Transcript
Page 1: Instalacion Aires Acondicionados Circunvalacion

Date 19 Agosto 2014 Page 1

Ver. Last Update

Instalación de Aires Acondicionados de 30TR en Data Center

DATA CENTER SAN BORJA

Jorge Valladares

Designed byJosé RiveraReviewed by

O&M

Rodolfo VilchezApproved byManager/VP

Confidential

P e r u E n g i n e e r i n g

Method of Procedure (MOP)

Page 2: Instalacion Aires Acondicionados Circunvalacion

Date 19 Agosto 2014 Page 2

Ver. Last Update

General InformationProposed Date:

Proposed Time:

[20/08/2014 , 24/08/2014]

[Peru GMT-5 (00:00 hrs ~ 05:00 hrs)]

Activity Description: Instalación de equipos de AA de 30TR en Sala Técnica Nextel Circunvalación

Activity Purpose: Cooling the air in order to avoid the raise of temperature in the Data Center

Network Type 2G 3G LTE WiMax Other

Network Domains Involved:

RAN (Radio Access Network) Transport/Transmission PS Core

CS Core DATACOM ISP VAS X Sites Other:______________

Involved NEs: Equipment MSO 2

Involved Services: 2G, 3G

Involved Markets and Providers:

Nextel NOC Monitoring

Sites & TX Voice Dispatch / ISP / HPPTT / CWAN

VAS Datacomm

RPN (Risk Priority Number)

Location for execution:

Distrito de San Borja, Provincia Lima, Departamento de Lima

Bridge (if needed):

Facilities:

Onsite Support Required: Yes No: Places (if yes): [ ]

Remote Support Required: Yes: No:

Partners Support Required: Yes: No: Contact Info: [O&M MSO’s]

Network Impact: Yes: No:

Impact Duration:

Confidential

P e r u E n g i n e e r i n g

Method of Procedure (MOP)

Page 3: Instalacion Aires Acondicionados Circunvalacion

Date 19 Agosto 2014 Page 3

Ver. Last Update

Notification to OSIPTEL:

Yes: No: Date: dd/mmm/yyyy]

Notification to Providers:

Yes: No: Date: dd/mmm/yyyy]

Impacted NEs:

Impacted Services:

Impacted Markets and Providers:

Ticket or Case reference (if any):

Comments and remarks:

Los trabajos se realizan por etapas. Se toman todas las medidas de Seguridad.

MOP Scope and Detailed Description

Pre-conditions in the Network

General Expected Results

Pre – Works

Attach test matrix and necessary checklist:1. [Item1]2. [Item2]

MOP Activities

Attach Hour by Hour Activity:

Confidential

P e r u E n g i n e e r i n g

Method of Procedure (MOP)

Page 4: Instalacion Aires Acondicionados Circunvalacion

Date 19 Agosto 2014 Page 4

Ver. Last Update

Description

Step Description Date Owner

Reference Start Time

Reference End Time

1 Instalación de soportería metálica y presentación de tuberías de Cu 20/08/14   00:00 06:00

2 Soldadura de tuberías de Cu en Sala técnica 21/08/14   00:00 06:00

3 Soldadura de tuberías de Cu en sala de rectificadores 22/08/14   00:00 06:00

4 Instalación de mangas armaflex 23/08/14   00:00 06:00

8 Instalación de mangas armaflex 24/08/14   00:00 06:00

Command Configuration

Attach the scripts and commands sequence:

1. [Item1]2. [Item2]

Validation Attach test matrix and necessary validations:

1. [Item1]2. [Item2]

Go / No Go Criteria

Attach the GO / NO GO Criteria and escalation levels:

1. [Item1]2. [Item2]

Confidential

P e r u E n g i n e e r i n g

Method of Procedure (MOP)

Page 5: Instalacion Aires Acondicionados Circunvalacion

Date 19 Agosto 2014 Page 5

Ver. Last Update

Roll Back Procedure

Attach the scripts and commands sequence:

1. [Item1]2. [Item2]

Roles & Responsibilities

The roles and responsibilities should be detailed below and some additional information can be gathered including providers:

Contact name Contact Number / UFMI

Area / Responsability E-mail

Jorge Valladares 971417601 O&M SITIOS Y ACCESOS DE RED [email protected]

Roberto Chavez *347615 PMI Emerson [email protected] Huamán 989134153 CPEA Conditioning [email protected]

Additional Information:

Se debe proporcionar energía comercial para funcionamiento de equipos y herramientas en Data Center.

Confidential

P e r u E n g i n e e r i n g

Method of Procedure (MOP)