27,377.28 5.66% 5 10/09/2014 9/10/2014 9/14/2014 1.13% 0.00%

$ 15.44 $ 5,558.40 1.15% 3 Err:502 Err:502 Err:502 0.38% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

$ 56.20 $ 4,720.80 0.98% 3 Err:502 Err:502 Err:502 0.33% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

$ 100.98 $ 9,088.20 1.88% 3 Err:502 Err:502 Err:502 0.63% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

$ 8,369.49 $ 8,369.49 1.73% 5 Err:502 Err:502 Err:502 0.35% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 $ 11.60 $ 2,784.00 0.58% 6 Err:502 Err:502 Err:502 0.10% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

$ 57.46 $ 1,379.04 0.29% 2 Err:502 Err:502 Err:502 0.14% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

$ 75.32 $ 1,807.68 0.37% 2 Err:502 Err:502 Err:502 0.19% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

$ 86,079.63 71.10% 96 09/08/2014 Err:502 Err:502 17.81% Err:502

$ 1,506.55 $ 10,545.85 2.18% 15 09/08/2014 8/9/2014 8/23/2014 0.15% 0.00%

$ 38.09 $ 2,590.12 0.54% 24 Err:502 Err:502 Err:502 0.02% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

$ 54.00 $ 1,080.00 0.22% 5 Err:502 Err:502 Err:502 0.04% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

$ 11.71 $ 8,782.50 1.82% 24 Err:502 Err:502 Err:502 0.08% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

$ 11.27 $ 20,286.00 4.20% 24 Err:502 Err:502 Err:502 0.17% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

$ 40.32 $ 806.40 0.17% 24 Err:502 Err:502 Err:502 0.01% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

$ 3,504.04 $ 7,008.08 1.45% 1 Err:502 Err:502 Err:502 1.45% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

$ 6,370.73 $ 12,741.46 2.64% 1 Err:502 Err:502 Err:502 2.64% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

$ 4,501.50 $ 13,504.50 2.79% 1 Err:502 Err:502 Err:502 2.79% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

$ 8,734.72 $ 8,734.72 1.81% 5 Err:502 Err:502 Err:502 0.36% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 $ 44,758.00 71.10% 96 Err:502 Err:502 Err:502 9.26% Err:502

$ 44,758.00 $ 44,758.00 9.26% 45 Err:502 Err:502 Err:502 0.21% Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

1 2 3 4 5 6

PRECIO UNITARIO

FECHA INIPRJ

FECHA FINAL

Page 9: Rdo 10- Os 123895 - c&f - 07.08.2014 - Ducto de Transferencia Payamino - Gacela-est Coca

4-A

ug

5-A

ug

6-A

ug

7-A

ug

8-A

ug

9-A

ug

10-A

ug

11-A

ug

12-A

ug

13-A

ug

14-A

ug

15-A

ug

16-A

ug

17-A

ug

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

0.27% 0.27% 0.27% 0.27% 0.27%

0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05%0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05%

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

7 8 9 10 11 12 13 14 15 16 17 18 19 20

Page 10: Rdo 10- Os 123895 - c&f - 07.08.2014 - Ducto de Transferencia Payamino - Gacela-est Coca

18-A

ug

19-A

ug

20-A

ug

21-A

ug

22-A

ug

23-A

ug

24-A

ug

25-A

ug

26-A

ug

27-A

ug

28-A

ug

29-A

ug

30-A

ug

31-A

ug

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

0.15% 0.15% 0.15% 0.15% 0.15% 0.15%

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

21 22 23 24 25 26 27 28 29 30 31 32 33 34

Page 11: Rdo 10- Os 123895 - c&f - 07.08.2014 - Ducto de Transferencia Payamino - Gacela-est Coca

1-S

ep

2-S

ep

3-S

ep

4-S

ep

5-S

ep

6-S

ep

7-S

ep

8-S

ep

9-S

ep

10-S

ep

11-S

ep

12-S

ep

13-S

ep

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

0.71% 0.71%Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

0.37% 0.37% 0.37% 0.37%

4.52% 4.52% 4.52% 4.52%

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

1.13% 1.13% 1.13% 1.13%

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

35 36 37 38 39 40 41 42 43 44 45 46 47

Page 12: Rdo 10- Os 123895 - c&f - 07.08.2014 - Ducto de Transferencia Payamino - Gacela-est Coca

14-S

ep

15-S

ep

16-S

ep

17-S

ep

18-S

ep

19-S

ep

20-S

ep

21-S

ep

22-S

ep

23-S

ep

24-S

ep

25-S

ep

26-S

ep

27-S

ep

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

0.37%

4.52%

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

1.13%

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502 Err:502

48 49 50 51 52 53 54 55 56 57 58 59 60 61

Page 13: Rdo 10- Os 123895 - c&f - 07.08.2014 - Ducto de Transferencia Payamino - Gacela-est Coca

28-S

ep

29-S

ep

30-S

ep

Err:502 Err:502 Err:502

Err:502 Err:502 Err:502Err:502 Err:502 Err:502Err:502 Err:502 Err:502Err:502 Err:502 Err:502Err:502 Err:502 Err:502Err:502 Err:502 Err:502

Err:502 Err:502 Err:502Err:502 Err:502 Err:502Err:502 Err:502 Err:502

Err:502 Err:502 Err:502

Err:502 Err:502 Err:502

Err:502 Err:502 Err:502

Err:502 Err:502 Err:502

Err:502 Err:502 Err:502Err:502 Err:502 Err:502

Err:502 Err:502 Err:502

Err:502 Err:502 Err:502

Err:502 Err:502 Err:502

Err:502 Err:502 Err:502

Err:502 Err:502 Err:502

Err:502 Err:502 Err:502

Err:502 Err:502 Err:502

Err:502 Err:502 Err:502

Err:502 Err:502 Err:502

Err:502 Err:502 Err:502

Err:502 Err:502 Err:502

Err:502 Err:502 Err:502

Err:502 Err:502 Err:502

62 63 64

Page 14: Rdo 10- Os 123895 - c&f - 07.08.2014 - Ducto de Transferencia Payamino - Gacela-est Coca

Formato C

Reporte de horas hombre para Ordenes de Servicios

7/29/2014 hasta: #ADDIN?

Nombre de la Empresa Contratista: CYFOIL

Número de Orden de servicio: 123895

Número total de empleados en este período: #ADDIN?

Horas / Hombre trabajadas en este período: #ADDIN?

Glosario de términos

Número total de empleados

Horas/hombre trabajadas La fórmula utilizada es la siguiente:

Período

Nombre y firma Nombre y firmaPor la Contratista Por Petroamazonas EP

Período que se reporta (dd/mm/aa): desde:

Locación: CPF____ EPF____ B7_ X__ B18____ B21____ B31____ Quito ____ Otros ____

Número de empleados que trabajaron en las instalaciones de Petroamazonas EP durante el período que se reporta.

Número de horas hombre trabajadas por los empleados de su compañía en las instalaciones de Petroamazonas EP durante el período que se reporta.

Horas Hombre = No. Trabajadores * No. De horas trabajadas por día * No. De días trabajados durante el mes

Espacio de tiempo mensual en el cual se realizó el trabajo en las instalaciones de Petroamazonas EP.