  • Interbank-El EjercitoHVAC Load Analysis

    for

    BANCO INTERBANK

    Prepared By:

    lunes, 15 de julio de 2013

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 2

    Project Information

    Project Title: Interbank-El EjercitoDesigned By: Ing.victor Mori Marin CIP.9099Date: sbado, 29 de junio de 2013Comment:

    Client Name: BANCO INTERBANK Company Name:Address: Representative:City: Address:Phone: City:Fax: Phone:Comment: Fax:

    Comment:

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 3

    General Project Data Input

    General Project InformationProject file name: CALCULOS DE CARGAS TERMICAS-INTERBANK EL

    EJERCITO.CH8Project title: Interbank-El EjercitoDesigned by: Ing.victor Mori Marin CIP.9099Project date: sbado, 29 de junio de 2013Weather reference city: LIMA, PERUClient name: BANCO INTERBANK

    Barometric pressure: 29.876 in.Hg.Altitude: 42 feetLatitude: -12 DegreesMean daily temperature range: 11.5 DegreesStarting & ending time for HVAC load calculations: 1am - 12amNumber of unique rooms in this project: 7

    Building Default ValuesCalculations performed: Cooling loads onlyLighting requirements: 1.70 Watts per square footEquipment requirements: 1.00 Watts per square footPeople sensible load multiplier: 250 Btuh per personPeople latent load multiplier: 200 Btuh per personRoom sensible safety factor: 10 %Room latent safety factor: 10 %Room heating safety factor: 10 %People diversity factor: 100 %Lighting profile number: 0Equipment profile number: 0People profile number: 0Building default ceiling height: 19.60 feetBuilding default wall height: 19.60 feet

    Internal Operating Load Profiles (C = 100)hr hr hr hr hr hr hr hr hr hr hr hr hr hr hr hr hr hr hr hr hr hr hr hr1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    1 C C C C C C C C C C C C C C C C C C C C C C C C2 C C C C C C C C C C C C C C C C C C C C C C C C3 C C C C C C C C C C C C C C C C C C C C C C C C4 C C C C C C C C C C C C C C C C C C C C C C C C5 C C C C C C C C C C C C C C C C C C C C C C C C6 C C C C C C C C C C C C C C C C C C C C C C C C7 C C C C C C C C C C C C C C C C C C C C C C C C8 C C C C C C C C C C C C C C C C C C C C C C C C9 C C C C C C C C C C C C C C C C C C C C C C C C

    10 C C C C C C C C C C C C C C C C C C C C C C C C

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 4

    General Project Data Input (cont'd)

    Building-Level Design Conditions

    DesignMonth

    OutdoorDry Bulb

    OutdoorWet Bulb

    IndoorRel.Hum

    IndoorDry Bulb

    GrainsDiff

    In/OutdoorCorrection

    February 88 74 55% 72 40.02 3Winter 58 75

    Master RoofsRoofNo.

    ASHRAERoof#

    RoofU-Fac

    DarkColor

    Susp.Ceil

    1 8 0.126 Yes No

    Master WallsWallNo.

    ASHRAEGroup

    WallU-Fac

    WallColor

    1 D 0.415 D

    Master PartitionsPartitionNo.

    PartitionU-Factor

    CoolT-D

    HeatT-D

    1 0.415 9 92 0.810 9 9

    Master GlassGlassNo.

    SummerU-Factor

    WinterU-Factor

    GlassShd.Coef.

    InteriorShading

    InteriorShd.Coef

    1 0.810 0.830 0.880 4 0.640

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 5

    Air Handler Input

    Air Handler Number 1 Input Data

    Name: Ue-01Terminal type: Constant VolumeMethod for CV Sum of PeaksSupply fan type: Draw-thru fanCalculations performed: Cooling loads onlyExcess supply air: ReserveOccurrences: 1People profile number: 0Lighting profile number: 0Equipment profile number: 0Exhaust may not exceed supply air: NoLeaving heating coil temp (deg.F): 90.0Leaving cooling coil temp (deg.F): 55.0Cooling coil CFM 0Misc. Btuh gain - supply side: 0Misc. Btuh gain - return side: 0Combined fan & motor efficiency: 0Static pressure across fan (in.wg.): 0.00Summer supply duct temp rise (deg.F): 0.000Summer return duct temp rise (deg.F): 0.000Winter supply duct temp drop (deg.F): 0.000Winter return duct temp drop (deg.F): 0.000Chilled water temp difference (deg.F): 10.000Hot water temp difference (deg.F): 20.000Cooling ventilation: 10 CFM/PrCooling infiltration: 0 AC/HrHeating ventilation: 0 CFM/PrHeating infiltration: 0 AC/HrPretreated outside air: nonePretreated air Summer DB (deg.F): 0Pretreated air Summer WB (deg.F): 0Pretreated air Winter DB (deg.F): 0

    DesignMonth

    OutdoorDry Bulb

    OutdoorWet Bulb

    IndoorRel.Hum

    IndoorDry Bulb

    GrainsDiff

    In/OutdoorCorrection

    February 88 74 55% 72 40.02 3Winter 58 75

    Air Handler Number 2 Input Data

    Name: Ue-02Terminal type: Constant VolumeMethod for CV Sum of PeaksSupply fan type: Draw-thru fanCalculations performed: Cooling loads onlyExcess supply air: ReserveOccurrences: 1People profile number: 0Lighting profile number: 0Equipment profile number: 0Exhaust may not exceed supply air: NoLeaving heating coil temp (deg.F): 90.0Leaving cooling coil temp (deg.F): 55.0Cooling coil CFM 0Misc. Btuh gain - supply side: 0Misc. Btuh gain - return side: 0Combined fan & motor efficiency: 0Static pressure across fan (in.wg.): 0.00Summer supply duct temp rise (deg.F): 0.000Summer return duct temp rise (deg.F): 0.000Winter supply duct temp drop (deg.F): 0.000

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 6

    Air Handler Input (cont'd)

    Air Handler Number 2 Input DataWinter return duct temp drop (deg.F): 0.000Chilled water temp difference (deg.F): 10.000Hot water temp difference (deg.F): 20.000Cooling ventilation: 10 CFM/PrCooling infiltration: 0 AC/HrHeating ventilation: 0 CFM/PrHeating infiltration: 0 AC/HrPretreated outside air: nonePretreated air Summer DB (deg.F): 0Pretreated air Summer WB (deg.F): 0Pretreated air Winter DB (deg.F): 0

    DesignMonth

    OutdoorDry Bulb

    OutdoorWet Bulb

    IndoorRel.Hum

    IndoorDry Bulb

    GrainsDiff

    In/OutdoorCorrection

    February 88 74 55% 72 40.02 3Winter 58 75

    Air Handler Number 3 Input Data

    Name: Fc-01Terminal type: Constant VolumeMethod for CV Sum of PeaksSupply fan type: Draw-thru fanCalculations performed: Cooling loads onlyExcess supply air: ReserveOccurrences: 1People profile number: 0Lighting profile number: 0Equipment profile number: 0Exhaust may not exceed supply air: NoLeaving heating coil temp (deg.F): 90.0Leaving cooling coil temp (deg.F): 55.0Cooling coil CFM 0Misc. Btuh gain - supply side: 0Misc. Btuh gain - return side: 0Combined fan & motor efficiency: 0Static pressure across fan (in.wg.): 0.00Summer supply duct temp rise (deg.F): 0.000Summer return duct temp rise (deg.F): 0.000Winter supply duct temp drop (deg.F): 0.000Winter return duct temp drop (deg.F): 0.000Chilled water temp difference (deg.F): 10.000Hot water temp difference (deg.F): 20.000Cooling ventilation: 15 CFM/PrCooling infiltration: 0 AC/HrHeating ventilation: 0 CFM/PrHeating infiltration: 0 AC/HrPretreated outside air: nonePretreated air Summer DB (deg.F): 0Pretreated air Summer WB (deg.F): 0Pretreated air Winter DB (deg.F): 0

    DesignMonth

    OutdoorDry Bulb

    OutdoorWet Bulb

    IndoorRel.Hum

    IndoorDry Bulb

    GrainsDiff

    In/OutdoorCorrection

    February 88 74 55% 72 40.02 3Winter 58 75

    Air Handler Number 4 Input Data

    Name: Fc-02

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 7

    Air Handler Input (cont'd)

    Air Handler Number 4 Input DataTerminal type: Constant VolumeMethod for CV Sum of PeaksSupply fan type: Draw-thru fanCalculations performed: Cooling loads onlyExcess supply air: ReserveOccurrences: 1People profile number: 0Lighting profile number: 0Equipment profile number: 0Exhaust may not exceed supply air: NoLeaving heating coil temp (deg.F): 90.0Leaving cooling coil temp (deg.F): 55.0Cooling coil CFM 0Misc. Btuh gain - supply side: 0Misc. Btuh gain - return side: 0Combined fan & motor efficiency: 0Static pressure across fan (in.wg.): 0.00Summer supply duct temp rise (deg.F): 0.000Summer return duct temp rise (deg.F): 0.000Winter supply duct temp drop (deg.F): 0.000Winter return duct temp drop (deg.F): 0.000Chilled water temp difference (deg.F): 10.000Hot water temp difference (deg.F): 20.000Cooling ventilation: 10 CFM/PrCooling infiltration: 0 AC/HrHeating ventilation: 0 CFM/PrHeating infiltration: 0 AC/HrPretreated outside air: nonePretreated air Summer DB (deg.F): 0Pretreated air Summer WB (deg.F): 0Pretreated air Winter DB (deg.F): 0

    DesignMonth

    OutdoorDry Bulb

    OutdoorWet Bulb

    IndoorRel.Hum

    IndoorDry Bulb

    GrainsDiff

    In/OutdoorCorrection

    February 88 74 55% 72 40.02 3Winter 58 75

    Air Handler Number 5 Input Data

    Name: Ue-05Terminal type: Constant VolumeMethod for CV Sum of PeaksSupply fan type: Draw-thru fanCalculations performed: Cooling loads onlyExcess supply air: ReserveOccurrences: 1People profile number: 0Lighting profile number: 0Equipment profile number: 0Exhaust may not exceed supply air: NoLeaving heating coil temp (deg.F): 90.0Leaving cooling coil temp (deg.F): 55.0Cooling coil CFM 0Misc. Btuh gain - supply side: 0Misc. Btuh gain - return side: 0Combined fan & motor efficiency: 0Static pressure across fan (in.wg.): 0.00Summer supply duct temp rise (deg.F): 0.000Summer return duct temp rise (deg.F): 0.000Winter supply duct temp drop (deg.F): 0.000Winter return duct temp drop (deg.F): 0.000

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 8

    Air Handler Input (cont'd)

    Air Handler Number 5 Input DataChilled water temp difference (deg.F): 10.000Hot water temp difference (deg.F): 20.000Cooling ventilation: 10 CFM/PrCooling infiltration: 0 AC/HrHeating ventilation: 0 CFM/PrHeating infiltration: 0 AC/HrPretreated outside air: nonePretreated air Summer DB (deg.F): 0Pretreated air Summer WB (deg.F): 0Pretreated air Winter DB (deg.F): 0

    DesignMonth

    OutdoorDry Bulb

    OutdoorWet Bulb

    IndoorRel.Hum

    IndoorDry Bulb

    GrainsDiff

    In/OutdoorCorrection

    February 88 74 55% 72 40.02 3Winter 58 75

    Air Handler Number 6 Input Data

    Name: Ue-03Terminal type: Constant VolumeMethod for CV Sum of PeaksSupply fan type: Draw-thru fanCalculations performed: Cooling loads onlyExcess supply air: ReserveOccurrences: 1People profile number: 0Lighting profile number: 0Equipment profile number: 0Exhaust may not exceed supply air: NoLeaving heating coil temp (deg.F): 90.0Leaving cooling coil temp (deg.F): 55.0Cooling coil CFM 0Misc. Btuh gain - supply side: 0Misc. Btuh gain - return side: 0Combined fan & motor efficiency: 0Static pressure across fan (in.wg.): 0.00Summer supply duct temp rise (deg.F): 0.000Summer return duct temp rise (deg.F): 0.000Winter supply duct temp drop (deg.F): 0.000Winter return duct temp drop (deg.F): 0.000Chilled water temp difference (deg.F): 10.000Hot water temp difference (deg.F): 20.000Cooling ventilation: 10 CFM/PrCooling infiltration: 0 AC/HrHeating ventilation: 0 CFM/PrHeating infiltration: 0 AC/HrPretreated outside air: nonePretreated air Summer DB (deg.F): 0Pretreated air Summer WB (deg.F): 0Pretreated air Winter DB (deg.F): 0

    DesignMonth

    OutdoorDry Bulb

    OutdoorWet Bulb

    IndoorRel.Hum

    IndoorDry Bulb

    GrainsDiff

    In/OutdoorCorrection

    February 88 74 55% 72 40.02 3Winter 58 75

    Air Handler Number 7 Input Data

    Name: Ue-04Terminal type: Constant Volume

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 9

    Air Handler Input (cont'd)

    Air Handler Number 7 Input DataMethod for CV Sum of PeaksSupply fan type: Draw-thru fanCalculations performed: Cooling loads onlyExcess supply air: ReserveOccurrences: 1People profile number: 0Lighting profile number: 0Equipment profile number: 0Exhaust may not exceed supply air: NoLeaving heating coil temp (deg.F): 90.0Leaving cooling coil temp (deg.F): 55.0Cooling coil CFM 0Misc. Btuh gain - supply side: 0Misc. Btuh gain - return side: 0Combined fan & motor efficiency: 0Static pressure across fan (in.wg.): 0.00Summer supply duct temp rise (deg.F): 0.000Summer return duct temp rise (deg.F): 0.000Winter supply duct temp drop (deg.F): 0.000Winter return duct temp drop (deg.F): 0.000Chilled water temp difference (deg.F): 10.000Hot water temp difference (deg.F): 20.000Cooling ventilation: 10 CFM/PrCooling infiltration: 0 AC/HrHeating ventilation: 0 CFM/PrHeating infiltration: 0 AC/HrPretreated outside air: nonePretreated air Summer DB (deg.F): 0Pretreated air Summer WB (deg.F): 0Pretreated air Winter DB (deg.F): 0

    DesignMonth

    OutdoorDry Bulb

    OutdoorWet Bulb

    IndoorRel.Hum

    IndoorDry Bulb

    GrainsDiff

    In/OutdoorCorrection

    February 88 74 50% 68 53.50 7Winter 58 75

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 10

    Room Input

    Room 1: Plataforma 1-2 (126 sq.ft) (Zone 0)

    Air Handler number: 1 Room occurrences: 1Room length: (feet) 14.00 Room width (feet): 9.00Lighting Watts: 214 Equipment Watts: 96Number of people in room: 6 People profile number: 0Lighting profile number: 0 Equipment profile number: 0Ceiling height (feet): 8.00 Heating safety factor (%): 10Sensible safety factor (%): 10 Latent safety factor (%): 10Sensible heat per person (Btuh): 250 Latent heat per person (Btuh): 200Cooling ventilation method: CFM/Pr Cooling ventilation value: 10.000Cooling infiltration method: AC/Hr Cooling infiltration value: 0.000Heating ventilation method: CFM/Pr Heating ventilation value: 0.000Heating infiltration method: AC/Hr Heating infiltration value: 0.000Winter exhaust air CFM: 0 Summer exhaust air CFM: 0Minimum supply CFM: 0 Latent Btuh equipment load: 0Ceil. exposed to plenum (sq.ft): 126 Exposed floor slab perimeter (ft): 0Cooling loads only are calculated for this room.

    Roof Type ASHRAE# U-Factor Dark Length Width Area Susp.Ceil

    1 1 8 0.126 Yes 14.00 9.00 126.0 No

    Part Type U-Factor Cool TD Heat TD Height Width Area

    2 1 0.415 9.000 9.000 8.00 14.00 112.04 1 0.415 9.000 9.000 8.00 9.00 72.0

    Wall Type ASHRAE# U-Factor Color Height Width Area Direction

    1 1 D 0.415 D 8.00 14.00 112.0 W3 1 D 0.415 D 8.00 9.00 72.0 N

    Glass Type S.U-F. Shd C. Height Width Occur. Area Shade Tilt Ref

    1 1 0.810 0.880 8.00 14.00 1 112.0 0 90 1

    Room 2: Gerente De Tienda (63 sq.ft) (Zone 0)

    Air Handler number: 2 Room occurrences: 1Room length: (feet) 7.00 Room width (feet): 9.00Lighting Watts: 107 Equipment Watts: 63Number of people in room: 3 People profile number: 0Lighting profile number: 0 Equipment profile number: 0Ceiling height (feet): 8.00 Heating safety factor (%): 10Sensible safety factor (%): 10 Latent safety factor (%): 10Sensible heat per person (Btuh): 250 Latent heat per person (Btuh): 200Cooling ventilation method: CFM/Pr Cooling ventilation value: 10.000Cooling infiltration method: AC/Hr Cooling infiltration value: 0.000Heating ventilation method: CFM/Pr Heating ventilation value: 0.000Heating infiltration method: AC/Hr Heating infiltration value: 0.000Winter exhaust air CFM: 0 Summer exhaust air CFM: 0Minimum supply CFM: 0 Latent Btuh equipment load: 0Ceil. exposed to plenum (sq.ft): 63 Exposed floor slab perimeter (ft): 0Cooling loads only are calculated for this room.

    Roof Type ASHRAE# U-Factor Dark Length Width Area Susp.Ceil

    1 1 8 0.126 Yes 7.00 9.00 63.0 No

    Part Type U-Factor Cool TD Heat TD Height Width Area

    2 1 0.415 9.000 9.000 8.00 7.00 56.03 1 0.415 9.000 9.000 8.00 9.00 72.04 1 0.415 9.000 9.000 8.00 9.00 72.0

    Wall Type ASHRAE# U-Factor Color Height Width Area Direction

    1 1 D 0.415 D 8.00 7.00 56.0 W

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 11

    Room Input (cont'd)

    Room 2: Gerente De Tienda (63 sq.ft) (Zone 0)

    Glass Type S.U-F. Shd C. Height Width Occur. Area Shade Tilt Ref

    1 1 0.810 0.880 8.00 7.00 1 56.0 0 90 1

    Room 3: Gerente Asist.-Embosadora (100 sq.ft) (Zone 0)

    Air Handler number: 3 Room occurrences: 1Room length: (feet) 10.00 Room width (feet): 10.00Lighting Watts: 170 Equipment Watts: 600Number of people in room: 4 People profile number: 0Lighting profile number: 0 Equipment profile number: 0Ceiling height (feet): 8.00 Heating safety factor (%): 10Sensible safety factor (%): 10 Latent safety factor (%): 10Sensible heat per person (Btuh): 250 Latent heat per person (Btuh): 200Cooling ventilation method: CFM/Pr Cooling ventilation value: 15.000Cooling infiltration method: AC/Hr Cooling infiltration value: 0.000Heating ventilation method: CFM/Pr Heating ventilation value: 0.000Heating infiltration method: AC/Hr Heating infiltration value: 0.000Winter exhaust air CFM: 0 Summer exhaust air CFM: 0Minimum supply CFM: 0 Latent Btuh equipment load: 0Ceil. exposed to plenum (sq.ft): 100 Exposed floor slab perimeter (ft): 0Cooling loads only are calculated for this room.

    Roof Type ASHRAE# U-Factor Dark Length Width Area Susp.Ceil

    1 1 8 0.126 Yes 10.00 10.00 100.0 No

    Part Type U-Factor Cool TD Heat TD Height Width Area

    2 1 0.415 9.000 9.000 8.00 10.00 80.04 1 0.415 9.000 9.000 8.00 10.00 80.0

    Wall Type ASHRAE# U-Factor Color Height Width Area Direction

    1 1 D 0.415 D 8.00 10.00 80.0 W3 1 D 0.415 D 8.00 10.00 80.0 N

    Room 4: Counter (139 sq.ft) (Zone 0)

    Air Handler number: 4 Room occurrences: 1Room length: (feet) 139.00 Room width (feet): 1.00Lighting Watts: 236 Equipment Watts: 192Number of people in room: 7 People profile number: 0Lighting profile number: 0 Equipment profile number: 0Ceiling height (feet): 8.00 Heating safety factor (%): 10Sensible safety factor (%): 10 Latent safety factor (%): 10Sensible heat per person (Btuh): 250 Latent heat per person (Btuh): 200Cooling ventilation method: CFM/Pr Cooling ventilation value: 10.000Cooling infiltration method: AC/Hr Cooling infiltration value: 0.000Heating ventilation method: CFM/Pr Heating ventilation value: 0.000Heating infiltration method: AC/Hr Heating infiltration value: 0.000Winter exhaust air CFM: 0 Summer exhaust air CFM: 0Minimum supply CFM: 0 Latent Btuh equipment load: 0Ceil. exposed to plenum (sq.ft): 139 Exposed floor slab perimeter (ft): 0Cooling loads only are calculated for this room.

    Roof Type ASHRAE# U-Factor Dark Length Width Area Susp.Ceil

    1 1 8 0.126 Yes 139.00 1.00 139.0 No

    Part Type U-Factor Cool TD Heat TD Height Width Area

    1 1 0.415 9.000 9.000 8.00 28.00 224.03 1 0.415 9.000 9.000 8.00 26.00 208.0

    Wall Type ASHRAE# U-Factor Color Height Width Area Direction

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 12

    Room Input (cont'd)

    Room 4: Counter (139 sq.ft) (Zone 0)

    2 1 D 0.415 D 8.00 5.00 40.0 N

    Room 5: Area Comun (388 sq.ft) (Zone 0)

    Air Handler number: 5 Room occurrences: 1Room length: (feet) 388.00 Room width (feet): 1.00Lighting Watts: 660 Equipment Watts: 388Number of people in room: 20 People profile number: 0Lighting profile number: 0 Equipment profile number: 0Ceiling height (feet): 19.60 Heating safety factor (%): 10Sensible safety factor (%): 10 Latent safety factor (%): 10Sensible heat per person (Btuh): 250 Latent heat per person (Btuh): 200Cooling ventilation method: CFM/Pr Cooling ventilation value: 10.000Cooling infiltration method: AC/Hr Cooling infiltration value: 0.000Heating ventilation method: CFM/Pr Heating ventilation value: 0.000Heating infiltration method: AC/Hr Heating infiltration value: 0.000Winter exhaust air CFM: 0 Summer exhaust air CFM: 0Minimum supply CFM: 0 Latent Btuh equipment load: 0Ceil. exposed to plenum (sq.ft): 388 Exposed floor slab perimeter (ft): 0Cooling loads only are calculated for this room.

    Roof Type ASHRAE# U-Factor Dark Length Width Area Susp.Ceil

    1 1 8 0.126 Yes 388.00 1.00 388.0 No

    Part Type U-Factor Cool TD Heat TD Height Width Area

    1 1 0.415 9.000 9.000 19.60 52.00 1,019.22 2 0.81 9.000 9.000 19.60 16.00 313.6

    Wall Type ASHRAE# U-Factor Color Height Width Area Direction

    3 1 D 0.415 D 19.60 16.00 313.6 S

    Glass Type S.U-F. Shd C. Height Width Occur. Area Shade Tilt Ref

    1 1 0.810 0.880 9.00 16.00 1 144.0 0 90 3

    Room 6: Banca Electronica (118 sq.ft) (Zone 0)

    Air Handler number: 6 Room occurrences: 1Room length: (feet) 118.00 Room width (feet): 1.00Lighting Watts: 201 Equipment Watts: 2,500Number of people in room: 10 People profile number: 0Lighting profile number: 0 Equipment profile number: 0Ceiling height (feet): 9.00 Heating safety factor (%): 10Sensible safety factor (%): 10 Latent safety factor (%): 10Sensible heat per person (Btuh): 250 Latent heat per person (Btuh): 200Cooling ventilation method: CFM/Pr Cooling ventilation value: 10.000Cooling infiltration method: AC/Hr Cooling infiltration value: 0.000Heating ventilation method: CFM/Pr Heating ventilation value: 0.000Heating infiltration method: AC/Hr Heating infiltration value: 0.000Winter exhaust air CFM: 0 Summer exhaust air CFM: 0Minimum supply CFM: 0 Latent Btuh equipment load: 0Ceil. exposed to plenum (sq.ft): 118 Exposed floor slab perimeter (ft): 0Cooling loads only are calculated for this room.

    Roof Type ASHRAE# U-Factor Dark Length Width Area Susp.Ceil

    1 1 8 0.126 Yes 118.00 1.00 118.0 No

    Part Type U-Factor Cool TD Heat TD Height Width Area

    1 1 0.415 9.000 9.000 9.00 22.00 198.0

    Wall Type ASHRAE# U-Factor Color Height Width Area Direction

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 13

    Room Input (cont'd)

    Room 6: Banca Electronica (118 sq.ft) (Zone 0)2 1 D 0.415 D 9.00 12.50 112.5 E3 1 D 0.415 D 9.00 14.00 126.0 S

    Glass Type S.U-F. Shd C. Height Width Occur. Area Shade Tilt Ref

    1 1 0.810 0.880 9.00 14.00 1 126.0 0 90 3

    Room 7: Rack (46 sq.ft) (Zone 0)

    Air Handler number: 7 Room occurrences: 1Room length: (feet) 46.00 Room width (feet): 1.00Lighting Watts: 78 Equipment Watts: 2,000Number of people in room: 0 People profile number: 0Lighting profile number: 0 Equipment profile number: 0Ceiling height (feet): 19.60 Heating safety factor (%): 10Sensible safety factor (%): 10 Latent safety factor (%): 10Sensible heat per person (Btuh): 250 Latent heat per person (Btuh): 200Cooling ventilation method: CFM/Pr Cooling ventilation value: 10.000Cooling infiltration method: AC/Hr Cooling infiltration value: 0.000Heating ventilation method: CFM/Pr Heating ventilation value: 0.000Heating infiltration method: AC/Hr Heating infiltration value: 0.000Winter exhaust air CFM: 0 Summer exhaust air CFM: 0Minimum supply CFM: 0 Latent Btuh equipment load: 0Ceil. exposed to plenum (sq.ft): 46 Exposed floor slab perimeter (ft): 0Cooling loads only are calculated for this room.

    Roof Type ASHRAE# U-Factor Dark Length Width Area Susp.Ceil

    1 1 8 0.126 Yes 46.00 1.00 46.0 No

    Part Type U-Factor Cool TD Heat TD Height Width Area

    2 1 0.415 9.000 9.000 8.90 7.00 62.34 1 0.415 9.000 9.000 8.90 9.84 87.6

    Wall Type ASHRAE# U-Factor Color Height Width Area Direction

    1 1 D 0.415 D 8.90 7.00 62.3 N3 1 D 0.415 D 8.90 9.84 87.6 W

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 14

    Plenum Input

    Plenum Number 1 Input Data

    Air Handler Number: 1Plenum active: NoPercent of light load to rooms: 100Floor u-factor (Btuh/Sq.ft-F): 0.000Watts of equipment: 0Summer plenum-room temp. difference (deg.F): 0Winter plenum-room temp. difference (deg.F): 0

    Roof Type ASHRAE# U-Factor Dark Length Width Area Susp.Ceil

    1 1 8 0.126 Yes 14.00 9.00 126.0 No

    Plenum Number 2 Input Data

    Air Handler Number: 2Plenum active: NoPercent of light load to rooms: 100Floor u-factor (Btuh/Sq.ft-F): 0.000Watts of equipment: 0Summer plenum-room temp. difference (deg.F): 0Winter plenum-room temp. difference (deg.F): 0

    Plenum Number 3 Input Data

    Air Handler Number: 3Plenum active: NoPercent of light load to rooms: 100Floor u-factor (Btuh/Sq.ft-F): 0.000Watts of equipment: 0Summer plenum-room temp. difference (deg.F): 0Winter plenum-room temp. difference (deg.F): 0

    Plenum Number 4 Input Data

    Air Handler Number: 4Plenum active: NoPercent of light load to rooms: 100Floor u-factor (Btuh/Sq.ft-F): 0.000Watts of equipment: 0Summer plenum-room temp. difference (deg.F): 0Winter plenum-room temp. difference (deg.F): 0

    Plenum Number 5 Input Data

    Air Handler Number: 5Plenum active: NoPercent of light load to rooms: 100Floor u-factor (Btuh/Sq.ft-F): 0.000Watts of equipment: 0Summer plenum-room temp. difference (deg.F): 0Winter plenum-room temp. difference (deg.F): 0

    Plenum Number 6 Input Data

    Air Handler Number: 6Plenum active: NoPercent of light load to rooms: 100Floor u-factor (Btuh/Sq.ft-F): 0.000Watts of equipment: 0Summer plenum-room temp. difference (deg.F): 0Winter plenum-room temp. difference (deg.F): 0

    Plenum Number 7 Input Data

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 15

    Plenum Input (cont'd)

    Plenum Number 7 Input DataAir Handler Number: 7Plenum active: NoPercent of light load to rooms: 100Floor u-factor (Btuh/Sq.ft-F): 0.000Watts of equipment: 0Summer plenum-room temp. difference (deg.F): 0Winter plenum-room temp. difference (deg.F): 0

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 16

    Building Envelope Report

    Envelope Report Using Summer U-Factors

    MaterialTypes

    GrossArea

    GlassArea

    NetArea

    -U-Factor

    Area xU-Factor

    AverageU-Factor

    Roof 1 980.0 0.0 980.0 0.126 123.480 0.126Tot.Roof 980.0 0.0 980.0 N/A 123.480 0.126

    Wall 1 1,142.0 438.0 704.0 0.415 292.150 0.415Tot.Wall 1,142.0 438.0 704.0 N/A 292.150 0.415

    Glass 1 438.0 N/A 438.0 0.810 354.780 0.810Tot.Glass 438.0 N/A 438.0 N/A 354.780 0.810

    Totals 2,122.0 770.410 0.363

    WallDirection

    WallArea

    GlassArea

    Wall NetArea

    Wall AvgU-Factor

    Glass AvgU-Factor

    Glass AvgShd.Coef

    N 254.3 0.0 254.3 0.415 0.000 0.000NE 0.0 0.0 0.0 0.000 0.000 0.000E 112.5 0.0 112.5 0.415 0.000 0.000SE 0.0 0.0 0.0 0.000 0.000 0.000S 439.6 270.0 169.6 0.415 0.810 0.880SW 0.0 0.0 0.0 0.000 0.000 0.000W 335.6 168.0 167.6 0.415 0.810 0.880NW 0.0 0.0 0.0 0.000 0.000 0.000

    Totals 1,142.0 438.0 704.0 0.415 0.810 0.880

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 17

    Air Handler #1 - Ue-01 - Summary Loads for Zones (Z)

    ZnNo

    DescriptionZone Peak Time

    AreaPeople

    Volume

    Htg.LossHtg.CFMCFM/Sqft

    Sen.GainClg.CFM

    CFM/Sqft

    Lat.GainS.Exh

    W.Exh

    Htg.O.A.Req.CFMAct.CFM

    Clg.O.A.Req.CFMAct.CFM

    0 Zone 05pm February

    1266

    1,008

    00

    0.00

    30,9921,68113.34

    1,32000

    n/a00

    n/a6060

    Zone Peak Totals:Total Zones: 1

    1266

    1,008

    00

    0.00

    30,9921,68113.34

    1,32000

    00

    6060

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 18

    Air Handler #2 - Ue-02 - Summary Loads for Zones (Z)

    ZnNo

    DescriptionZone Peak Time

    AreaPeople

    Volume

    Htg.LossHtg.CFMCFM/Sqft

    Sen.GainClg.CFM

    CFM/Sqft

    Lat.GainS.Exh

    W.Exh

    Htg.O.A.Req.CFMAct.CFM

    Clg.O.A.Req.CFMAct.CFM

    0 Zone 05pm February

    633

    504

    00

    0.00

    15,609847

    13.44

    66000

    n/a00

    n/a3030

    Zone Peak Totals:Total Zones: 1

    633

    504

    00

    0.00

    15,609847

    13.44

    66000

    00

    3030

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 19

    Air Handler #3 - Fc-01 - Summary Loads for Zones (Z)

    ZnNo

    DescriptionZone Peak Time

    AreaPeople

    Volume

    Htg.LossHtg.CFMCFM/Sqft

    Sen.GainClg.CFM

    CFM/Sqft

    Lat.GainS.Exh

    W.Exh

    Htg.O.A.Req.CFMAct.CFM

    Clg.O.A.Req.CFMAct.CFM

    0 Zone 08pm February

    1004

    800

    00

    0.00

    7,900429

    4.29

    88000

    n/a00

    n/a6060

    Zone Peak Totals:Total Zones: 1

    1004

    800

    00

    0.00

    7,900429

    4.29

    88000

    00

    6060

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 20

    Air Handler #4 - Fc-02 - Summary Loads for Zones (Z)

    ZnNo

    DescriptionZone Peak Time

    AreaPeople

    Volume

    Htg.LossHtg.CFMCFM/Sqft

    Sen.GainClg.CFM

    CFM/Sqft

    Lat.GainS.Exh

    W.Exh

    Htg.O.A.Req.CFMAct.CFM

    Clg.O.A.Req.CFMAct.CFM

    0 Zone 08pm February

    1397

    1,112

    00

    0.00

    6,863372

    2.68

    1,54000

    n/a00

    n/a7070

    Zone Peak Totals:Total Zones: 1

    1397

    1,112

    00

    0.00

    6,863372

    2.68

    1,54000

    00

    7070

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 21

    Air Handler #5 - Ue-05 - Summary Loads for Zones (Z)

    ZnNo

    DescriptionZone Peak Time

    AreaPeople

    Volume

    Htg.LossHtg.CFMCFM/Sqft

    Sen.GainClg.CFM

    CFM/Sqft

    Lat.GainS.Exh

    W.Exh

    Htg.O.A.Req.CFMAct.CFM

    Clg.O.A.Req.CFMAct.CFM

    0 Zone 05pm February

    38820

    7,605

    00

    0.00

    27,3061,4813.82

    4,40000

    n/a00

    n/a200200

    Zone Peak Totals:Total Zones: 1

    38820

    7,605

    00

    0.00

    27,3061,4813.82

    4,40000

    00

    200200

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 22

    Air Handler #6 - Ue-03 - Summary Loads for Zones (Z)

    ZnNo

    DescriptionZone Peak Time

    AreaPeople

    Volume

    Htg.LossHtg.CFMCFM/Sqft

    Sen.GainClg.CFM

    CFM/Sqft

    Lat.GainS.Exh

    W.Exh

    Htg.O.A.Req.CFMAct.CFM

    Clg.O.A.Req.CFMAct.CFM

    0 Zone 02pm February

    11810

    1,062

    00

    0.00

    22,9751,24610.56

    2,20000

    n/a00

    n/a100100

    Zone Peak Totals:Total Zones: 1

    11810

    1,062

    00

    0.00

    22,9751,24610.56

    2,20000

    00

    100100

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 23

    Air Handler #7 - Ue-04 - Summary Loads for Zones (Z)

    ZnNo

    DescriptionZone Peak Time

    AreaPeople

    Volume

    Htg.LossHtg.CFMCFM/Sqft

    Sen.GainClg.CFM

    CFM/Sqft

    Lat.GainS.Exh

    W.Exh

    Htg.O.A.Req.CFMAct.CFM

    Clg.O.A.Req.CFMAct.CFM

    0 Zone 08pm February

    460

    902

    00

    0.00

    11,610827

    17.98

    10100

    n/a00

    n/a55

    Zone Peak Totals:Total Zones: 1

    460

    902

    00

    0.00

    11,610827

    17.98

    10100

    00

    55

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 24

    Air Handler #1 - Ue-01 - Summary Loads for Rooms (Z)

    RmNo

    DescriptionZone Peak Time

    AreaPeople

    Volume

    Htg.LossHtg.CFMCFM/Sqft

    Sen.GainClg.CFM

    CFM/Sqft

    Lat.GainS.Exh

    W.Exh

    Htg.O.A.Req.CFMAct.CFM

    Clg.O.A.Req.CFMAct.CFM

    1 Plataforma 1-25pm February

    1266

    1,008

    00

    0.00

    30,9921,68113.34

    1,32000

    None00

    10/P6060

    Room Peak Totals:Total Rooms: 1

    1266

    1,008

    00

    0.00

    30,9921,68113.34

    1,32000

    00

    6060

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 25

    Air Handler #1 - Ue-01 - Total Load Summary (Z)Air Handler Description: Ue-01 Constant Volume - Sum of PeaksSupply Air Fan: Draw-Thru with program estimated horsepower of 0.16 HPFan Input: 0% motor and fan efficiency with 0 in. water across the fanSensible Heat Ratio: 0.96 --- This system occurs 1 time(s) in the building. ---

    Air System Peak Time: 5pm in February. Outdoor Conditions: Clg: 87 DB, 74 WB, 106.28 grainsIndoor Conditions: Clg: 72 DB, 55% RH

    Summer: Ventilation controls outside air, ----- Winter: Exhaust controls outside air.

    Room Space sensible loss: 0 BtuhInfiltration sensible loss: 0 Btuh 0 CFMOutside Air sensible loss: 0 Btuh 0 CFMSupply Duct sensible loss: 0 BtuhReturn Duct sensible loss: 0 BtuhReturn Plenum sensible loss: 0 BtuhTotal System sensible loss: 0 Btuh

    Heating Supply Air: 0 / (.998 X 1.08 X 0) = 0 CFMWinter Vent Outside Air (0.0% of supply) = 0 CFM

    Room space sensible gain: 30,992 BtuhInfiltration sensible gain: 0 BtuhDraw-thru fan sensible gain: 402 BtuhSupply duct sensible gain: 0 BtuhReserve sensible gain: 0 BtuhTotal sensible gain on supply side of coil: 31,394 Btuh

    Cooling Supply Air: 31,394 / (.998 X 1.1 X 17) = 1,681 CFMSummer Vent Outside Air (3.6% of supply) = 60 CFM

    Return duct sensible gain: 0 BtuhReturn plenum sensible gain: 0 BtuhOutside air sensible gain: 988 Btuh 60 CFMBlow-thru fan sensible gain: 0 BtuhTotal sensible gain on return side of coil: 988 BtuhTotal sensible gain on air handling system: 32,383 Btuh

    Room space latent gain: 1,320 BtuhInfiltration latent gain: 0 BtuhOutside air latent gain: 1,684 BtuhTotal latent gain on air handling system: 3,004 BtuhTotal system sensible and latent gain: 35,387 Btuh

    Check FiguresTotal Air Handler Supply Air (based on a 17 TD): 1,681 CFMTotal Air Handler Vent. Air (3.57% of Supply): 60 CFM

    Total Conditioned Air Space: 126 Sq.ftSupply Air Per Unit Area: 13.3444 CFM/Sq.ftArea Per Cooling Capacity: 42.7 Sq.ft/TonCooling Capacity Per Area: 0.0234 Tons/Sq.ftHeating Capacity Per Area: 0.00 Btuh/Sq.ft

    Total Heating Required With Outside Air: 0 BtuhTotal Cooling Required With Outside Air: 2.95 Tons

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 26

    Air Handler #2 - Ue-02 - Summary Loads for Rooms (Z)

    RmNo

    DescriptionZone Peak Time

    AreaPeople

    Volume

    Htg.LossHtg.CFMCFM/Sqft

    Sen.GainClg.CFM

    CFM/Sqft

    Lat.GainS.Exh

    W.Exh

    Htg.O.A.Req.CFMAct.CFM

    Clg.O.A.Req.CFMAct.CFM

    2 Gerente De Tienda5pm February

    633

    504

    00

    0.00

    15,609847

    13.44

    66000

    None00

    10/P3030

    Room Peak Totals:Total Rooms: 1

    633

    504

    00

    0.00

    15,609847

    13.44

    66000

    00

    3030

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 27

    Air Handler #2 - Ue-02 - Total Load Summary (Z)Air Handler Description: Ue-02 Constant Volume - Sum of PeaksSupply Air Fan: Draw-Thru with program estimated horsepower of 0.08 HPFan Input: 0% motor and fan efficiency with 0 in. water across the fanSensible Heat Ratio: 0.96 --- This system occurs 1 time(s) in the building. ---

    Air System Peak Time: 5pm in February. Outdoor Conditions: Clg: 87 DB, 74 WB, 106.28 grainsIndoor Conditions: Clg: 72 DB, 55% RH

    Summer: Ventilation controls outside air, ----- Winter: Exhaust controls outside air.

    Room Space sensible loss: 0 BtuhInfiltration sensible loss: 0 Btuh 0 CFMOutside Air sensible loss: 0 Btuh 0 CFMSupply Duct sensible loss: 0 BtuhReturn Duct sensible loss: 0 BtuhReturn Plenum sensible loss: 0 BtuhTotal System sensible loss: 0 Btuh

    Heating Supply Air: 0 / (.998 X 1.08 X 0) = 0 CFMWinter Vent Outside Air (0.0% of supply) = 0 CFM

    Room space sensible gain: 15,609 BtuhInfiltration sensible gain: 0 BtuhDraw-thru fan sensible gain: 203 BtuhSupply duct sensible gain: 0 BtuhReserve sensible gain: 0 BtuhTotal sensible gain on supply side of coil: 15,812 Btuh

    Cooling Supply Air: 15,812 / (.998 X 1.1 X 17) = 847 CFMSummer Vent Outside Air (3.5% of supply) = 30 CFM

    Return duct sensible gain: 0 BtuhReturn plenum sensible gain: 0 BtuhOutside air sensible gain: 494 Btuh 30 CFMBlow-thru fan sensible gain: 0 BtuhTotal sensible gain on return side of coil: 494 BtuhTotal sensible gain on air handling system: 16,306 Btuh

    Room space latent gain: 660 BtuhInfiltration latent gain: 0 BtuhOutside air latent gain: 842 BtuhTotal latent gain on air handling system: 1,502 BtuhTotal system sensible and latent gain: 17,808 Btuh

    Check FiguresTotal Air Handler Supply Air (based on a 17 TD): 847 CFMTotal Air Handler Vent. Air (3.54% of Supply): 30 CFM

    Total Conditioned Air Space: 63 Sq.ftSupply Air Per Unit Area: 13.4413 CFM/Sq.ftArea Per Cooling Capacity: 42.5 Sq.ft/TonCooling Capacity Per Area: 0.0236 Tons/Sq.ftHeating Capacity Per Area: 0.00 Btuh/Sq.ft

    Total Heating Required With Outside Air: 0 BtuhTotal Cooling Required With Outside Air: 1.48 Tons

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 28

    Air Handler #3 - Fc-01 - Summary Loads for Rooms (Z)

    RmNo

    DescriptionZone Peak Time

    AreaPeople

    Volume

    Htg.LossHtg.CFMCFM/Sqft

    Sen.GainClg.CFM

    CFM/Sqft

    Lat.GainS.Exh

    W.Exh

    Htg.O.A.Req.CFMAct.CFM

    Clg.O.A.Req.CFMAct.CFM

    3Gerente Asist.-Embosadora8pm February

    1004

    800

    00

    0.00

    7,900429

    4.29

    88000

    None00

    15/P6060

    Room Peak Totals:Total Rooms: 1

    1004

    800

    00

    0.00

    7,900429

    4.29

    88000

    00

    6060

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 29

    Air Handler #3 - Fc-01 - Total Load Summary (Z)Air Handler Description: Fc-01 Constant Volume - Sum of PeaksSupply Air Fan: Draw-Thru with program estimated horsepower of 0.04 HPFan Input: 0% motor and fan efficiency with 0 in. water across the fanSensible Heat Ratio: 0.90 --- This system occurs 1 time(s) in the building. ---

    Air System Peak Time: 8pm in February. Outdoor Conditions: Clg: 82 DB, 73 WB, 107.10 grainsIndoor Conditions: Clg: 72 DB, 55% RH

    Summer: Ventilation controls outside air, ----- Winter: Exhaust controls outside air.

    Room Space sensible loss: 0 BtuhInfiltration sensible loss: 0 Btuh 0 CFMOutside Air sensible loss: 0 Btuh 0 CFMSupply Duct sensible loss: 0 BtuhReturn Duct sensible loss: 0 BtuhReturn Plenum sensible loss: 0 BtuhTotal System sensible loss: 0 Btuh

    Heating Supply Air: 0 / (.998 X 1.08 X 0) = 0 CFMWinter Vent Outside Air (0.0% of supply) = 0 CFM

    Room space sensible gain: 7,900 BtuhInfiltration sensible gain: 0 BtuhDraw-thru fan sensible gain: 103 BtuhSupply duct sensible gain: 0 BtuhReserve sensible gain: 0 BtuhTotal sensible gain on supply side of coil: 8,003 Btuh

    Cooling Supply Air: 8,003 / (.998 X 1.1 X 17) = 429 CFMSummer Vent Outside Air (14.0% of supply) = 60 CFM

    Return duct sensible gain: 0 BtuhReturn plenum sensible gain: 0 BtuhOutside air sensible gain: 659 Btuh 60 CFMBlow-thru fan sensible gain: 0 BtuhTotal sensible gain on return side of coil: 659 BtuhTotal sensible gain on air handling system: 8,662 Btuh

    Room space latent gain: 880 BtuhInfiltration latent gain: 0 BtuhOutside air latent gain: 1,775 BtuhTotal latent gain on air handling system: 2,655 BtuhTotal system sensible and latent gain: 11,316 Btuh

    Check FiguresTotal Air Handler Supply Air (based on a 17 TD): 429 CFMTotal Air Handler Vent. Air (14.00% of Supply): 60 CFM

    Total Conditioned Air Space: 100 Sq.ftSupply Air Per Unit Area: 4.2858 CFM/Sq.ftArea Per Cooling Capacity: 106.0 Sq.ft/TonCooling Capacity Per Area: 0.0094 Tons/Sq.ftHeating Capacity Per Area: 0.00 Btuh/Sq.ft

    Total Heating Required With Outside Air: 0 BtuhTotal Cooling Required With Outside Air: 0.94 Tons

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 30

    Air Handler #4 - Fc-02 - Summary Loads for Rooms (Z)

    RmNo

    DescriptionZone Peak Time

    AreaPeople

    Volume

    Htg.LossHtg.CFMCFM/Sqft

    Sen.GainClg.CFM

    CFM/Sqft

    Lat.GainS.Exh

    W.Exh

    Htg.O.A.Req.CFMAct.CFM

    Clg.O.A.Req.CFMAct.CFM

    4 Counter8pm February

    1397

    1,112

    00

    0.00

    6,863372

    2.68

    1,54000

    None00

    10/P7070

    Room Peak Totals:Total Rooms: 1

    1397

    1,112

    00

    0.00

    6,863372

    2.68

    1,54000

    00

    7070

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 31

    Air Handler #4 - Fc-02 - Total Load Summary (Z)Air Handler Description: Fc-02 Constant Volume - Sum of PeaksSupply Air Fan: Draw-Thru with program estimated horsepower of 0.04 HPFan Input: 0% motor and fan efficiency with 0 in. water across the fanSensible Heat Ratio: 0.82 --- This system occurs 1 time(s) in the building. ---

    Air System Peak Time: 5pm in February. Outdoor Conditions: Clg: 87 DB, 74 WB, 106.28 grainsIndoor Conditions: Clg: 72 DB, 55% RH

    Summer: Ventilation controls outside air, ----- Winter: Exhaust controls outside air.

    Room Space sensible loss: 0 BtuhInfiltration sensible loss: 0 Btuh 0 CFMOutside Air sensible loss: 0 Btuh 0 CFMSupply Duct sensible loss: 0 BtuhReturn Duct sensible loss: 0 BtuhReturn Plenum sensible loss: 0 BtuhTotal System sensible loss: 0 Btuh

    Heating Supply Air: 0 / (.998 X 1.08 X 0) = 0 CFMWinter Vent Outside Air (0.0% of supply) = 0 CFM

    Room space sensible gain: 6,673 BtuhInfiltration sensible gain: 0 BtuhDraw-thru fan sensible gain: 89 BtuhSupply duct sensible gain: 0 BtuhReserve sensible gain: 0 BtuhTotal sensible gain on supply side of coil: 6,762 Btuh

    Cooling Supply Air: 6,953 / (.998 X 1.1 X 17) = 372 CFMSummer Vent Outside Air (18.8% of supply) = 70 CFM

    Return duct sensible gain: 0 BtuhReturn plenum sensible gain: 0 BtuhOutside air sensible gain: 1,153 Btuh 70 CFMBlow-thru fan sensible gain: 0 BtuhTotal sensible gain on return side of coil: 1,153 BtuhTotal sensible gain on air handling system: 7,915 Btuh

    Room space latent gain: 1,540 BtuhInfiltration latent gain: 0 BtuhOutside air latent gain: 1,965 BtuhTotal latent gain on air handling system: 3,505 BtuhTotal system sensible and latent gain: 11,420 Btuh

    Check FiguresTotal Air Handler Supply Air (based on a 17 TD): 372 CFMTotal Air Handler Vent. Air (18.80% of Supply): 70 CFM

    Total Conditioned Air Space: 139 Sq.ftSupply Air Per Unit Area: 2.6787 CFM/Sq.ftArea Per Cooling Capacity: 146.1 Sq.ft/TonCooling Capacity Per Area: 0.0068 Tons/Sq.ftHeating Capacity Per Area: 0.00 Btuh/Sq.ft

    Total Heating Required With Outside Air: 0 BtuhTotal Cooling Required With Outside Air: 0.95 Tons

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 32

    Air Handler #5 - Ue-05 - Summary Loads for Rooms (Z)

    RmNo

    DescriptionZone Peak Time

    AreaPeople

    Volume

    Htg.LossHtg.CFMCFM/Sqft

    Sen.GainClg.CFM

    CFM/Sqft

    Lat.GainS.Exh

    W.Exh

    Htg.O.A.Req.CFMAct.CFM

    Clg.O.A.Req.CFMAct.CFM

    5 Area Comun5pm February

    38820

    7,605

    00

    0.00

    27,3061,4813.82

    4,40000

    None00

    10/P200200

    Room Peak Totals:Total Rooms: 1

    38820

    7,605

    00

    0.00

    27,3061,4813.82

    4,40000

    00

    200200

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 33

    Air Handler #5 - Ue-05 - Total Load Summary (Z)Air Handler Description: Ue-05 Constant Volume - Sum of PeaksSupply Air Fan: Draw-Thru with program estimated horsepower of 0.14 HPFan Input: 0% motor and fan efficiency with 0 in. water across the fanSensible Heat Ratio: 0.86 --- This system occurs 1 time(s) in the building. ---

    Air System Peak Time: 5pm in February. Outdoor Conditions: Clg: 87 DB, 74 WB, 106.28 grainsIndoor Conditions: Clg: 72 DB, 55% RH

    Summer: Ventilation controls outside air, ----- Winter: Exhaust controls outside air.

    Room Space sensible loss: 0 BtuhInfiltration sensible loss: 0 Btuh 0 CFMOutside Air sensible loss: 0 Btuh 0 CFMSupply Duct sensible loss: 0 BtuhReturn Duct sensible loss: 0 BtuhReturn Plenum sensible loss: 0 BtuhTotal System sensible loss: 0 Btuh

    Heating Supply Air: 0 / (.998 X 1.08 X 0) = 0 CFMWinter Vent Outside Air (0.0% of supply) = 0 CFM

    Room space sensible gain: 27,306 BtuhInfiltration sensible gain: 0 BtuhDraw-thru fan sensible gain: 354 BtuhSupply duct sensible gain: 0 BtuhReserve sensible gain: 0 BtuhTotal sensible gain on supply side of coil: 27,660 Btuh

    Cooling Supply Air: 27,660 / (.998 X 1.1 X 17) = 1,481 CFMSummer Vent Outside Air (13.5% of supply) = 200 CFM

    Return duct sensible gain: 0 BtuhReturn plenum sensible gain: 0 BtuhOutside air sensible gain: 3,295 Btuh 200 CFMBlow-thru fan sensible gain: 0 BtuhTotal sensible gain on return side of coil: 3,295 BtuhTotal sensible gain on air handling system: 30,955 Btuh

    Room space latent gain: 4,400 BtuhInfiltration latent gain: 0 BtuhOutside air latent gain: 5,613 BtuhTotal latent gain on air handling system: 10,013 BtuhTotal system sensible and latent gain: 40,968 Btuh

    Check FiguresTotal Air Handler Supply Air (based on a 17 TD): 1,481 CFMTotal Air Handler Vent. Air (13.50% of Supply): 200 CFM

    Total Conditioned Air Space: 388 Sq.ftSupply Air Per Unit Area: 3.8180 CFM/Sq.ftArea Per Cooling Capacity: 113.6 Sq.ft/TonCooling Capacity Per Area: 0.0088 Tons/Sq.ftHeating Capacity Per Area: 0.00 Btuh/Sq.ft

    Total Heating Required With Outside Air: 0 BtuhTotal Cooling Required With Outside Air: 3.41 Tons

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 34

    Air Handler #6 - Ue-03 - Summary Loads for Rooms (Z)

    RmNo

    DescriptionZone Peak Time

    AreaPeople

    Volume

    Htg.LossHtg.CFMCFM/Sqft

    Sen.GainClg.CFM

    CFM/Sqft

    Lat.GainS.Exh

    W.Exh

    Htg.O.A.Req.CFMAct.CFM

    Clg.O.A.Req.CFMAct.CFM

    6 Banca Electronica2pm February

    11810

    1,062

    00

    0.00

    22,9751,24610.56

    2,20000

    None00

    10/P100100

    Room Peak Totals:Total Rooms: 1

    11810

    1,062

    00

    0.00

    22,9751,24610.56

    2,20000

    00

    100100

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 35

    Air Handler #6 - Ue-03 - Total Load Summary (Z)Air Handler Description: Ue-03 Constant Volume - Sum of PeaksSupply Air Fan: Draw-Thru with program estimated horsepower of 0.12 HPFan Input: 0% motor and fan efficiency with 0 in. water across the fanSensible Heat Ratio: 0.91 --- This system occurs 1 time(s) in the building. ---

    Air System Peak Time: 2pm in February. Outdoor Conditions: Clg: 87 DB, 74 WB, 104.97 grainsIndoor Conditions: Clg: 72 DB, 55% RH

    Summer: Ventilation controls outside air, ----- Winter: Exhaust controls outside air.

    Room Space sensible loss: 0 BtuhInfiltration sensible loss: 0 Btuh 0 CFMOutside Air sensible loss: 0 Btuh 0 CFMSupply Duct sensible loss: 0 BtuhReturn Duct sensible loss: 0 BtuhReturn Plenum sensible loss: 0 BtuhTotal System sensible loss: 0 Btuh

    Heating Supply Air: 0 / (.998 X 1.08 X 0) = 0 CFMWinter Vent Outside Air (0.0% of supply) = 0 CFM

    Room space sensible gain: 22,975 BtuhInfiltration sensible gain: 0 BtuhDraw-thru fan sensible gain: 298 BtuhSupply duct sensible gain: 0 BtuhReserve sensible gain: 0 BtuhTotal sensible gain on supply side of coil: 23,273 Btuh

    Cooling Supply Air: 23,273 / (.998 X 1.1 X 17) = 1,246 CFMSummer Vent Outside Air (8.0% of supply) = 100 CFM

    Return duct sensible gain: 0 BtuhReturn plenum sensible gain: 0 BtuhOutside air sensible gain: 1,757 Btuh 100 CFMBlow-thru fan sensible gain: 0 BtuhTotal sensible gain on return side of coil: 1,757 BtuhTotal sensible gain on air handling system: 25,030 Btuh

    Room space latent gain: 2,200 BtuhInfiltration latent gain: 0 BtuhOutside air latent gain: 2,806 BtuhTotal latent gain on air handling system: 5,006 BtuhTotal system sensible and latent gain: 30,037 Btuh

    Check FiguresTotal Air Handler Supply Air (based on a 17 TD): 1,246 CFMTotal Air Handler Vent. Air (8.02% of Supply): 100 CFM

    Total Conditioned Air Space: 118 Sq.ftSupply Air Per Unit Area: 10.5626 CFM/Sq.ftArea Per Cooling Capacity: 47.1 Sq.ft/TonCooling Capacity Per Area: 0.0212 Tons/Sq.ftHeating Capacity Per Area: 0.00 Btuh/Sq.ft

    Total Heating Required With Outside Air: 0 BtuhTotal Cooling Required With Outside Air: 2.50 Tons

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 36

    Air Handler #7 - Ue-04 - Summary Loads for Rooms (Z)

    RmNo

    DescriptionZone Peak Time

    AreaPeople

    Volume

    Htg.LossHtg.CFMCFM/Sqft

    Sen.GainClg.CFM

    CFM/Sqft

    Lat.GainS.Exh

    W.Exh

    Htg.O.A.Req.CFMAct.CFM

    Clg.O.A.Req.CFMAct.CFM

    7 Rack8pm February

    460

    902

    00

    0.00

    11,610827

    17.98

    10100

    None00

    10/P55

    Room Peak Totals:Total Rooms: 1

    460

    902

    00

    0.00

    11,610827

    17.98

    10100

    00

    55

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 37

    Air Handler #7 - Ue-04 - Total Load Summary (Z)Air Handler Description: Ue-04 Constant Volume - Sum of PeaksSupply Air Fan: Draw-Thru with program estimated horsepower of 0.08 HPFan Input: 0% motor and fan efficiency with 0 in. water across the fanSensible Heat Ratio: 0.99 --- This system occurs 1 time(s) in the building. ---

    Air System Peak Time: 8pm in February. Outdoor Conditions: Clg: 82 DB, 73 WB, 107.10 grainsIndoor Conditions: Clg: 68 DB, 50% RH

    Summer: Ventilation controls outside air, ----- Winter: Exhaust controls outside air.

    Room Space sensible loss: 0 BtuhInfiltration sensible loss: 0 Btuh 0 CFMOutside Air sensible loss: 0 Btuh 0 CFMSupply Duct sensible loss: 0 BtuhReturn Duct sensible loss: 0 BtuhReturn Plenum sensible loss: 0 BtuhTotal System sensible loss: 0 Btuh

    Heating Supply Air: 0 / (.998 X 1.08 X 0) = 0 CFMWinter Vent Outside Air (0.0% of supply) = 0 CFM

    Room space sensible gain: 11,610 BtuhInfiltration sensible gain: 0 BtuhDraw-thru fan sensible gain: 198 BtuhSupply duct sensible gain: 0 BtuhReserve sensible gain: 0 BtuhTotal sensible gain on supply side of coil: 11,808 Btuh

    Cooling Supply Air: 11,808 / (.998 X 1.1 X 13) = 827 CFMSummer Vent Outside Air (0.6% of supply) = 5 CFM

    Return duct sensible gain: 0 BtuhReturn plenum sensible gain: 0 BtuhOutside air sensible gain: 71 Btuh 5 CFMBlow-thru fan sensible gain: 0 BtuhTotal sensible gain on return side of coil: 71 BtuhTotal sensible gain on air handling system: 11,878 Btuh

    Room space latent gain: 101 BtuhInfiltration latent gain: 0 BtuhOutside air latent gain: 178 BtuhTotal latent gain on air handling system: 279 BtuhTotal system sensible and latent gain: 12,158 Btuh

    Check FiguresTotal Air Handler Supply Air (based on a 13 TD): 827 CFMTotal Air Handler Vent. Air (0.56% of Supply): 5 CFM

    Total Conditioned Air Space: 46 Sq.ftSupply Air Per Unit Area: 17.9766 CFM/Sq.ftArea Per Cooling Capacity: 45.4 Sq.ft/TonCooling Capacity Per Area: 0.0220 Tons/Sq.ftHeating Capacity Per Area: 0.00 Btuh/Sq.ft

    Total Heating Required With Outside Air: 0 BtuhTotal Cooling Required With Outside Air: 1.01 Tons

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 38

    Zone Detailed Loads (At Zone Peak Times)

    LoadDescription

    UnitQuan

    -SC-CFAC

    CLTDSHGF

    U.Fac-CLF-

    Sen.Gain

    Lat.Gain

    Htg.Mult.

    Htg.Loss

    Room 1-Plataforma 1-2 - Air Handler 1 (Ue-01), Zone 0 peaks (sensible) in February at 5pm.

    Roof-1-8-No.Clg-D 126 1.00 48.6 0.126 771 2.142 270Wall-1-W-D-D 0 1 26.1 0.415 0 0.000 0Wall-3-N-D-D 72 1 23.6 0.415 704 7.055 508Partition-2-1 112 9/9 0.415 418 3.735 418Partition-4-1 72 9/9 0.415 269 3.735 269Gls-W-1-90-Tran 112.0 1.000 16 0.810 1,456 14.110 1,580 0%S-0-UNS-Solar 112.0 0.880 240 0.930 21,999Lights-Prof=0 214 1.000 731Equipment-Prof=0 96 1.000 328 0People-Prof=0 6.0 1.000 1,500 1,200

    Sub-total 28,175 1,200 0Safety factors: +10%

    ---------

    +10%---------

    +10%---------

    Total w/ safety factors: 30,992 1,320 0

    Room 2-Gerente De Tienda - Air Handler 2 (Ue-02), Zone 0 peaks (sensible) in February at 5pm.

    Roof-1-8-No.Clg-D 63 1.00 48.6 0.126 385 2.142 135Wall-1-W-D-D 0 1 26.1 0.415 0 0.000 0Partition-2-1 56 9/9 0.415 209 3.735 209Partition-3-1 72 9/9 0.415 269 3.735 269Partition-4-1 72 9/9 0.415 269 3.735 269Gls-W-1-90-Tran 56.0 1.000 16 0.810 728 14.110 790 0%S-0-UNS-Solar 56.0 0.880 240 0.930 10,999Lights-Prof=0 107 1.000 365Equipment-Prof=0 63 1.000 215 0People-Prof=0 3.0 1.000 750 600

    Sub-total 14,190 600 0Safety factors: +10%

    ---------

    +10%---------

    +10%---------

    Total w/ safety factors: 15,609 660 0

    Room 3-Gerente Asist.-Embosadora - Air Handler 3 (Fc-01), Zone 0 peaks (sensible) in February at 8pm.

    Roof-1-8-No.Clg-D 100 1.00 56.6 0.126 713 2.142 214Wall-1-W-D-D 80 1 42.1 0.415 1,396 7.055 564Wall-3-N-D-D 80 1 25.6 0.415 848 7.055 564Partition-2-1 80 9/9 0.415 299 3.735 299Partition-4-1 80 9/9 0.415 299 3.735 299Lights-Prof=0 170 1.000 580Equipment-Prof=0 600 1.000 2,047 0People-Prof=0 4.0 1.000 1,000 800

    Sub-total 7,182 800 0Safety factors: +10%

    ---------

    +10%---------

    +10%---------

    Total w/ safety factors: 7,900 880 0

    Room 4-Counter - Air Handler 4 (Fc-02), Zone 0 peaks (sensible) in February at 8pm.

    Roof-1-8-No.Clg-D 139 1.00 56.6 0.126 990 2.142 298Wall-2-N-D-D 40 1 25.6 0.415 424 7.055 282Partition-1-1 224 9/9 0.415 837 3.735 837Partition-3-1 208 9/9 0.415 777 3.735 777Lights-Prof=0 236 1.000 806

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 39

    Zone Detailed Loads (At Zone Peak Times) (cont'd)

    LoadDescription

    UnitQuan

    -SC-CFAC

    CLTDSHGF

    U.Fac-CLF-

    Sen.Gain

    Lat.Gain

    Htg.Mult.

    Htg.Loss

    Equipment-Prof=0 192 1.000 655 0People-Prof=0 7.0 1.000 1,750 1,400

    Sub-total 6,239 1,400 0Safety factors: +10%

    ---------

    +10%---------

    +10%---------

    Total w/ safety factors: 6,863 1,540 0

    Room 5-Area Comun - Air Handler 5 (Ue-05), Zone 0 peaks (sensible) in February at 5pm.

    Roof-1-8-No.Clg-D 388 1.00 48.6 0.126 2,374 2.142 831Wall-3-S-D-D 170 1 18.6 0.415 1,306 7.055 1,197Partition-1-1 1019.2 9/9 0.415 3,807 3.735 3,807Partition-2-2 313.6 9/9 0.810 2,286 7.290 2,286Gls-S-1-90-Tran 144.0 1.000 16 0.810 1,872 14.110 2,032 0%S-0-UNS-Solar 144.0 0.880 46 0.790 4,605Lights-Prof=0 660 1.000 2,251Equipment-Prof=0 388 1.000 1,324 0People-Prof=0 20.0 1.000 5,000 4,000

    Sub-total 24,824 4,000 0Safety factors: +10%

    ---------

    +10%---------

    +10%---------

    Total w/ safety factors: 27,306 4,400 0

    Room 6-Banca Electronica - Air Handler 6 (Ue-03), Zone 0 peaks (sensible) in February at 2pm.

    Roof-1-8-No.Clg-D 118 1.00 27.6 0.126 410 2.142 253Wall-2-E-D-D 113 1 34.1 0.415 1,590 7.055 794Wall-3-S-D-D 0 1 13.6 0.415 0 0.000 0Partition-1-1 198 9/9 0.415 740 3.735 740Gls-S-1-90-Tran 126.0 1.000 16 0.810 1,638 14.110 1,778 0%S-0-UNS-Solar 126.0 0.880 46 0.940 4,794Lights-Prof=0 201 1.000 684Equipment-Prof=0 2,500 1.000 8,530 0People-Prof=0 10.0 1.000 2,500 2,000

    Sub-total 20,886 2,000 0Safety factors: +10%

    ---------

    +10%---------

    +10%---------

    Total w/ safety factors: 22,975 2,200 0

    Room 7-Rack - Air Handler 7 (Ue-04), Zone 0 peaks (sensible) in February at 8pm.

    Roof-1-8-No.Clg-D 46 1.00 60.6 0.126 351 2.142 99Wall-1-N-D-D 62 1 29.6 0.415 764 7.055 440Wall-3-W-D-D 88 1 46.1 0.415 1,674 7.055 618Partition-2-1 62.3 9/9 0.415 233 3.735 233Partition-4-1 87.576 9/9 0.415 327 3.735 327Lights-Prof=0 78 1.000 267Equipment-Prof=0 2,000 1.000 6,824 0People-Prof=0 0.5 1.000 115 92

    Sub-total 10,554 92 0Safety factors: +10%

    ---------

    +10%---------

    +10%---------

    Total w/ safety factors: 11,610 101 0

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 40

    Room Detailed Loads (At Room Peak Times)

    LoadDescription

    UnitQuan

    -SC-CFAC

    CLTDSHGF

    U.Fac-CLF-

    Sen.Gain

    Lat.Gain

    Htg.Mult.

    Htg.Loss

    Room 1-Plataforma 1-2 peaks (sensible) in February at 5pm, Air Handler 1 (Ue-01), Zone 0, 14.0 x 9.0, Construction Type: 4 (Light)

    Roof-1-8-No.Clg-D 126 1.00 48.6 0.126 771 2.142 270Wall-1-W-D-D 0 1 26.1 0.415 0 0.000 0Wall-3-N-D-D 72 1 23.6 0.415 704 7.055 508Partition-2-1 112 9/9 0.415 418 3.735 418Partition-4-1 72 9/9 0.415 269 3.735 269Gls-W-1-90-Tran 112.0 1.000 16 0.810 1,456 14.110 1,580 0%S-0-UNS-Solar 112.0 0.880 240 0.930 21,999Lights-Prof=0 214 1.000 731Equipment-Prof=0 96 1.000 328 0People-Prof=0 6.0 1.000 1,500 1,200

    Sub-total 28,175 1,200 0Safety factors: +10%

    ---------

    +10%---------

    +10%---------

    Total w/ safety factors: 30,992 1,320 0

    Equipment Cooling Loads

    ItemName

    NominalOutput

    Sensible

    QuantityType

    Sensible

    NominalOutputLatent

    QuantityType

    Latent

    SensibleLoad

    (Btuh)LatentLoad

    (Btuh)Desktop computer,

    Manufacturer B (model B)

    3.0 GHz processor, 2 GB RAM

    48 watts 0 watts 328 0

    Total 328 0

    Room 2-Gerente De Tienda peaks (sensible) in February at 5pm, Air Handler 2 (Ue-02), Zone 0, 7.0 x 9.0, Construction Type: 1 (Light)

    Roof-1-8-No.Clg-D 63 1.00 48.6 0.126 385 2.142 135Wall-1-W-D-D 0 1 26.1 0.415 0 0.000 0Partition-2-1 56 9/9 0.415 209 3.735 209Partition-3-1 72 9/9 0.415 269 3.735 269Partition-4-1 72 9/9 0.415 269 3.735 269Gls-W-1-90-Tran 56.0 1.000 16 0.810 728 14.110 790 0%S-0-UNS-Solar 56.0 0.880 240 0.930 10,999Lights-Prof=0 107 1.000 365Equipment-Prof=0 63 1.000 215 0People-Prof=0 3.0 1.000 750 600

    Sub-total 14,190 600 0Safety factors: +10%

    ---------

    +10%---------

    +10%---------

    Total w/ safety factors: 15,609 660 0

    Room 3-Gerente Asist.-Embosadora peaks (sensible) in February at 8pm, Air Handler 3 (Fc-01), Zone 0, 10.0 x 10.0, Construction Type: 1 (Light)

    Roof-1-8-No.Clg-D 100 1.00 56.6 0.126 713 2.142 214Wall-1-W-D-D 80 1 42.1 0.415 1,396 7.055 564Wall-3-N-D-D 80 1 25.6 0.415 848 7.055 564Partition-2-1 80 9/9 0.415 299 3.735 299Partition-4-1 80 9/9 0.415 299 3.735 299Lights-Prof=0 170 1.000 580Equipment-Prof=0 600 1.000 2,047 0

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 41

    Room Detailed Loads (At Room Peak Times) (cont'd)

    LoadDescription

    UnitQuan

    -SC-CFAC

    CLTDSHGF

    U.Fac-CLF-

    Sen.Gain

    Lat.Gain

    Htg.Mult.

    Htg.Loss

    People-Prof=0 4.0 1.000 1,000 800

    Sub-total 7,182 800 0Safety factors: +10%

    ---------

    +10%---------

    +10%---------

    Total w/ safety factors: 7,900 880 0

    Room 4-Counter peaks (sensible) in February at 8pm, Air Handler 4 (Fc-02), Zone 0, 139.0 x 1.0, Construction Type: 1 (Light)

    Roof-1-8-No.Clg-D 139 1.00 56.6 0.126 990 2.142 298Wall-2-N-D-D 40 1 25.6 0.415 424 7.055 282Partition-1-1 224 9/9 0.415 837 3.735 837Partition-3-1 208 9/9 0.415 777 3.735 777Lights-Prof=0 236 1.000 806Equipment-Prof=0 192 1.000 655 0People-Prof=0 7.0 1.000 1,750 1,400

    Sub-total 6,239 1,400 0Safety factors: +10%

    ---------

    +10%---------

    +10%---------

    Total w/ safety factors: 6,863 1,540 0

    Equipment Cooling Loads

    ItemName

    NominalOutput

    Sensible

    QuantityType

    Sensible

    NominalOutputLatent

    QuantityType

    Latent

    SensibleLoad

    (Btuh)LatentLoad

    (Btuh)Desktop computer,

    Manufacturer B (model B)

    3.0 GHz processor, 2 GB RAM

    48 watts 0 watts 655 0

    Total 655 0

    Room 5-Area Comun peaks (sensible) in February at 5pm, Air Handler 5 (Ue-05), Zone 0, 388.0 x 1.0, Construction Type: 1 (Light)

    Roof-1-8-No.Clg-D 388 1.00 48.6 0.126 2,374 2.142 831Wall-3-S-D-D 170 1 18.6 0.415 1,306 7.055 1,197Partition-1-1 1019.2 9/9 0.415 3,807 3.735 3,807Partition-2-2 313.6 9/9 0.810 2,286 7.290 2,286Gls-S-1-90-Tran 144.0 1.000 16 0.810 1,872 14.110 2,032 0%S-0-UNS-Solar 144.0 0.880 46 0.790 4,605Lights-Prof=0 660 1.000 2,251Equipment-Prof=0 388 1.000 1,324 0People-Prof=0 20.0 1.000 5,000 4,000

    Sub-total 24,824 4,000 0Safety factors: +10%

    ---------

    +10%---------

    +10%---------

    Total w/ safety factors: 27,306 4,400 0

    Room 6-Banca Electronica peaks (sensible) in February at 2pm, Air Handler 6 (Ue-03), Zone 0, 118.0 x 1.0, Construction Type: 1 (Light)

    Roof-1-8-No.Clg-D 118 1.00 27.6 0.126 410 2.142 253Wall-2-E-D-D 113 1 34.1 0.415 1,590 7.055 794Wall-3-S-D-D 0 1 13.6 0.415 0 0.000 0

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 42

    Room Detailed Loads (At Room Peak Times) (cont'd)

    LoadDescription

    UnitQuan

    -SC-CFAC

    CLTDSHGF

    U.Fac-CLF-

    Sen.Gain

    Lat.Gain

    Htg.Mult.

    Htg.Loss

    Partition-1-1 198 9/9 0.415 740 3.735 740Gls-S-1-90-Tran 126.0 1.000 16 0.810 1,638 14.110 1,778 0%S-0-UNS-Solar 126.0 0.880 46 0.940 4,794Lights-Prof=0 201 1.000 684Equipment-Prof=0 2,500 1.000 8,530 0People-Prof=0 10.0 1.000 2,500 2,000

    Sub-total 20,886 2,000 0Safety factors: +10%

    ---------

    +10%---------

    +10%---------

    Total w/ safety factors: 22,975 2,200 0

    Room 7-Rack peaks (sensible) in February at 8pm, Air Handler 7 (Ue-04), Zone 0, 46.0 x 1.0, Construction Type: 4 (Light)

    Roof-1-8-No.Clg-D 46 1.00 60.6 0.126 351 2.142 99Wall-1-N-D-D 62 1 29.6 0.415 764 7.055 440Wall-3-W-D-D 88 1 46.1 0.415 1,674 7.055 618Partition-2-1 62.3 9/9 0.415 233 3.735 233Partition-4-1 87.576 9/9 0.415 327 3.735 327Lights-Prof=0 78 1.000 267Equipment-Prof=0 2,000 1.000 6,824 0People-Prof=0 0.5 1.000 115 92

    Sub-total 10,554 92 0Safety factors: +10%

    ---------

    +10%---------

    +10%---------

    Total w/ safety factors: 11,610 101 0

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 43

    Building Load Profiles

    Bldg.Hour

    FebruaryNet Load

    (None)Net Load

    (None)Net Load

    (None)Net Load

    (None)Net Load

    (None)Net Load

    1am 98,045 0 0 0 0 02am 96,184 0 0 0 0 03am 94,033 0 0 0 0 04am 92,961 0 0 0 0 05am 91,896 0 0 0 0 06am 98,798 0 0 0 0 07am 101,212 0 0 0 0 08am 104,809 0 0 0 0 09am 106,705 0 0 0 0 010am 111,924 0 0 0 0 011am 114,961 0 0 0 0 012pm 117,984 0 0 0 0 01pm 127,798 0 0 0 0 02pm 139,264 0 0 0 0 03pm 149,316 0 0 0 0 04pm 155,941 0 0 0 0 05pm 157,227 0 0 0 0 06pm 145,436 0 0 0 0 07pm 123,932 0 0 0 0 08pm 115,490 0 0 0 0 09pm 111,017 0 0 0 0 010pm 105,928 0 0 0 0 011pm 104,314 0 0 0 0 012am 99,924 0 0 0 0 0

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 44

    Air System #1 (Ue-01) Psychrometric Analysis (Z)

    System Load Analysis Latent Grains Sensible Temp CFMLeaving Coil Condition 63.206 55.000Draw-Thru Fan 402 0.218 22Misc Load on Supply Side 0 0.000 0 0.000 0Supply Air Duct 0 0.000 0Room Loads 1,320 1.156 30,992 16.782 1,660Sensible Reserve 0 0.000 0

    Room Condition 1,320 64.363 31,394 72.000 1,681Return Air Duct 0 0.000Return Air Plenum 0 0.000Misc Load on Return Side 0 0.000 0 0.000Vent Air 60 CFM 1,684 1.476 988 0.535Blow-Thru Fan 0 0.000

    Entering Coil Condition 3,004 65.838 32,383 72.535 1,681

    General Psychrometric Equations Used In Analysis:PR =(Barometric pressure of site / Standard ASHRAE pressure of 29.921)TSH = PR x 1.10 x CFM x (DB entering - DB leaving)TLH = PR x 0.68 x CFM x (Grains entering - Grains leaving)GTH = PR x 4.50 x CFM x (Enthalpy entering - Enthalpy leaving)

    TSH = 0.998 x 1.10 x 1,681 x ( 72.5 - 55.0 ) = 32,383 BtuhTLH = 0.998 x 0.68 x 1,681 x ( 65.8 - 63.2 ) = 3,004 Btuh

    ----------

    SUM = 35,387 BtuhGTH = 0.998 x 4.50 x 1,681 x ( 27.7 - 23.0 ) = 35,431 BtuhTotal System Load = 35,387 Btuh

    Chilled and Hot Water Flow Rates and Steam RequirementCooling GPM = 35,431 / ( 10.00 x 500 ) = 7.1 GPMHeating GPM = 0 / ( 20.00 x 500 ) = 0.0 GPMSteam Req. = 0 / 970 = 0.0 lb./hr

    Entering Cooling Coil Conditions Entering Heating Coil ConditionsDry bulb temperature: 72.54 Dry bulb temperature: 75.00Wet bulb temperature: 61.92Relative humidity: 55.22Enthalpy: 27.69 Btu/lbm

    Leaving Cooling Coil Conditions Leaving Heating Coil ConditionsDry bulb temperature: 55.00 Dry bulb temperature: 75.00Wet bulb temperature: 54.69Relative humidity: 98.09Enthalpy: 23.00 Btu/lbm

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 45

    Air System #2 (Ue-02) Psychrometric Analysis (Z)

    System Load Analysis Latent Grains Sensible Temp CFMLeaving Coil Condition 63.215 55.000Draw-Thru Fan 203 0.218 11Misc Load on Supply Side 0 0.000 0 0.000 0Supply Air Duct 0 0.000 0Room Loads 660 1.148 15,609 16.783 836Sensible Reserve 0 0.000 0

    Room Condition 660 64.363 15,812 72.000 847Return Air Duct 0 0.000Return Air Plenum 0 0.000Misc Load on Return Side 0 0.000 0 0.000Vent Air 30 CFM 842 1.465 494 0.531Blow-Thru Fan 0 0.000

    Entering Coil Condition 1,502 65.828 16,306 72.531 847

    General Psychrometric Equations Used In Analysis:PR =(Barometric pressure of site / Standard ASHRAE pressure of 29.921)TSH = PR x 1.10 x CFM x (DB entering - DB leaving)TLH = PR x 0.68 x CFM x (Grains entering - Grains leaving)GTH = PR x 4.50 x CFM x (Enthalpy entering - Enthalpy leaving)

    TSH = 0.998 x 1.10 x 847 x ( 72.5 - 55.0 ) = 16,305 BtuhTLH = 0.998 x 0.68 x 847 x ( 65.8 - 63.2 ) = 1,502 Btuh

    ----------

    SUM = 17,808 BtuhGTH = 0.998 x 4.50 x 847 x ( 27.7 - 23.0 ) = 17,829 BtuhTotal System Load = 17,808 Btuh

    Chilled and Hot Water Flow Rates and Steam RequirementCooling GPM = 17,829 / ( 10.00 x 500 ) = 3.6 GPMHeating GPM = 0 / ( 20.00 x 500 ) = 0.0 GPMSteam Req. = 0 / 970 = 0.0 lb./hr

    Entering Cooling Coil Conditions Entering Heating Coil ConditionsDry bulb temperature: 72.53 Dry bulb temperature: 75.00Wet bulb temperature: 61.91Relative humidity: 55.21Enthalpy: 27.69 Btu/lbm

    Leaving Cooling Coil Conditions Leaving Heating Coil ConditionsDry bulb temperature: 55.00 Dry bulb temperature: 75.00Wet bulb temperature: 54.69Relative humidity: 98.09Enthalpy: 23.00 Btu/lbm

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 46

    Air System #3 (Fc-01) Psychrometric Analysis (Z)

    System Load Analysis Latent Grains Sensible Temp CFMLeaving Coil Condition 61.316 55.000Draw-Thru Fan 103 0.218 5Misc Load on Supply Side 0 0.000 0 0.000 0Supply Air Duct 0 0.000 0Room Loads 880 3.024 7,900 16.783 423Sensible Reserve 0 0.000 0

    Room Condition 880 64.340 8,003 72.000 429Return Air Duct 0 0.000Return Air Plenum 0 0.000Misc Load on Return Side 0 0.000 0 0.000Vent Air 60 CFM 1,775 6.105 659 1.400Blow-Thru Fan 0 0.000

    Entering Coil Condition 2,655 70.445 8,662 73.400 429

    General Psychrometric Equations Used In Analysis:PR =(Barometric pressure of site / Standard ASHRAE pressure of 29.921)TSH = PR x 1.10 x CFM x (DB entering - DB leaving)TLH = PR x 0.68 x CFM x (Grains entering - Grains leaving)GTH = PR x 4.50 x CFM x (Enthalpy entering - Enthalpy leaving)

    TSH = 0.998 x 1.10 x 429 x ( 73.4 - 55.0 ) = 8,661 BtuhTLH = 0.998 x 0.68 x 429 x ( 70.4 - 61.3 ) = 2,656 Btuh

    ----------

    SUM = 11,318 BtuhGTH = 0.998 x 4.50 x 429 x ( 28.6 - 22.7 ) = 11,388 BtuhTotal System Load = 11,316 Btuh

    Chilled and Hot Water Flow Rates and Steam RequirementCooling GPM = 11,388 / ( 10.00 x 500 ) = 2.3 GPMHeating GPM = 0 / ( 20.00 x 500 ) = 0.0 GPMSteam Req. = 0 / 970 = 0.0 lb./hr

    Entering Cooling Coil Conditions Entering Heating Coil ConditionsDry bulb temperature: 73.40 Dry bulb temperature: 75.00Wet bulb temperature: 63.21Relative humidity: 57.32Enthalpy: 28.62 Btu/lbm

    Leaving Cooling Coil Conditions Leaving Heating Coil ConditionsDry bulb temperature: 55.00 Dry bulb temperature: 75.00Wet bulb temperature: 54.21Relative humidity: 95.21Enthalpy: 22.71 Btu/lbm

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 47

    Air System #4 (Fc-02) Psychrometric Analysis (Z)

    System Load Analysis Latent Grains Sensible Temp CFMLeaving Coil Condition 58.208 55.000Draw-Thru Fan 89 0.218 5Misc Load on Supply Side 0 0.000 0 0.000 0Supply Air Duct 0 0.000 0Room Loads 1,540 6.092 6,863 16.783 368Sensible Reserve 0 0.000 0

    Room Condition 1,540 64.300 6,953 72.000 372Return Air Duct 0 0.000Return Air Plenum 0 0.000Misc Load on Return Side 0 0.000 0 0.000Vent Air 70 CFM 1,965 7.785 1,153 2.820Blow-Thru Fan 0 0.000

    Entering Coil Condition 3,505 72.085 8,106 74.820 372

    General Psychrometric Equations Used In Analysis:PR =(Barometric pressure of site / Standard ASHRAE pressure of 29.921)TSH = PR x 1.10 x CFM x (DB entering - DB leaving)TLH = PR x 0.68 x CFM x (Grains entering - Grains leaving)GTH = PR x 4.50 x CFM x (Enthalpy entering - Enthalpy leaving)

    TSH = 0.998 x 1.10 x 372 x ( 74.8 - 55.0 ) = 8,106 BtuhTLH = 0.998 x 0.68 x 372 x ( 72.1 - 58.2 ) = 3,508 Btuh

    ----------

    SUM = 11,614 BtuhGTH = 0.998 x 4.50 x 372 x ( 29.2 - 22.2 ) = 11,710 BtuhTotal System Load = 11,420 Btuh

    Chilled and Hot Water Flow Rates and Steam RequirementCooling GPM = 11,710 / ( 10.00 x 500 ) = 2.3 GPMHeating GPM = 0 / ( 20.00 x 500 ) = 0.0 GPMSteam Req. = 0 / 970 = 0.0 lb./hr

    Entering Cooling Coil Conditions Entering Heating Coil ConditionsDry bulb temperature: 74.82 Dry bulb temperature: 75.00Wet bulb temperature: 64.04Relative humidity: 55.92Enthalpy: 29.23 Btu/lbm

    Leaving Cooling Coil Conditions Leaving Heating Coil ConditionsDry bulb temperature: 55.00 Dry bulb temperature: 75.00Wet bulb temperature: 53.41Relative humidity: 90.45Enthalpy: 22.23 Btu/lbm

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 48

    Air System #5 (Ue-05) Psychrometric Analysis (Z)

    System Load Analysis Latent Grains Sensible Temp CFMLeaving Coil Condition 59.947 55.000Draw-Thru Fan 354 0.218 19Misc Load on Supply Side 0 0.000 0 0.000 0Supply Air Duct 0 0.000 0Room Loads 4,400 4.375 27,306 16.782 1,462Sensible Reserve 0 0.000 0

    Room Condition 4,400 64.322 27,660 72.000 1,481Return Air Duct 0 0.000Return Air Plenum 0 0.000Misc Load on Return Side 0 0.000 0 0.000Vent Air 200 CFM 5,613 5.588 3,295 2.025Blow-Thru Fan 0 0.000

    Entering Coil Condition 10,013 69.910 30,955 74.025 1,481

    General Psychrometric Equations Used In Analysis:PR =(Barometric pressure of site / Standard ASHRAE pressure of 29.921)TSH = PR x 1.10 x CFM x (DB entering - DB leaving)TLH = PR x 0.68 x CFM x (Grains entering - Grains leaving)GTH = PR x 4.50 x CFM x (Enthalpy entering - Enthalpy leaving)

    TSH = 0.998 x 1.10 x 1,481 x ( 74.0 - 55.0 ) = 30,955 BtuhTLH = 0.998 x 0.68 x 1,481 x ( 69.9 - 59.9 ) = 10,020 Btuh

    ----------

    SUM = 40,976 BtuhGTH = 0.998 x 4.50 x 1,481 x ( 28.7 - 22.5 ) = 41,238 BtuhTotal System Load = 40,968 Btuh

    Chilled and Hot Water Flow Rates and Steam RequirementCooling GPM = 41,238 / ( 10.00 x 500 ) = 8.2 GPMHeating GPM = 0 / ( 20.00 x 500 ) = 0.0 GPMSteam Req. = 0 / 970 = 0.0 lb./hr

    Entering Cooling Coil Conditions Entering Heating Coil ConditionsDry bulb temperature: 74.03 Dry bulb temperature: 75.00Wet bulb temperature: 63.31Relative humidity: 55.71Enthalpy: 28.69 Btu/lbm

    Leaving Cooling Coil Conditions Leaving Heating Coil ConditionsDry bulb temperature: 55.00 Dry bulb temperature: 75.00Wet bulb temperature: 53.86Relative humidity: 93.10Enthalpy: 22.50 Btu/lbm

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 49

    Air System #6 (Ue-03) Psychrometric Analysis (Z)

    System Load Analysis Latent Grains Sensible Temp CFMLeaving Coil Condition 61.745 55.000Draw-Thru Fan 298 0.218 16Misc Load on Supply Side 0 0.000 0 0.000 0Supply Air Duct 0 0.000 0Room Loads 2,200 2.600 22,975 16.783 1,230Sensible Reserve 0 0.000 0

    Room Condition 2,200 64.345 23,273 72.000 1,246Return Air Duct 0 0.000Return Air Plenum 0 0.000Misc Load on Return Side 0 0.000 0 0.000Vent Air 100 CFM 2,806 3.188 1,757 1.284Blow-Thru Fan 0 0.000

    Entering Coil Condition 5,006 67.533 25,030 73.284 1,246

    General Psychrometric Equations Used In Analysis:PR =(Barometric pressure of site / Standard ASHRAE pressure of 29.921)TSH = PR x 1.10 x CFM x (DB entering - DB leaving)TLH = PR x 0.68 x CFM x (Grains entering - Grains leaving)GTH = PR x 4.50 x CFM x (Enthalpy entering - Enthalpy leaving)

    TSH = 0.998 x 1.10 x 1,246 x ( 73.3 - 55.0 ) = 25,030 BtuhTLH = 0.998 x 0.68 x 1,246 x ( 67.5 - 61.7 ) = 4,898 Btuh

    ----------

    SUM = 29,928 BtuhGTH = 0.998 x 4.50 x 1,246 x ( 28.1 - 22.8 ) = 30,040 BtuhTotal System Load = 30,037 Btuh

    Chilled and Hot Water Flow Rates and Steam RequirementCooling GPM = 30,040 / ( 10.00 x 500 ) = 6.0 GPMHeating GPM = 0 / ( 20.00 x 500 ) = 0.0 GPMSteam Req. = 0 / 970 = 0.0 lb./hr

    Entering Cooling Coil Conditions Entering Heating Coil ConditionsDry bulb temperature: 73.28 Dry bulb temperature: 75.00Wet bulb temperature: 62.55Relative humidity: 55.20Enthalpy: 28.14 Btu/lbm

    Leaving Cooling Coil Conditions Leaving Heating Coil ConditionsDry bulb temperature: 55.00 Dry bulb temperature: 75.00Wet bulb temperature: 54.31Relative humidity: 95.84Enthalpy: 22.78 Btu/lbm

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 50

    Air System #7 (Ue-04) Psychrometric Analysis (Z)

    System Load Analysis Latent Grains Sensible Temp CFMLeaving Coil Condition 50.720 55.000Draw-Thru Fan 198 0.218 14Misc Load on Supply Side 0 0.000 0 0.000 0Supply Air Duct 0 0.000 0Room Loads 101 0.180 11,610 12.783 813Sensible Reserve 0 0.000 0

    Room Condition 101 50.901 11,808 68.000 827Return Air Duct 0 0.000Return Air Plenum 0 0.000Misc Load on Return Side 0 0.000 0 0.000Vent Air 5 CFM 178 0.317 71 0.078Blow-Thru Fan 0 0.000

    Entering Coil Condition 279 51.218 11,878 68.078 827

    General Psychrometric Equations Used In Analysis:PR =(Barometric pressure of site / Standard ASHRAE pressure of 29.921)TSH = PR x 1.10 x CFM x (DB entering - DB leaving)TLH = PR x 0.68 x CFM x (Grains entering - Grains leaving)GTH = PR x 4.50 x CFM x (Enthalpy entering - Enthalpy leaving)

    TSH = 0.998 x 1.10 x 827 x ( 68.1 - 55.0 ) = 11,878 BtuhTLH = 0.998 x 0.68 x 827 x ( 51.2 - 50.7 ) = 279 Btuh

    ----------

    SUM = 12,157 BtuhGTH = 0.998 x 4.50 x 827 x ( 24.3 - 21.1 ) = 12,106 BtuhTotal System Load = 12,158 Btuh

    Chilled and Hot Water Flow Rates and Steam RequirementCooling GPM = 12,106 / ( 10.00 x 500 ) = 2.4 GPMHeating GPM = 0 / ( 20.00 x 500 ) = 0.0 GPMSteam Req. = 0 / 970 = 0.0 lb./hr

    Entering Cooling Coil Conditions Entering Heating Coil ConditionsDry bulb temperature: 68.08 Dry bulb temperature: 75.00Wet bulb temperature: 56.90Relative humidity: 50.17Enthalpy: 24.32 Btu/lbm

    Leaving Cooling Coil Conditions Leaving Heating Coil ConditionsDry bulb temperature: 55.00 Dry bulb temperature: 75.00Wet bulb temperature: 51.43Relative humidity: 78.95Enthalpy: 21.07 Btu/lbm

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 51

    Air Handler #1 - Ue-01 - Pie Charts (Z)Air Handler #1 peaks in February at 5pm.

    Air Handler#1

    Net Gain35,387Btuh

    Roof - 2.40%Wall - 2.19%

    Glass - 72.91%

    Lighting - 2.27%Equipment - 1.02%

    People - 8.39%

    Partition - 2.14%Cool. Vent. - 7.55%

    Draw-Thru Fan - 1.14%

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 52

    Air Handler #2 - Ue-02 - Pie Charts (Z)Air Handler #2 peaks in February at 5pm.

    Air Handler#2

    Net Gain17,808Btuh

    Roof - 2.38%

    Glass - 72.44%

    Lighting - 2.26%Equipment - 1.33%

    People - 8.34%

    Partition - 4.61%

    Cool. Vent. - 7.50%Draw-Thru Fan - 1.14%

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 53

    Air Handler #3 - Fc-01 - Pie Charts (Z)Air Handler #3 peaks in February at 8pm.

    Air Handler#3

    Net Gain11,316Btuh

    Roof - 6.93%

    Wall - 21.82%

    Lighting - 5.64%

    Equipment - 19.90%

    People - 17.50%

    Partition - 5.81%

    Cool. Vent. - 21.51%

    Draw-Thru Fan - 0.91%

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 54

    Air Handler #4 - Fc-02 - Pie Charts (Z)Air Handler #4 peaks in February at 5pm.

    Air Handler#4

    Net Gain11,420Btuh

    Roof - 8.19%Wall - 3.77%

    Lighting - 7.77%

    Equipment - 6.31%

    People - 30.34%

    Partition - 15.54%

    Cool. Vent. - 27.30%

    Draw-Thru Fan - 0.78%

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 55

    Air Handler #5 - Ue-05 - Pie Charts (Z)Air Handler #5 peaks in February at 5pm.

    Air Handler#5

    Net Gain40,968Btuh

    Roof - 6.37%Wall - 3.51%

    Glass - 17.39%

    Lighting - 6.04%

    Equipment - 3.55%

    People - 24.17%

    Partition - 16.36%

    Cool. Vent. - 21.74%

    Draw-Thru Fan - 0.86%

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 56

    Air Handler #6 - Ue-03 - Pie Charts (Z)Air Handler #6 peaks in February at 2pm.

    Air Handler#6

    Net Gain30,037Btuh

    Roof - 1.50%Wall - 5.82%

    Glass - 23.56%

    Lighting - 2.51%

    Equipment - 31.24%

    People - 16.48%

    Partition - 2.71%

    Cool. Vent. - 15.19%Draw-Thru Fan - 0.99%

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.

  • Chvac - Full Commercial HVAC Loads Calculation Program Elite Software Development, Inc.VMH Ingenieros SAC Interbank-El EjercitoLima, Peru, LIM-01 Page 57

    Air Handler #7 - Ue-04 - Pie Charts (Z)Air Handler #7 peaks in February at 8pm.

    Air Handler#7

    Net Gain12,158Btuh

    Roof - 3.18%

    Wall - 22.05%

    Lighting - 2.41%

    Equipment - 61.74%

    People - 1.87%Partition - 5.06%

    Cool. Vent. - 2.05%Draw-Thru Fan - 1.63%

    Z:\ ...\CALCULOS DE ... EJERCITO.CH8 lunes, 15 de julio de 2013, 05:47 p.m.