HOJA DE METRADOS
PROYECTO: DEPARTAMENTO DE 5 PISOS
HOJA : ESTRUCTURAS PROPIETARIO : -
DEPARTAMENTO : JUNIN PROVINCIA : -
DISTRITO : HUANCAYO LUGAR : -
HECHO POR : [email protected] REVISADO : -
FECHA : ABRIL 2015
ITEM DENOMINACION UNIDAD VECES LARGO ANCHO ALTO PARCIAL
01.00 ESTRUCTURAS
01.01.00 OBRAS PRELIMINARES
01.01.01 TRAZO, NIVELES Y REPLANTEO m2
1.00 Area = 113.50 113.50
01.01.02 LIMPIEZA DEL TERRENO MANUAL m2
1.00 Area = 113.50 113.50
01.02.00 MOVIMIENTO DE TIERRAS
01.02.01 EXCAVACION DE ZANJA MANUAL m3
Z-1,2,4,6,7 6.00 2.00 1.80 2.10 45.36
Z-3 1.00 1.88 1.80 2.10 7.11
Z-5 1.00 1.90 1.80 2.10 7.18
CIMIENTOS
A-A 1.00 7.72 0.60 0.50 2.32
B-B 1.00 5.75 0.50 0.50 1.44
C-C 1.00 7.76 0.60 0.50 2.33
1-1 1.00 2.70 0.60 0.50 0.81
2-2 1.00 6.22 0.50 0.50 1.55
3-3 1.00 6.00 0.60 0.50 1.80
CISTERNA 1.00 Area = 3.80 3.15 11.97
01.02.02 NIVELACION INTERIOR APISONADO MANUAL m2
Z-1,2,4,6,7 6.00 2.00 1.80 21.60
Z-3 1.00 1.88 1.80 3.38
Z-5 1.00 1.90 1.80 3.42
CIMIENTOS
A-A 1.00 7.72 0.60 4.63
B-B 1.00 5.75 0.50 2.88
C-C 1.00 7.76 0.60 4.66
1-1 1.00 2.70 0.60 1.62
2-2 1.00 6.22 0.50 3.11
3-3 1.00 6.00 0.60 3.60
CISTERNA 1.00 Area = 3.80 3.15 11.97
01.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3
1.30 81.86 106.42
01.02.00 OBRAS DE CONCRETO SIMPLE
01.02.01 SOLADO EN ZAPATAS E=4" m2
Z-1,2,4,6,7 6.00 2.00 1.80 21.60
Z-3 1.00 1.88 1.80 3.38
Z-5 1.00 1.90 1.80 3.42
CISTERNA 1.00 Area = 3.80 3.80
01.02.02 CONCRETO CICLOPEO 1:10 CON 30% PG m3
A-A 1.00 7.72 0.35 0.50 1.35
B-B 1.00 5.75 0.25 0.50 0.72
C-C 1.00 7.76 0.35 0.50 1.36
1-1 1.00 2.70 0.35 0.50 0.47
2-2 1.00 6.22 0.25 0.50 0.78
3-3 1.00 6.00 0.35 0.50 1.05
01.02.03 ENCOFRADO Y DESENCOFRADO EN CIMIENTOS m2
A-A 2.00 7.72 0.50 7.72
B-B 2.00 5.75 0.50 5.75
C-C 2.00 7.76 0.50 7.76
1-1 2.00 2.70 0.50 2.70
2-2 2.00 6.22 0.50 6.22
3-3 2.00 6.00 0.50 6.00
01.02.05 CONCRETO EN FALSO PISO 1:8 E=4" m2
SOTANO 1.00 Area = 102.94 102.94
01.03.00 OBRAS DE CONCRETO ARMADO
01.03.01 CONCRETO PARA ZAPATAS F'C=175 KG/CM2 m3
Z-1,2,4,6,7 6.00 2.00 1.80 1.50 32.40
Z-3 1.00 1.88 1.80 1.50 5.08
Z-5 1.00 1.90 1.80 1.50 5.13
01.03.02 ACERO F'Y=4200 KG/CM2 GRADO 60 EN ZAPATAS kg
Z-1,2,4,6,7 72.00 1.90 Peso = 0.99 135.43
78.00 1.70 Peso = 0.99 131.27
Z-3 12.00 1.78 Peso = 0.99 21.15
13.00 1.70 Peso = 0.99 21.88
Z-5 12.00 1.80 Peso = 0.99 21.38
13.00 1.70 Peso = 0.99 21.88
01.03.03 CONCRETO PARA COLUMNAS F'C=210 KG/CM2 m3
C-1 2.00 0.60 0.25 15.45 4.64
C-2 3.00 0.60 0.25 15.45 6.95
C-3 1.00 0.60 0.25 15.45 2.32
C-4 1.00 0.59 0.25 15.45 2.28
C-5 1.00 0.59 0.25 15.45 2.26
01.03.04 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2
C-1 2.00 1.70 15.45 52.53
C-2 3.00 1.70 15.45 78.80
C-3 1.00 1.70 15.45 26.27
C-4 1.00 1.68 15.45 25.96
C-5 1.00 1.67 15.45 25.80
01.03.05 ACERO F'Y=4200 KG/CM2 GRADO 60 EN COLUMNAS kg
C-1 16.00 16.81 Peso = 1.55 416.89
4.00 16.81 Peso = 0.99 66.57
C-2 24.00 16.81 Peso = 1.55 625.33
6.00 16.81 Peso = 0.99 99.85
C-3 8.00 16.81 Peso = 1.55 208.44
C-4 8.00 16.81 Peso = 1.55 208.44
2.00 16.81 Peso = 0.99 33.28
C-5 8.00 16.81 Peso = 1.55 208.44
2.00 16.81 Peso = 0.99 33.28
ESTRIBOS
C-1 230.00 1.50 Peso = 0.56 193.20
C-2 345.00 1.50 Peso = 0.56 289.80
C-3 115.00 1.50 Peso = 0.56 96.60
C-4 115.00 1.48 Peso = 0.56 95.31
C-5 115.00 1.47 Peso = 0.56 94.67
HOJA DE METRADOS
TOTAL
113.50
113.50
81.86
60.87
106.42
32.20
5.73
36.15
102.94
42.61
352.99
18.44
209.35
2,670.12