1 examen de recup
DESCRIPTION
recuperacion de metradosTRANSCRIPT
1.00 ACERO EN VIGA
1.01 ESTRIBOS
Nº DESCRIPCION DIAM. Nº DEPIEZA
S
PARCIALml
PARCIALKg
OBSERVACION
1.01.01 ESTRIBOS 3/8”
TRAMO A:
1.90 16 30.40 17.33 0.57 Kg/m
TRAMO A´
1.90 15 28.50 16.25 0.57 Kg/m
TRAMO B´:
1.90 32 60.80 34.66 0.57 Kg/m
TRAMO B:
1.90 35 66.50 37.91 0.57 Kg/m
PARCIAL 106.15 kg.
TOTAL = 106.15 kg. de 3/8”
1.01.02 ACERO LONGITUDINAL
NºDESCRIPCION
DIAM.
Nº DE VECE
S
Nº DEPIEZA
S
1” 3/4” 5/8” PARCIAL
PARCIAL
4.03.04 ML Kg.
TRAMO A - B3.4 1” 1 5 3.4 17
3.4
3/4” 2 5 3.4 34
6.2751" 2 5
6.275
62.75
8.9753/4" 2 5
8.975
89.75
8.8 5/8” 3 5 8.8 132
TRAMO B - B´8.0 1” 2 5 8.0 80.0
3.5 1” 1 5 3.5 17.5
3.5 3/4" 2 5 3.5 35.0
7.8 3/4" 2 5 7.8 78.0
TRAMO B´ - A´3.25 1” 1 5 3.25 16.25
3.25 3/4” 2 5 3.25 32.50
6.2251” 2 5
6.225
62.25
7.9253/4” 1 5
7.925
39.625
7.925 5/8” 1 5 7.925 39.625
1” = 255.75 * 3.97 kg/m = 1015.33 kg.
3/4” = 308.875 * 2.24 kg/m = 691.88 kg.
5/8" = 171.625 * 1.55 kg/m = 266.01875 kg.
Consideramos el 5% de desperdicios
TOTAL :1” = 1015.33 * 0.05 = 50.766 kg.
3/4” = 691.88 * 0.05 = 34.594 kg.
5/8" = 266.019 * 0.05 = 13.301 kg.
3/8" = 106.15 * 0.05 = 111.458 kg.
2.00. CONCRETO
Volumen de concreto de viga llena = 17.95 * 0.60 * 0.30
Volumen = 3.231 m3.
Consideramos 5% de desperdicios = 3.231 * 0.05 = 3.393 m3.
3.00 ENCOFRADO Y DESENCOFRADO
((0.60-0.025) * 17.95 )* 2 + (2+6.6+5.6+1.95) * 0.3 + (0.6 * 0.3) * 2 = 17.77 m2.
1 m2 10.69 p2
17.77 m2 X
X = 191.365 p2
Consideramos 5 % de desperdicios = 191.365 * 0.05 = 200.933 p2