Date 19 Agosto 2014 Page 1
Ver. Last Update
Instalación de Aires Acondicionados de 30TR en Data Center
DATA CENTER SAN BORJA
Jorge Valladares
Designed byJosé RiveraReviewed by
O&M
Rodolfo VilchezApproved byManager/VP
Confidential
P e r u E n g i n e e r i n g
Method of Procedure (MOP)
Date 19 Agosto 2014 Page 2
Ver. Last Update
General InformationProposed Date:
Proposed Time:
[20/08/2014 , 24/08/2014]
[Peru GMT-5 (00:00 hrs ~ 05:00 hrs)]
Activity Description: Instalación de equipos de AA de 30TR en Sala Técnica Nextel Circunvalación
Activity Purpose: Cooling the air in order to avoid the raise of temperature in the Data Center
Network Type 2G 3G LTE WiMax Other
Network Domains Involved:
RAN (Radio Access Network) Transport/Transmission PS Core
CS Core DATACOM ISP VAS X Sites Other:______________
Involved NEs: Equipment MSO 2
Involved Services: 2G, 3G
Involved Markets and Providers:
Nextel NOC Monitoring
Sites & TX Voice Dispatch / ISP / HPPTT / CWAN
VAS Datacomm
RPN (Risk Priority Number)
Location for execution:
Distrito de San Borja, Provincia Lima, Departamento de Lima
Bridge (if needed):
Facilities:
Onsite Support Required: Yes No: Places (if yes): [ ]
Remote Support Required: Yes: No:
Partners Support Required: Yes: No: Contact Info: [O&M MSO’s]
Network Impact: Yes: No:
Impact Duration:
Confidential
P e r u E n g i n e e r i n g
Method of Procedure (MOP)
Date 19 Agosto 2014 Page 3
Ver. Last Update
Notification to OSIPTEL:
Yes: No: Date: dd/mmm/yyyy]
Notification to Providers:
Yes: No: Date: dd/mmm/yyyy]
Impacted NEs:
Impacted Services:
Impacted Markets and Providers:
Ticket or Case reference (if any):
Comments and remarks:
Los trabajos se realizan por etapas. Se toman todas las medidas de Seguridad.
MOP Scope and Detailed Description
Pre-conditions in the Network
General Expected Results
Pre – Works
Attach test matrix and necessary checklist:1. [Item1]2. [Item2]
MOP Activities
Attach Hour by Hour Activity:
Confidential
P e r u E n g i n e e r i n g
Method of Procedure (MOP)
Date 19 Agosto 2014 Page 4
Ver. Last Update
Description
Step Description Date Owner
Reference Start Time
Reference End Time
1 Instalación de soportería metálica y presentación de tuberías de Cu 20/08/14 00:00 06:00
2 Soldadura de tuberías de Cu en Sala técnica 21/08/14 00:00 06:00
3 Soldadura de tuberías de Cu en sala de rectificadores 22/08/14 00:00 06:00
4 Instalación de mangas armaflex 23/08/14 00:00 06:00
8 Instalación de mangas armaflex 24/08/14 00:00 06:00
Command Configuration
Attach the scripts and commands sequence:
1. [Item1]2. [Item2]
Validation Attach test matrix and necessary validations:
1. [Item1]2. [Item2]
Go / No Go Criteria
Attach the GO / NO GO Criteria and escalation levels:
1. [Item1]2. [Item2]
Confidential
P e r u E n g i n e e r i n g
Method of Procedure (MOP)
Date 19 Agosto 2014 Page 5
Ver. Last Update
Roll Back Procedure
Attach the scripts and commands sequence:
1. [Item1]2. [Item2]
Roles & Responsibilities
The roles and responsibilities should be detailed below and some additional information can be gathered including providers:
Contact name Contact Number / UFMI
Area / Responsability E-mail
Jorge Valladares 971417601 O&M SITIOS Y ACCESOS DE RED [email protected]
Roberto Chavez *347615 PMI Emerson [email protected] Huamán 989134153 CPEA Conditioning [email protected]
Additional Information:
Se debe proporcionar energía comercial para funcionamiento de equipos y herramientas en Data Center.
Confidential
P e r u E n g i n e e r i n g
Method of Procedure (MOP)