17.rampa y otros

36
"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR" HOJA DE METRADOS CONSTRUCCION MODULO RAMPAS Y OTROS ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL 17.0 MODULO DE RAMPA Y OTROS 17.01 ESTRUCTURAS 17.01.01 TRABAJOS PRELIMINARES 17.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 LIMPIEZA PARA MODULO DE RAMPA 1.00 1.00 ### 1.00 160.80 17.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 LIMPIEZA PARA MODULO DE RAMPAS 1.00 1.00 ### 1.00 160.80 17.01.02 MOVIMIENTO DE TIERRAS 17.01.02.01 NIVELACION DEL TERRENO m2 Corte de area 1.00 1.00 ### 1.00 160.80 17.01.02.02 EXCAVACION DE ZANJAS Y ZAPATAS m3 Rampa 1.00 39.60 0.10 3.96 Eje B´, D´,E´,F´,G´ 5.00 1.00 1.50 0.80 1.20 7.20 eje 20,21 9.00 1.00 4.00 0.80 1.20 34.56 eje 15, A´ 3.00 1.00 4.20 0.80 1.20 12.10 . Zapata Z1 3.00 1.00 1.50 1.50 1.70 11.48 Zapata Z3 7.00 1.00 1.80 1.80 1.70 38.56 Zapata Z8 1.00 1.00 1.80 1.80 1.70 5.51 Zapata Z10 2.00 1.00 1.90 1.50 1.70 9.69 17.01.02.03 NIVELACION Y COMPACTACION CON PLANCHA COMPACT. DEL SUD-BAS m2 Rampa 1.00 39.60 39.60 Eje B´, D´,E´,F´,G´ 5.00 1.00 1.50 0.80 6.00 eje 20,21 9.00 1.00 4.00 0.80 28.80 eje 15, A´ 3.00 1.00 4.20 0.80 10.08 . Zapata Z1 3.00 1.00 1.50 1.50 6.75 Zapata Z3 7.00 1.00 1.80 1.80 22.68 Zapata Z8 1.00 1.00 1.80 1.80 3.24 Zapata Z10 2.00 1.00 1.90 1.50 5.70 17.01.02.04 AFIRMADO CON MATERIAL DE PRESTAMO 4" EN CIMENTACION Y RAMPA m2 Bajo el cimiento y zapatas 1.00 1.00 16.70 9.00 150.30 17.01.02.05 AFIRMADO DE 4" PARA PASADIZO, COMPACTADO m2 Pasadizo 1.00 1.00 ### 108.20 17.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE m3 1.00 1.00 16.70 9.00 165.33 17.01.03 CONCRETO SIMPLE 17.01.03.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% P.G. m3 Eje B´, D´,E´,F´,G´ 5.00 1.00 1.50 0.60 0.50 2.25 eje 20,21 9.00 1.00 4.00 0.60 0.50 10.80 eje 15, A´ 3.00 1.00 4.20 0.60 0.50 3.78 17.01.03.02 SOBRECIMIENTO CONCRETO 1:8 + 25% P.M. m3 Eje B´, D´,E´,F´,G´ 5.00 1.00 1.50 0.25 0.50 0.94 eje 20,21 9.00 1.00 4.00 0.25 0.50 4.50 eje 15, A´ 3.00 1.00 4.20 0.25 0.50 1.58 17.01.03.03 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS m2 Eje B´, D´,E´,F´,G´ 5.00 2.00 1.50 0.50 7.50 eje 20,21 9.00 2.00 4.00 0.50 36.00 eje 15, A´ 3.00 2.00 4.20 0.50 12.60 Eje B´, D´,E´,F´,G´ 5.00 2.00 1.50 0.25 3.75 eje 20,21 9.00 2.00 4.00 0.25 18.00 eje 15, A´ 3.00 2.00 4.20 0.25 6.30 17.01.03.04 FALSO PISO MEZCLA 1:8 e=4" m2 Pasadizo 1.00 108.20 108.20 OBRA : "CONSTRUCCION DEL COELGIO PRIVADO CRISTIANO EL BUEN PASTOR" PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR UBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO

Upload: berly-tovar-vergara

Post on 23-Dec-2015

2 views

Category:

Documents


0 download

DESCRIPTION

METRADO RAMPAS

TRANSCRIPT

Page 1: 17.Rampa y Otros

"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR"

HOJA DE METRADOS CONSTRUCCION MODULO RAMPAS Y OTROS

ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL TOTAL

17.0 MODULO DE RAMPA Y OTROS17.01 ESTRUCTURAS

17.01.01 TRABAJOS PRELIMINARES17.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 160.80

LIMPIEZA PARA MODULO DE RAMPA 1.00 1.00 160.80 1.00 160.80

17.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 160.80LIMPIEZA PARA MODULO DE RAMPAS 1.00 1.00 160.80 1.00 160.80

17.01.02 MOVIMIENTO DE TIERRAS17.01.02.01 NIVELACION DEL TERRENO m2 160.80

Corte de area 1.00 1.00 160.80 1.00 160.80

17.01.02.02 EXCAVACION DE ZANJAS Y ZAPATAS m3 123.05Rampa 1.00 39.60 0.10 3.96

Eje B´, D´,E´,F´,G´ 5.00 1.00 1.50 0.80 1.20 7.20eje 20,21 9.00 1.00 4.00 0.80 1.20 34.56eje 15, A´ 3.00 1.00 4.20 0.80 1.20 12.10

.Zapata Z1 3.00 1.00 1.50 1.50 1.70 11.48Zapata Z3 7.00 1.00 1.80 1.80 1.70 38.56Zapata Z8 1.00 1.00 1.80 1.80 1.70 5.51Zapata Z10 2.00 1.00 1.90 1.50 1.70 9.69

17.01.02.03 NIVELACION Y COMPACTACION CON PLANCHA COMPACT. DEL SUD-BASE m2 122.85Rampa 1.00 39.60 39.60

Eje B´, D´,E´,F´,G´ 5.00 1.00 1.50 0.80 6.00eje 20,21 9.00 1.00 4.00 0.80 28.80eje 15, A´ 3.00 1.00 4.20 0.80 10.08

.Zapata Z1 3.00 1.00 1.50 1.50 6.75Zapata Z3 7.00 1.00 1.80 1.80 22.68Zapata Z8 1.00 1.00 1.80 1.80 3.24Zapata Z10 2.00 1.00 1.90 1.50 5.70

17.01.02.04 AFIRMADO CON MATERIAL DE PRESTAMO 4" EN CIMENTACION Y RAMPA m2 150.30

Bajo el cimiento y zapatas 1.00 1.00 16.70 9.00 150.30

17.01.02.05 AFIRMADO DE 4" PARA PASADIZO, COMPACTADO m2

Pasadizo 1.00 1.00 108.20 108.20 108.20

17.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE m31.00 1.00 16.70 9.00 165.33 165.33

17.01.03 CONCRETO SIMPLE17.01.03.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% P.G. m3 16.83

Eje B´, D´,E´,F´,G´ 5.00 1.00 1.50 0.60 0.50 2.25eje 20,21 9.00 1.00 4.00 0.60 0.50 10.80eje 15, A´ 3.00 1.00 4.20 0.60 0.50 3.78

17.01.03.02 SOBRECIMIENTO CONCRETO 1:8 + 25% P.M. m3 7.01Eje B´, D´,E´,F´,G´ 5.00 1.00 1.50 0.25 0.50 0.94eje 20,21 9.00 1.00 4.00 0.25 0.50 4.50eje 15, A´ 3.00 1.00 4.20 0.25 0.50 1.58

17.01.03.03 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS m2 84.15Eje B´, D´,E´,F´,G´ 5.00 2.00 1.50 0.50 7.50eje 20,21 9.00 2.00 4.00 0.50 36.00eje 15, A´ 3.00 2.00 4.20 0.50 12.60

Eje B´, D´,E´,F´,G´ 5.00 2.00 1.50 0.25 3.75eje 20,21 9.00 2.00 4.00 0.25 18.00eje 15, A´ 3.00 2.00 4.20 0.25 6.30

17.01.03.04 FALSO PISO MEZCLA 1:8 e=4" m2 108.20Pasadizo 1.00 108.20 108.20

OBRA : "CONSTRUCCION DEL COELGIO PRIVADO CRISTIANO EL BUEN PASTOR"PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTORUBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO

Page 2: 17.Rampa y Otros

"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR"

ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL TOTAL

PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTORUBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO

17.01.03.05 SOLADO PARA ZAPATAS DE 4" MEZCLA 1:12 CEMENTO-HORMIGON m2 38.37Zapata Z1 3.00 1.00 1.50 1.50 6.75Zapata Z3 7.00 1.00 1.80 1.80 22.68Zapata Z8 1.00 1.00 1.80 1.80 3.24Zapata Z10 2.00 1.00 1.90 1.50 5.70

17.01.03.06 RAMPA DE MEZCLA 1.8 CEMENTO - HORMIGON m3 9.80

Rampa 1.00 9.80 1.00 9.80

17.01.04 OBRAS DE CONCRETO ARMADO17.01.04.01 ZAPATAS CONCRETO F`C=210 kg/cm2 m3 19.19

Zapata Z1 3.00 1.00 1.50 1.50 0.50 3.38Zapata Z3 7.00 1.00 1.80 1.80 0.50 11.34Zapata Z8 1.00 1.00 1.80 1.80 0.50 1.62Zapata Z10 2.00 1.00 1.90 1.50 0.50 2.85

17.01.04.02 ZAPATAS, ACERO FY=4200KG/CM2 kg 546.76

17.01.04.03 VIGAS DE CIMENTACION CONCRETO F`C=210 kg/cm2 m3 20.20Eje B´, D´,E´,F´,G´ 5.00 2.00 1.50 0.30 0.60 2.70eje 20,21 9.00 2.00 4.00 0.30 0.60 12.96eje 15, A´ 3.00 2.00 4.20 0.30 0.60 4.54

17.01.04.04 VIGAS DE CIMENTACION, ENCOFRADO Y DESENCOFRADO m2 100.98Eje B´, D´,E´,F´,G´ 5.00 2.00 1.50 0.60 9.00eje 20,21 9.00 2.00 4.00 0.60 43.20eje 15, A´ 3.00 2.00 4.20 0.60 15.12

Eje B´, D´,E´,F´,G´ 5.00 2.00 1.50 0.30 4.50eje 20,21 9.00 2.00 4.00 0.30 21.60eje 15, A´ 3.00 2.00 4.20 0.30 7.56

17.01.04.05 VIGAS DE CIMENTACION, ACERO FY=4200KG/CM2 kg 2,887.31

17.01.04.06 COLUMNAS, CONCRETO 210 kg/cm2 m3 5.38Columna C1 1.00 7.00 0.45 0.30 3.00 2.84Columna C5 1.00 3.00 0.13 3.00 1.17Columna C7 1.00 2.00 0.38 0.30 3.00 0.68Columna C8 1.00 0.23 3.00 0.69

17.01.04.06 COLUMNAS, ENCOFRADO Y DESENCOFRADO m2 48.36Columna C1 2.00 7.00 0.45 3.00 18.90Columna C5 2.00 3.00 0.13 3.00 2.34Columna C7 2.00 2.00 0.38 3.00 4.56Columna C8 2.00 0.23 3.00 1.38

Columna C1 2.00 7.00 0.30 3.00 18.90Columna C7 2.00 2.00 0.30 3.00 2.28

17.01.04.07 COLUMNAS, ACERO FY=4200KG/CM2 kg 4,227.81

17.01.04.08 VIGAS, CONCRETO 210 kg/cm2 (VIGUETAS AMARRE) m3 4.94Viga de amarre Eje E´ lateral 1.00 78.00 0.10 4.22 0.15 4.94

17.01.04.09 VIGAS, CONCRETO 210 kg/cm2, m3 16.74V-1 (0.30X0.60) 1.00 14.00 0.30 5.50 0.60 13.86V-2 (0.30X0.40) 1.00 5.00 0.30 4.80 0.40 2.88

17.01.04.10 VIGAS, ENCOFRADO DESENCOFRADO m2 172.20V-1 (0.30X0.60) 2.00 14.00 5.50 0.60 92.40V-2 (0.30X0.40) 2.00 5.00 4.80 0.40 19.20

V-1 (0.30X0.60) 2.00 14.00 0.30 5.50 46.20V-2 (0.30X0.40) 2.00 5.00 0.30 4.80 14.40

17.01.04.11 VIGAS, ACERO FY=4200KG/CM2 kg 1,157.07

17.01.04.12 LOSA ALIGERADA, CONCRETO 210 kg/cm2 m2 108.20Paños pasadizo 1.00 108.20 108.20

17.01.05 MUROS Y TABIQUES DE ALBAÑILERIA17.01.05.01 MURO DE LADRILLO KK TIPO IV CABEZA M:1:1:4 m2 169.18

Eje 21 1.00 1.00 29.40 2.80 82.32

Page 3: 17.Rampa y Otros

"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR"

ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL TOTAL

PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTORUBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO

Eje A,D,E 1.00 3.00 10.34 2.80 86.86

17.02 ARQUITECTURA17.02.01 ENCHAPADO DE LA RAMPA

17.02.01.01 PUEDRA LAJA ESTUCUTRADO m2 34.50Rampa 1.00 34.50 34.50

17.02.02 REVOQUES ENLUCIDOS Y MOLDURAS17.02.02.01 TARRAJEO EN MURO: INTERIOR m2 162.96

Eje 21 1.00 1.00 34.80 2.8 97.44

Eje 20 1.00 2.00 11.70 2.8 65.52

17.02.02.02 TARRAJEO DE COLUMNAS m2 5.88

Columna EjeA´,B´,C´, D´E,F´,G´ elevacion y frontal 1.00 14.00 0.15 2.80 5.88

17.02.02.03 TARRAJEO DE VIGAS m2 6.32

V-2 (0.30X0.40) 2.00 1.00 4.80 0.20 1.92

V-1 (0.30X0.60) 2.00 1.00 5.50 0.40 4.40

17.02.03 CIELO RASOS17.02.03.01 CIELO RASO CON MEZCLA C:A 1:5 m2 670.84

Paños horizontales 1.00 1.00 108.20 6.20 670.84

17.02.04 PINTURA17.02.04.01 PINTURA LATEX 2 MANOS EN CIELO RASO m2 162.96

Eje 21 1.00 1.00 34.80 2.8 97.44

Eje 20 1.00 2.00 11.70 2.8 65.52

17.02.04.02 PINTURA OLEO 2 MANOS EN MUROS, VIGAS Y COLUMNAS m2

MUROS 142.40

Eje 21 1.00 1.00 34.80 2.8 97.44

Eje 20 1.00 1.00 11.70 2.8 32.76

COLUMNASColumna EjeA´,B´,C´, D´E,F´,G´ elevacion y frontal 1.00 14.00 0.15 2.80 5.88

VIGASV-2 (0.30X0.40) 2.00 1.00 4.80 0.20 1.92

V-1 (0.30X0.60) 2.00 1.00 5.50 0.40 4.40

17.02.04.03 PINTURA ESMALTE 2 MANOS EN CONTRAZOCALO DE CEMENTO H=20CM m 46.50

Eje 21 1.00 1.00 34.80 34.80

Eje 20 1.00 1.00 11.70 11.70

17.02.04.04 JUNTA DE DILATACION RELLENO CON MORTERO ASFALTICO E=1/2" m 168.20

Veredas laterales 1.00 1.00 168.20 168.20

Page 4: 17.Rampa y Otros

"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR"

ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL TOTAL

PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTORUBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO

Page 5: 17.Rampa y Otros

"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR"

ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL TOTAL

PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTORUBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO

Page 6: 17.Rampa y Otros

"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR"

ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL TOTAL

PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTORUBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO

Page 7: 17.Rampa y Otros

"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR"

ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL TOTAL

PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTORUBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO

Page 8: 17.Rampa y Otros

"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR"

ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL TOTAL

PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTORUBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO

Page 9: 17.Rampa y Otros

"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR"

ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL TOTAL

PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTORUBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO

Page 10: 17.Rampa y Otros

"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR"

ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL TOTAL

PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTORUBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO

Page 11: 17.Rampa y Otros

"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR"

ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL TOTAL

PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTORUBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO

Page 12: 17.Rampa y Otros

"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR"

ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL TOTAL

PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTORUBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO

Page 13: 17.Rampa y Otros

"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR"

ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL TOTAL

PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTORUBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO

Page 14: 17.Rampa y Otros

"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR"

ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL TOTAL

PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTORUBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO

Page 15: 17.Rampa y Otros

"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR"

ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL TOTAL

PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTORUBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO

Page 16: 17.Rampa y Otros

"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR"

ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL TOTAL

PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTORUBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO

Page 17: 17.Rampa y Otros

"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR"

ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL TOTAL

PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTORUBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO

Page 18: 17.Rampa y Otros

"CONSTRUCCION DEL COLEGIO PRIVADO CRISTIANO EL BUEN PASTOR"

ITEM DESCRIPCION UND # VECES CANT ANCHO LARGO ALTO PARCIAL TOTAL

PROPIETARIO : COLEGIO PRIVADO CRISTIANO EL BUEN PASTORUBICACIÓN : BARRIO DE SANTA ANA - AYACUCHO - HUAMANGA - AYACUCHO