upgrading the angermünde–szczecin route...in szczecin, the route is the only trimodal ten-v core...

1
Publisher DB Netz AG Elisabeth-Schwarzhaupt-Platz 1 10155 Berlin Photos: Front cover: IVD Ingenieur- und Vermessungsbüro Dimitrov Page 5: Fotolia Maps: designhaus berlin Subject to change No responsibility accepted for the correctness of the information As of November 2018 Print management: DB Kommunikationstechnik GmbH Karlsruhe, www.dbkt.de Connecting Europe – upgrading the Angermünde–Szczecin route A fast, efficient and sustainable route between Berlin and Szczecin would be extremely valuable for Europe. Schwedt/Oder Raffinerie Gartz Tantow Gumience Grenze D/PL Petershagen Casekow Schönow A 11 A 20 B 166 B 2 B 198 B 2 Flugplatz Crussow Angermünde Passow 31 Szczecin 1st construction phase 2nd construction phase What does the upgrade of the Angermünde–Szczecin route mean for Europe? Sustained improvement in transport links between Scandinavia, Central and Western Europe as well as between Germany and Poland Improved links between the TEN-V core network corridors Scandinavia-Mediterranean North Sea-Baltic Sea Baltic Sea-Adriatic Orient-Eastern Mediterranean Improved hinterland connection to Poland's Baltic Sea ports Improved cross-border rail traffic: development impetus along the route, as well as in the metropolitan areas of Szczecin and Berlin-Brandenburg Future sustainability of the rail connection between Szczecin and Berlin In conjunction with the A11/E28 motorway and Oder-Havel Canal in Szczecin, the route is the only trimodal TEN-V core network axis between Poland and Germany. Route upgrade Angermünde–D/PL border, 49 kilometres Angermünde Berlin Szczecin Berlin–Szczecin twin-track improvement of European rail traffic Orient-Eastern Mediterranean Scandinavia-Mediterranean North Sea–Baltic Sea Baltic Sea-Adriatic TEN-V network corridors What to expect: project milestones 1st section (Angermünde-Passow) Construction legislation (planning approval): expected 2021 Start of construction: expected 2021 Operational: expected 2025 2nd section (Passow-D/PL border) Construction legislation (planning approval): expected 2022/23 Start of construction: expected 2024 Operational: expected 2026 As of November 2018 What do we aim to achieve? More passengers, more freight transport: increased route capacity Faster and more convenient: travel time between Berlin and Szczecin reduced to 90 minutes (including Nordkreuz-Karow upgrade) by increasing the route speed from 120 km/h to 160 km/h Zero emission transport: continuous electrification between Berlin and Szczecin What are we doing? 1st section (Angermünde–Passow, 19 kilometres) Replacing the existing overhead power cables Upgrading existing tracks to 160km/h Building a new conversion plant in Angermünde for traction power supply Modernising one station Building 740 metres of overtaking tracks Equipping the route with ETCS (European Train Control System) 2nd section (Passow–D/PL border, 30 kilometres) Building a second track Installing new overhead power cables (initial electrification) Upgrading existing tracks to 160km/h Modernising four stations Building 740 metres of overtaking tracks Equipping the route with ETCS

Upload: others

Post on 12-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: upgrading the Angermünde–Szczecin route...in Szczecin, the route is the only trimodal TEN-V core network axis between Poland and Germany. Route upgrade Angermünde–D/PL border,

Publisher

DB Netz AG

Elisabeth-Schwarzhaupt-Platz 1

10155 Berlin

Photos:

Front cover: IVD Ingenieur- und

Vermessungsbüro Dimitrov

Page 5: Fotolia

Maps:

designhaus berlin

Subject to change

No responsibility accepted

for the correctness of the information

As of November 2018

Print management:

DB Kommunikationstechnik GmbH

Karlsruhe, www.dbkt.de

Connecting Europe – upgrading theAngermünde–Szczecin route

A fast, efficient and

sustainable route between Berlin and Szczecin would be

extremely valuable for Europe.

Schwedt/Oder

Raffinerie

Gartz

Tantow

Gumience

Grenze D/PL

Petershagen

Casekow

Schönow

A 11

A 20

B 166

B 2

B 198

B 2

FlugplatzCrussow

Angermünde

Passow

31

Szczecin

1st construction phase

2nd construction phase

What does the upgrade of the Angermünde–Szczecin route mean for Europe?

Sustained improvement in transport links between

Scandinavia, Central and Western Europe as well as between

Germany and Poland

Improved links between the TEN-V core network corridors

Scandinavia-Mediterranean North Sea-Baltic Sea Baltic Sea-Adriatic Orient-Eastern Mediterranean

Improved hinterland connection to Poland's Baltic Sea ports

Improved cross-border rail traffic: development impetus along

the route, as well as in the metropolitan areas of Szczecin and

Berlin-Brandenburg

Future sustainability of the rail connection between Szczecin

and Berlin

In conjunction with the A11/E28 motorway and Oder-Havel Canal

in Szczecin, the route is the only trimodal TEN-V core network axis

between Poland and Germany.

Route upgrade

Angermünde–D/PL border, 49 kilometres

Angermünde

Berlin

Szczecin

Berlin–Szczecin twin-track improvement of European rail traffic

Orient-Eastern Mediterranean

Scandinavia-Mediterranean

North Sea–Baltic Sea

Baltic Sea-Adriatic

TEN-V network corridors

What to expect: project milestones1st section (Angermünde-Passow)

Construction legislation (planning approval): expected 2021

Start of construction: expected 2021

Operational: expected 2025

2nd section (Passow-D/PL border)

Construction legislation (planning approval): expected 2022/23

Start of construction: expected 2024

Operational: expected 2026

As of November 2018What do we aim to achieve?

More passengers, more freight transport: increased route capacity

Faster and more convenient: travel time between Berlin and Szczecin reduced to

90 minutes (including Nordkreuz-Karow upgrade) by

increasing the route speed from 120 km/h to 160 km/h

Zero emission transport: continuous electrification between Berlin and Szczecin

What are we doing?1st section (Angermünde–Passow, 19 kilometres)

Replacing the existing overhead power cables

Upgrading existing tracks to 160km/h

Building a new conversion plant in Angermünde for traction

power supply

Modernising one station

Building 740 metres of overtaking tracks

Equipping the route with ETCS (European Train Control System)

2nd section (Passow–D/PL border, 30 kilometres)

Building a second track

Installing new overhead power cables (initial electrification)

Upgrading existing tracks to 160km/h

Modernising four stations

Building 740 metres of overtaking tracks

Equipping the route with ETCS