tabla de costos directos

81
TIENDA PROVEDOR CONCETO UNIDAD FLETE MANEJO DESUENTO CEMENTO TONELADA $2,040.00 $1,758.62 CAL HIDRA TONELADA $1,480.00 $1,275.86 MORTERO TONELADA $1,780.00 $1,534.48 ACERO TONELADA $12,600.00 $10,862.07 ALAMBRON TONELADA $15,000.00 $12,931.03 GRAVA M3 $235.00 $202.59 M3 $185.00 $159.48 M3 $170.00 $146.55 MILLAR $1,500.00 $1,293.10 PRECIO CON IVA PRECIO SIN IVA PIEDRA BRAZA ARENA DE MINA (MATA GALLINA) TABIQUE COMUN

Upload: antonio-morales-salinas

Post on 27-Nov-2014

262 views

Category:

Documents


7 download

TRANSCRIPT

Page 1: Tabla de Costos Directos

TIENDA

PROVEDOR

CONCETO UNIDAD FLETE MANEJO DESUENTO P.OBRA

CEMENTO TONELADA $2,040.00 $1,758.62CAL HIDRA TONELADA $1,480.00 $1,275.86MORTERO TONELADA $1,780.00 $1,534.48ACERO TONELADA $12,600.00 $10,862.07ALAMBRON TONELADA $15,000.00 $12,931.03GRAVA M3 $235.00 $202.59

M3 $185.00 $159.48

M3 $170.00 $146.55

MILLAR $1,500.00 $1,293.10

PRECIO CON IVA

PRECIO SIN IVA

PIEDRA BRAZA

ARENA DE MINA (MATA GALLINA)

TABIQUE COMUN

Page 2: Tabla de Costos Directos

OBSERVACIONES

Page 3: Tabla de Costos Directos

CONCEPTO VALORIMSS 5%SALARIO INTEGRADO $ 1.0452 FACTOR DE SALARIO REAL $ 1.254 salario minimo del df $ 59.82 SALARIO DEL DF X 3 $ 179.46 CUOTA FIJA 20.40% $ 12.20

OFICIO SALARIO SEMANAL SALARIO DIARIO VIATICOS FACTOR DEMANDA SALARIO DIARIO2

PEON $800.00 $114.29 $50.00 $5.71 $170.00AYUDANTE $900.00 $128.57 $50.00 $6.43 $185.00ALBAÑIL $1,500.00 $214.29 $50.00 $10.71 $275.00CAPINTERO OBRA NEGRA $1,500.00 $214.29 $50.00 $10.71 $275.00FIERRERO $1,500.00 $214.29 $50.00 $10.71 $275.00ELECTRICISTA $1,500.00 $214.29 $50.00 $10.71 $275.00PLOMERO $1,700.00 $242.86 $50.00 $12.14 $305.00CARPINTERO DE BANCO $2,000.00 $285.71 $50.00 $14.29 $350.00HERRERO $1,700.00 $242.86 $50.00 $12.14 $305.00ALUMINERO $1,700.00 $242.86 $50.00 $12.14 $305.00PINTOR $1,200.00 $171.43 $50.00 $8.57 $230.00AZULEJERO $2,000.00 $285.71 $50.00 $14.29 $350.00JARDINERO $2,100.00 $300.00 $50.00 $15.00 $365.00SOLDADOR $2,100.00 $300.00 $50.00 $15.00 $365.00

Page 4: Tabla de Costos Directos

MONTADOR $2,100.00 $300.00 $50.00 $15.00 $365.00CHOFER $1,200.00 $171.43 $50.00 $8.57 $230.00CABO $1,500.00 $214.29 $50.00 $10.71 $275.00MAESTRO DE OBRA $3,000.00 $428.57 $50.00 $21.43 $500.00

LIMITE INFERIOR CUOTA FIJA SUBSIDIO

$ 0.01 $ - 1.92% $ 0.01 $ 93.73 $ 114.25 $ 2.17 6.40% $ 407.34 $ 93.66 $ 969.51 $ 56.91 10.88% $ 610.97 $ 93.66 $ 1,703.81 $ 136.85 16.00% $ 799.69 $ 90.44 $ 1,980.59 $ 181.09 17.92% $ 814.67 $ 88.06 $ 2,371.33 $ 251.16 21.36% $ 1,023.76 $ 81.55 $ 4,782.62 $ 766.15 23.52% $ 1,086.20 $ 74.83 $ 7,538.10 $ 1,414.28 30.00% $ 1,228.58 $ 67.83

$ 1,433.33 $ 58.38 $ 1,638.08 $ 50.12 $ 1,699.89 $ -

TABLA PARA CALCULO DEL ISRSALARIO NETO $ 3,000.00 INTRO. MANUALLIMITE INFERIOR $ 2,371.33 INTRO. MANUAL

$ 628.67 % APLICACIÓN S.E.L.I 21.36% INTRO. MANUAL

$ 134.28

%PARA APLICACIÓN SOBRE EL

EXCEDENTE DE LIMITE INFERIOR

PARA COBRAR SUBSIDIO

Page 5: Tabla de Costos Directos

CUOTA FIJA $ 251.16 INTRO. MANUAL $ 385.44

SUBSIDIO $ - INTRO. MANUALISR $ 385.44

SALARIO NETO $ 3,000.00 IMS $ 150.00 ISR $ 385.44 SALARIO SEMANAL $ 3,535.44

SALARIO NETO $ 3,535.44 LIMITE INFERIOR $ 2,371.33 INTRO. MANUAL

$ 1,164.11 % APLICACIÓN S.E.L.I 21.36% INTRO. MANUAL

$ 248.65 CUOTA FIJA $ 251.16 INTRO. MANUAL

$ 499.81 SUBSIDIO $ - INTRO. MANUALISR $ 499.81

SALARIO NETO $ 3,000.00 IMS $ 150.00 ISR $ 499.81 SALARIO SEMANAL $ 3,649.81

SALARIO NETO $ 3,649.81 LIMITE INFERIOR $ 2,371.33 INTRO. MANUAL

$ 1,278.48 % APLICACIÓN S.E.L.I 21.36% INTRO. MANUAL

$ 273.08

Page 6: Tabla de Costos Directos

CUOTA FIJA $ 251.16 INTRO. MANUAL $ 524.24

SUBSIDIO $ - INTRO. MANUALISR $ 524.24

SALARIO NETO $ 3,000.00 IMS $ 150.00 ISR $ 524.24 SALARIO SEMANAL $ 3,674.24

Page 7: Tabla de Costos Directos

1.10%P

IMSS ISR P/EXEDENTE EXEDENTE 3

$40.00 $ - $ 840.00 $ 120.00 $ 125.42 -$ 54.04 -$ 0.59 $45.00 $ - $ 945.00 $ 135.00 $ 141.10 -$ 38.36 -$ 0.42 $75.00 $ 80.33 $ 1,655.33 $ 236.48 $ 247.16 $ 67.70 $ 0.74 $75.00 $ 80.33 $ 1,655.33 $ 236.48 $ 247.16 $ 67.70 $ 0.74 $75.00 $ 80.33 $ 1,655.33 $ 236.48 $ 247.16 $ 67.70 $ 0.74 $75.00 $ 80.33 $ 1,655.33 $ 236.48 $ 247.16 $ 67.70 $ 0.74 $85.00 $ 177.30 $ 1,962.30 $ 280.33 $ 293.00 $ 113.54 $ 1.25

$100.00 $ 244.70 $ 2,344.70 $ 334.96 $ 350.10 $ 170.64 $ 1.88 $85.00 $ 177.30 $ 1,962.30 $ 280.33 $ 293.00 $ 113.54 $ 1.25 $85.00 $ 177.30 $ 1,962.30 $ 280.33 $ 293.00 $ 113.54 $ 1.25 $60.00 $ 23.02 $ 1,283.02 $ 183.29 $ 191.57 $ 12.11 $ 0.13

$100.00 $ 244.70 $ 2,344.70 $ 334.96 $ 350.10 $ 170.64 $ 1.88 $105.00 $ 251.16 $ 2,456.16 $ 350.88 $ 366.74 $ 187.28 $ 2.06 $105.00 $ 251.16 $ 2,456.16 $ 350.88 $ 366.74 $ 187.28 $ 2.06

SALARIO SEMANAL

SALARIO DIARIO3

SALARIO DIARIO INTEGRADO

Page 8: Tabla de Costos Directos

$105.00 $ 251.16 $ 2,456.16 $ 350.88 $ 366.74 $ 187.28 $ 2.06 $60.00 $ 23.02 $ 1,283.02 $ 183.29 $ 191.57 $ 12.11 $ 0.13 $75.00 $ 80.33 $ 1,655.33 $ 236.48 $ 247.16 $ 67.70 $ 0.74

$150.00 $ 529.46 $ 3,679.46 $ 525.64 $ 549.40 $ 369.94 $ 4.07

OFICIO ISR

PEON $ - AYUDANTE $ - ALBAÑIL $ 80.33 CAPINTERO OBRA NEGRA $ 80.33 FIERRERO $ 80.33 ELECTRICISTA $ 80.33 PLOMERO $ 177.30 CARPINTERO BLANCO $ 244.70 HERRERO $ 177.30 ALUMINERO $ 177.30 PINTOR $ 23.02 AZULEJERO $ 244.70 JARDINERO $ 251.16 SOLDADOR $ 251.16 MONTADOR $ 251.16 CHOFER $ 23.02 CABO $ 80.33 MAESTRO DE OBRA $ 529.46

Page 9: Tabla de Costos Directos

0.40% 0.70% 0.25% 1.05% 0.735% 1.75% 0.625% 1.00% 2%T P T P T P T P T P T

EXEDENTE 3 INVALIDEZ Y VIDA GUARDERIAS SAR

-$ 0.22 $ 0.88 $ 0.31 $ 1.32 $ 0.92 $ 2.19 $ 0.78 $ 1.25 $ 2.51 -$ 0.15 $ 0.99 $ 0.35 $ 1.48 $ 1.04 $ 2.47 $ 0.88 $ 1.41 $ 2.82 $ 0.27 $ 1.73 $ 0.62 $ 2.60 $ 1.82 $ 4.33 $ 1.54 $ 2.47 $ 4.94 $ 0.27 $ 1.73 $ 0.62 $ 2.60 $ 1.82 $ 4.33 $ 1.54 $ 2.47 $ 4.94 $ 0.27 $ 1.73 $ 0.62 $ 2.60 $ 1.82 $ 4.33 $ 1.54 $ 2.47 $ 4.94 $ 0.27 $ 1.73 $ 0.62 $ 2.60 $ 1.82 $ 4.33 $ 1.54 $ 2.47 $ 4.94 $ 0.45 $ 2.05 $ 0.73 $ 3.08 $ 2.15 $ 5.13 $ 1.83 $ 2.93 $ 5.86 $ 0.68 $ 2.45 $ 0.88 $ 3.68 $ 2.57 $ 6.13 $ 2.19 $ 3.50 $ 7.00 $ 0.45 $ 2.05 $ 0.73 $ 3.08 $ 2.15 $ 5.13 $ 1.83 $ 2.93 $ 5.86 $ 0.45 $ 2.05 $ 0.73 $ 3.08 $ 2.15 $ 5.13 $ 1.83 $ 2.93 $ 5.86 $ 0.05 $ 1.34 $ 0.48 $ 2.01 $ 1.41 $ 3.35 $ 1.20 $ 1.92 $ 3.83 $ 0.68 $ 2.45 $ 0.88 $ 3.68 $ 2.57 $ 6.13 $ 2.19 $ 3.50 $ 7.00 $ 0.75 $ 2.57 $ 0.92 $ 3.85 $ 2.70 $ 6.42 $ 2.29 $ 3.67 $ 7.33 $ 0.75 $ 2.57 $ 0.92 $ 3.85 $ 2.70 $ 6.42 $ 2.29 $ 3.67 $ 7.33

PRESTACIONES EN DINERO

GASTOS MEDICO PENCIONADOS

Page 10: Tabla de Costos Directos

$ 0.75 $ 2.57 $ 0.92 $ 3.85 $ 2.70 $ 6.42 $ 2.29 $ 3.67 $ 7.33 $ 0.05 $ 1.34 $ 0.48 $ 2.01 $ 1.41 $ 3.35 $ 1.20 $ 1.92 $ 3.83 $ 0.27 $ 1.73 $ 0.62 $ 2.60 $ 1.82 $ 4.33 $ 1.54 $ 2.47 $ 4.94 $ 1.48 $ 3.85 $ 1.37 $ 5.77 $ 4.04 $ 9.61 $ 3.43 $ 5.49 $ 10.99

Page 11: Tabla de Costos Directos

3.150% 1.125% 5% 2%P T P T P P

CESANTA Y VEJES SUMATORIA INFONAVIT PRESTACIONES

$ 3.95 $ 1.41 $ 24.31 $ 6.27 $ 2.51 $ 33.09 $ 158.51 $ 4.44 $ 1.59 $ 25.82 $ 7.06 $ 2.82 $ 35.70 $ 176.80 $ 7.79 $ 2.78 $ 36.80 $ 12.36 $ 4.94 $ 54.10 $ 301.27 $ 7.79 $ 2.78 $ 36.80 $ 12.36 $ 4.94 $ 54.10 $ 301.27 $ 7.79 $ 2.78 $ 36.80 $ 12.36 $ 4.94 $ 54.10 $ 301.27 $ 7.79 $ 2.78 $ 36.80 $ 12.36 $ 4.94 $ 54.10 $ 301.27 $ 9.23 $ 3.30 $ 41.73 $ 14.65 $ 5.86 $ 62.24 $ 355.24 $ 11.03 $ 3.94 $ 47.86 $ 17.50 $ 7.00 $ 72.37 $ 422.47 $ 9.23 $ 3.30 $ 41.73 $ 14.65 $ 5.86 $ 62.24 $ 355.24 $ 9.23 $ 3.30 $ 41.73 $ 14.65 $ 5.86 $ 62.24 $ 355.24 $ 6.03 $ 2.16 $ 30.82 $ 9.58 $ 3.83 $ 44.23 $ 235.81 $ 11.03 $ 3.94 $ 47.86 $ 17.50 $ 7.00 $ 72.37 $ 422.47 $ 11.55 $ 4.13 $ 49.65 $ 18.34 $ 7.33 $ 75.33 $ 442.07 $ 11.55 $ 4.13 $ 49.65 $ 18.34 $ 7.33 $ 75.33 $ 442.07

IMPUESTO SOBRE LA NOMINA

SALARIO DIARIO PRESTACIONES

Page 12: Tabla de Costos Directos

$ 11.55 $ 4.13 $ 49.65 $ 18.34 $ 7.33 $ 75.33 $ 442.07 $ 6.03 $ 2.16 $ 30.82 $ 9.58 $ 3.83 $ 44.23 $ 235.81 $ 7.79 $ 2.78 $ 36.80 $ 12.36 $ 4.94 $ 54.10 $ 301.27 $ 17.31 $ 6.18 $ 69.29 $ 27.47 $ 10.99 $ 107.75 $ 657.14

Page 13: Tabla de Costos Directos

SALARIO DIARIO REAL

$ 198.77 $ 221.71 $ 377.79 $ 377.79 $ 377.79 $ 377.79 $ 445.47 $ 529.78 $ 445.47 $ 445.47 $ 295.70 $ 529.78 $ 554.35 $ 554.35

Page 14: Tabla de Costos Directos

$ 554.35 $ 295.70 $ 377.79 $ 824.06

Page 15: Tabla de Costos Directos

OFICIO

PEON $ 198.77 AYUDANTE $ 221.71 ALBAÑIL $ 377.79 CAPINTERO OBRA NEGRA $ 377.79 FIERRERO $ 377.79 ELECTRICISTA $ 377.79 PLOMERO $ 445.47 CARPINTERO DE BANCO $ 529.78 HERRERO $ 445.47 ALUMINERO $ 445.47 PINTOR $ 295.70 AZULEJERO $ 529.78 JARDINERO $ 554.35 SOLDADOR $ 554.35 MONTADOR $ 554.35 CHOFER $ 295.70 CABO $ 377.79 MAESTRO DE OBRA $ 806.89

CUADRILLA N° 1 unidad jornada1 PEONCONCEPTO UNIDAD CANTIDAD COSTO UNITARIO1 PEON JORNADA 1 $ 198.77 1 CABO JORNADA 0.0500 $ 377.79 1 MAESTRO DE OBRA JORNADA 0.0167 $ 806.89

SUMATORIAHERRAMIENTA % 5% $ 231.11

SUMATORIA

CUADRILLA N° 3 unidad jornadaCARPINTERO OBRA NEGRA Y AYUDANTECONCEPTO UNIDAD CANTIDAD COSTO UNITARIOCARPINTERO DE OBRA NEGRA JORNADA 1 $ 377.79 AYUDANTE JORNADA 1 $ 221.71 1 CABO JORNADA 0.1000 $ 377.79 1 MAESTRO DE OBRA JORNADA 0.0333 $ 806.89

SUMATORIAHERRAMIENTA % 5% $ 664.17

SUMATORIA

SALARIO DIARIO REAL

Page 16: Tabla de Costos Directos

CUADRILLA N° 5 unidad jornadaOPERADOR DE REVOLVEDORA Y 7 PEONESCONCEPTO UNIDAD CANTIDAD COSTO UNITARIOOPERADOR JORNADA 1 $ 377.79 PEON JORNADA 7 $ 198.77 1 CABO JORNADA 0.4000 $ 377.79 1 MAESTRO DE OBRA JORNADA 0.1333 $ 806.89

SUMATORIAHERRAMIENTA % 5% $ 2,027.89

SUMATORIA

CUADRILLA N° 7 unidad jornadaAZULEJERO Y AYUDANTECONCEPTO UNIDAD CANTIDAD COSTO UNITARIOAZULEJERO JORNADA 1 $ 529.78 AYUDANTE JORNADA 1 $ 221.71 1 CABO JORNADA 0.1000 $ 377.79 1 MAESTRO DE OBRA JORNADA 0.0333 $ 806.89

SUMATORIAHERRAMIENTA % 5% $ 816.16

SUMATORIA

CUADRILLA N° 9 unidad jornadaPINTOR Y AYUDANTECONCEPTO UNIDAD CANTIDAD COSTO UNITARIOPINTOR JORNADA 1 $ 295.70 AYUDANTE JORNADA 1 $ 221.71 1 CABO JORNADA 0.1000 $ 377.79 1 MAESTRO DE OBRA JORNADA 0.0333 $ 806.89

SUMATORIAHERRAMIENTA % 5% $ 582.08

SUMATORIA

CUADRILLA N° 13 unidad jornadaPLOMERO Y AYUDANTECONCEPTO UNIDAD CANTIDAD COSTO UNITARIOPLOMERO JORNADA 1 $ 445.47 AYUDANTE JORNADA 1 $ 221.71 1 CABO JORNADA 0.1000 $ 377.79 1 MAESTRO DE OBRA JORNADA 0.0333 $ 806.89

SUMATORIA

Page 17: Tabla de Costos Directos

HERRAMIENTA % 5% $ 731.85 SUMATORIA

Page 18: Tabla de Costos Directos

CUADRILLA N° 1 unidad jornada CUADRILLA N° 2 unidad jornada1 PEON ALBAÑIL Y PEON

IMPORTE CONCEPTO UNIDAD CANTIDAD $ 198.77 1 PEON JORNADA 1 $ 18.89 1 ALBAÑIL JORNADA 1 $ 13.45 1 CABO JORNADA 0.1000 $ 231.11 1 MAESTRO DE OBRA JORNADA 0.0333 $ 11.56 $ 242.66 HERRAMIENTA % 5%

CUADRILLA N° 3 unidad jornada CUADRILLA N° 4 unidad jornadaFIERRERO Y AYUDANTE

IMPORTE CONCEPTO UNIDAD CANTIDAD $ 377.79 FIERRERO JORNADA 1 $ 221.71 AYUDANTE JORNADA 1 $ 37.78 1 CABO JORNADA 0.1000 $ 26.90 1 MAESTRO DE OBRA JORNADA 0.0333 $ 664.17 $ 33.21 HERRAMIENTA % 5% $ 697.38

Page 19: Tabla de Costos Directos

CUADRILLA N° 5 unidad jornada CUADRILLA N° 6 unidad jornadaALBAÑIL Y 4 PEONES

IMPORTE CONCEPTO UNIDAD CANTIDAD $ 377.79 ALBAÑIL JORNADA 1 $ 1,391.40 PEON JORNADA 4 $ 151.11 1 CABO JORNADA 0.2500 $ 107.59 1 MAESTRO DE OBRA JORNADA 0.0833 $ 2,027.89 $ 101.39 HERRAMIENTA % 5% $ 2,129.29

CUADRILLA N° 7 unidad jornada CUADRILLA N° 8 unidad jornadaYESERO Y AYUDANTE

IMPORTE CONCEPTO UNIDAD CANTIDAD $ 529.78 YESERO JORNADA 1 $ 221.71 AYUDANTE JORNADA 1 $ 37.78 1 CABO JORNADA 0.1000 $ 26.90 1 MAESTRO DE OBRA JORNADA 0.0333 $ 816.16 $ 40.81 HERRAMIENTA % 5% $ 856.96

CUADRILLA N° 9 unidad jornada CUADRILLA N° 10 unidad jornadaHERRERO Y AYUDANTE

IMPORTE CONCEPTO UNIDAD CANTIDAD $ 295.70 HERRERO JORNADA 1 $ 221.71 AYUDANTE JORNADA 1 $ 37.78 1 CABO JORNADA 0.1000 $ 26.90 1 MAESTRO DE OBRA JORNADA 0.0333 $ 582.08 $ 29.10 HERRAMIENTA % 5% $ 611.19

CUADRILLA N° 13 unidad jornada CUADRILLA N° 28 unidad jornada5 PEONES

IMPORTE CONCEPTO UNIDAD CANTIDAD $ 445.47 PEON JORNADA 5 $ 221.71 1 CABO JORNADA 0.2500 $ 37.78 1 MAESTRO DE OBRA JORNADA 0.0833 $ 26.90

731.85 HERRAMIENTA % 5%

Page 20: Tabla de Costos Directos

$ 36.59 768.44

Page 21: Tabla de Costos Directos

CUADRILLA N° 2 unidad jornada

COSTO UNITARIO IMPORTE $ 198.77 $ 198.77 $ 377.79 $ 377.79 $ 377.79 $ 37.78 $ 806.89 $ 26.90 SUMATORIA $ 641.23 $ 641.23 $ 32.06 SUMATORIA $ 673.30

CUADRILLA N° 4 unidad jornada

COSTO UNITARIO IMPORTE $ 377.79 $ 377.79 $ 221.71 $ 221.71 $ 377.79 $ 37.78 $ 806.89 $ 26.90 SUMATORIA $ 664.17 $ 664.17 $ 33.21 SUMATORIA $ 697.38

Page 22: Tabla de Costos Directos

CUADRILLA N° 6 unidad jornada

COSTO UNITARIO IMPORTE $ 377.79 $ 377.79 $ 198.77 $ 795.09 $ 377.79 $ 94.45 $ 806.89 $ 67.24 SUMATORIA $ 1,334.56 $ 1,334.56 $ 66.73 SUMATORIA $ 1,401.29

CUADRILLA N° 8 unidad jornada

COSTO UNITARIO IMPORTE $ 529.78 $ 529.78 $ 221.71 $ 221.71 $ 377.79 $ 37.78 $ 806.89 $ 26.90 SUMATORIA $ 816.16 $ 816.16 $ 40.81 SUMATORIA $ 856.96

CUADRILLA N° 10 unidad jornada

COSTO UNITARIO IMPORTE $ 445.47 $ 445.47 $ 221.71 $ 221.71 $ 377.79 $ 37.78 $ 806.89 $ 26.90 SUMATORIA 731.85 $ 731.85 $ 36.59 SUMATORIA 768.44

CUADRILLA N° 28 unidad jornada

COSTO UNITARIO IMPORTE $ 198.77 $ 993.86 $ 377.79 $ 94.45 $ 806.89 $ 67.24 SUMATORIA 1155.55 $ 1,155.55 $ 57.78

Page 23: Tabla de Costos Directos

SUMATORIA 1213.32

Page 24: Tabla de Costos Directos

metro cubico del agua

MORTERO CEMENTO - ARENA

CEMENTO- AREA 1:2 (UNIDAD M3)

DESCRIPCION UNIDAD CANTIDADCEMENTI TIPO 1 0.603 3% TON 0.621

ARENA 1 7% 1.070

AGUA 0.275 25% 0.344

CEMENTO- AREA 1:3 (UNIDAD M3)

DESCRIPCION UNIDAD CANTIDADCEMENTI TIPO 1 0.510 3% TON 0.525

ARENA 1.100 7% 1.177

AGUA 0.272 25% 0.340

CEMENTO- AREA 1:4 (UNIDAD M3)

DESCRIPCION UNIDAD CANTIDADCEMENTI TIPO 1 0.430 3% TON 0.443

ARENA 1.120 7% 1.198

AGUA 0.266 25% 0.333

CEMENTO- AREA 1:5 (UNIDAD M3)

DESCRIPCION UNIDAD CANTIDADCEMENTI TIPO 1 0.360 3% TON 0.371

ARENA 1.150 7% 1.231

AGUA 0.261 25% 0.326

CEMENTO- AREA 1:6 (UNIDAD M3)

DESCRIPCION UNIDAD CANTIDADCEMENTI TIPO 1 0.300 3% TON 0.309

ARENA 1.190 7% 1.273

AGUA 0.257 25% 0.321

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

Page 25: Tabla de Costos Directos

CEMENTO- AREA 1:7 (UNIDAD M3)

DESCRIPCION UNIDAD CANTIDADCEMENTI TIPO 1 0.250 3% TON 0.258

ARENA 1.240 7% 1.327

AGUA 0.252 25% 0.315

CEMENTO- AREA 1:8 (UNIDAD M3)

DESCRIPCION UNIDAD CANTIDADCEMENTI TIPO 1 0.210 3% TON 0.216

ARENA 1.300 7% 1.391

AGUA 0.246 25% 0.308

Entre mas arena se ocupe el precio del mortero es mas varato

MEZCLA CEMENTO - ARENA CERNIDA

CEMENTO- ARENA CERNIDA 1:2

DESCRIPCION UNIDAD CANTIDADCEMENTI TIPO 1 0.603 3% TON 0.621

ARENA 1 7% 1.070

AGUA 0.285 25% 0.356

CEMENTO- AREA CERNIDA 1:3

DESCRIPCION UNIDAD CANTIDADCEMENTI TIPO 1 0.540 3% TON 0.556

ARENA 1.050 7% 1.124

AGUA 0.28 25% 0.350

CEMENTO- AREA CERNIDA 1:4

DESCRIPCION UNIDAD CANTIDAD

M3

M3

M3

M3

M3

M3

M3

M3

Page 26: Tabla de Costos Directos

CEMENTI TIPO 1 0.440 3% TON 0.453

ARENA 1.100 7% 1.177

AGUA 0.278 25% 0.348

CEMENTO- AREA CERNIDA 1:5

DESCRIPCION UNIDAD CANTIDADCEMENTI TIPO 1 0.380 3% TON 0.391

ARENA 1.150 7% 1.231

AGUA 0.275 25% 0.344

CEMENTO- AREA CERENIDA 1:6

DESCRIPCION UNIDAD CANTIDADCEMENTI TIPO 1 0.310 3% TON 0.319

ARENA 1.170 7% 1.252

AGUA 0.273 25% 0.341

PASTAS

PASTA DE CEMENTO BLANCO (UNIDAD M3)

DESCRIPCION UNIDAD CANTIDADCEMENTO BLANCO 1.545 3% TON 1.591

AGUA 0.91 30% 1.183

PASTA DE CEMENTO GRIS (UNIDAD M3)

DESCRIPCION UNIDAD CANTIDADCEMENTO GRIS 1.545 3% TON 1.591

M3

M3

M3

M3

M3

M3

M3

Page 27: Tabla de Costos Directos

AGUA 0.91 30% 1.183

PASTA DE YESO (UNIDAD M3)

DESCRIPCION UNIDAD CANTIDADYESO 0.834 3% TON 0.859

AGUA 1.17 30% 1.521

LECHADA CEMENTO BLANCO (UNIDAD M3)

DESCRIPCION UNIDAD CANTIDADCEMENTO BLANCO 1.339 3% TON 1.379

AGUA 1.17 30% 1.521

LECHADA CEMENTO GRIS (UNIDAD M3)

DESCRIPCION UNIDAD CANTIDADCEMENTO GRIS 1.339 3% TON 1.379

AGUA 1.17 30% 1.521

M3

M3

M3

M3

Page 28: Tabla de Costos Directos

MORTERO CEMENTO - ARENA MORTERO CALHIDRA - ARENA

CEMENTO- AREA 1:2 (UNIDAD M3) CALHIDRA- AREA 1:2

COSTO UNITARIO IMPORTE DESCRIPCION $ 1,940.00 $ 1,204.91 CALHIDRA 3%

$ 170.00 $ 181.90 ARENA 7%

$ 2.00 $ 0.69 AGUA 25%SUMATORIA $ 1,387.50

CEMENTO- AREA 1:3 (UNIDAD M3) CALHIDRA- AREA 1:3

COSTO UNITARIO IMPORTE DESCRIPCION $ 1,940.00 $ 1,019.08 CALHIDRA 0.250 3%

$ 170.00 $ 200.09 ARENA 1.000 7%

$ 2.00 $ 0.68 AGUA 0.270 25%SUMATORIA $ 1,219.85

CEMENTO- AREA 1:4 (UNIDAD M3) CALHIDRA- AREA 1:4

COSTO UNITARIO IMPORTE DESCRIPCION $ 1,940.00 $ 859.23 CALHIDRA 0.200 3%

$ 170.00 $ 203.73 ARENA 1.070 7%

$ 2.00 $ 0.67 AGUA 0.260 25%SUMATORIA $ 1,063.62

CEMENTO- AREA 1:5 (UNIDAD M3) CALHIDRA- AREA 1:5

COSTO UNITARIO IMPORTE DESCRIPCION $ 1,940.00 $ 719.35 CALHIDRA 0.170 3%

$ 170.00 $ 209.18 ARENA 1.130 7%

$ 2.00 $ 0.65 AGUA 0.255 25%SUMATORIA $ 929.19

CEMENTO- AREA 1:6 (UNIDAD M3) CALHIDRA- AREA 1:6

COSTO UNITARIO IMPORTE DESCRIPCION $ 1,940.00 $ 599.46 CALHIDRA 0.145 3%

$ 170.00 $ 216.46 ARENA 1.180 7%

$ 2.00 $ 0.64 AGUA 0.250 25%SUMATORIA $ 816.56

Page 29: Tabla de Costos Directos

CEMENTO- AREA 1:7 (UNIDAD M3) CALHIDRA- AREA 1:7

COSTO UNITARIO IMPORTE DESCRIPCION $ 1,940.00 $ 499.55 CALHIDRA 0.125 3%

$ 170.00 $ 225.56 ARENA 1.220 7%

$ 2.00 $ 0.63 AGUA 0.245 25%SUMATORIA $ 725.74

CEMENTO- AREA 1:8 (UNIDAD M3) CALHIDRA- AREA 1:8

COSTO UNITARIO IMPORTE DESCRIPCION $ 1,940.00 $ 419.62 CALHIDRA 0.110 3%

$ 170.00 $ 236.47 ARENA 1.250 7%

$ 2.00 $ 0.62 AGUA 0.240 25%SUMATORIA $ 656.71

Entre mas arena se ocupe el precio del mortero es mas varato Es un mortero de menor calidad

MEZCLA CEMENTO - ARENA CERNIDA MEZCLA CEMENTO- CALHIDRA - ARENA

CEMENTO- ARENA CERNIDA 1:2 CEMENTO-CALHIDRA- AREA 1:1:4

COSTO UNITARIO IMPORTE DESCRIPCION $ 1,940.00 $ 1,204.91 CEMENTI TIPO 1 0.300 3%

$ 170.00 $ 181.90 CALHIDRA 0.150 3%

$ 2.00 $ 0.71 ARENA 1.000 7%

SUMATORIA $ 1,387.53 AGUA 0.280 25%

CEMENTO- AREA CERNIDA 1:3CEMENTO-CALHIDRA- AREA 1:1:6

COSTO UNITARIO IMPORTE $ 1,940.00 $ 1,079.03 DESCRIPCION

$ 170.00 $ 191.00 CEMENTI TIPO 1 0.255 3%

$ 2.00 $ 0.70 CALHIDRA 0.125 3%

SUMATORIA $ 1,270.72 ARENA 1.050 7%

AGUA 0.279 25%CEMENTO- AREA CERNIDA 1:4

COSTO UNITARIO IMPORTE CEMENTO-CALHIDRA- AREA 1:1:8

Page 30: Tabla de Costos Directos

$ 1,940.00 $ 879.21

$ 170.00 $ 200.09 DESCRIPCION

$ 2.00 $ 0.70 CEMENTI TIPO 1 0.215 3%SUMATORIA $ 1,079.99 CALHIDRA 0.100 3%

ARENA 1.095 7%

CEMENTO- AREA CERNIDA 1:5 AGUA 0.278 25%

COSTO UNITARIO IMPORTE $ 1,940.00 $ 759.32 CEMENTO-CALHIDRA- AREA 1:1:10

$ 170.00 $ 209.18

$ 2.00 $ 0.69 DESCRIPCION

SUMATORIA $ 969.19 CEMENTI TIPO 1 0.180 3%CALHIDRA 0.085 3%

CEMENTO- AREA CERENIDA 1:6 ARENA 1.065 7%

AGUA 0.275 25%COSTO UNITARIO IMPORTE

$ 1,940.00 $ 619.44

$ 170.00 $ 212.82 CEMENTO-CALHIDRA- AREA 1:1:12

$ 2.00 $ 0.68 SUMATORIA $ 832.95 DESCRIPCION

CEMENTI TIPO 1 0.150 3%CALHIDRA 0.075 3%

ARENA 1.185 7%

AGUA 0.273 25%

PASTAS

PASTA DE CEMENTO BLANCO (UNIDAD M3) PASTA CEMENTO BLANCO-PALVO DE MARMOL 1:3 (UNIDAD M3)

COSTO UNITARIO IMPORTE DESCRIPCION $ 3,200.00 $ 5,092.32 CEMENTO 0.540 3%

$ 2.00 $ 2.37 POLVO DE MARMOL 2.100 5%

SUMATORIA $ 5,094.69 AGUA 0.280 30%

PASTA DE CEMENTO GRIS (UNIDAD M3)

COSTO UNITARIO IMPORTE $ 1,940.00 $ 3,087.22

Page 31: Tabla de Costos Directos

$ 2.00 $ 2.37 SUMATORIA $ 3,089.58

PASTA DE YESO (UNIDAD M3)

COSTO UNITARIO IMPORTE $ 2,000.00 $ 1,718.04

$ 2.00 $ 3.04 SUMATORIA $ 1,721.08

LECHADA CEMENTO BLANCO (UNIDAD M3)

COSTO UNITARIO IMPORTE $ 3,200.00 $ 4,413.34

$ 2.00 $ 3.04 SUMATORIA $ 4,416.39

LECHADA CEMENTO GRIS (UNIDAD M3)

COSTO UNITARIO IMPORTE $ 1,940.00 $ 2,675.59

$ 2.00 $ 3.04 SUMATORIA $ 2,678.63

Page 32: Tabla de Costos Directos

MORTERO CALHIDRA - ARENA

CALHIDRA- AREA 1:2

UNIDAD CANTIDAD COSTO UNITARIO IMPORTETON 0.000 $ -

0.000 $ -

0.000 $ - SUMATORIA $ -

CALHIDRA- AREA 1:3

UNIDAD CANTIDAD COSTO UNITARIO IMPORTETON 0.258 $ 1,480.00 $ 381.10

1.070 $ 170.00 $ 181.90

0.338 $ 2.00 $ 0.68 SUMATORIA $ 563.68

CALHIDRA- AREA 1:4

UNIDAD CANTIDAD COSTO UNITARIO IMPORTETON 0.206 $ 1,480.00 $ 304.88

1.145 $ 170.00 $ 194.63

0.325 $ 2.00 $ 0.65 SUMATORIA $ 500.16

CALHIDRA- AREA 1:5

UNIDAD CANTIDAD COSTO UNITARIO IMPORTETON 0.175 $ 1,480.00 $ 259.15

1.209 $ 170.00 $ 205.55

0.319 $ 2.00 $ 0.64 SUMATORIA $ 465.33

CALHIDRA- AREA 1:6

UNIDAD CANTIDAD COSTO UNITARIO IMPORTETON 0.149 $ 1,480.00 $ 221.04

1.263 $ 170.00 $ 214.64

0.313 $ 2.00 $ 0.63 SUMATORIA $ 436.30

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

Page 33: Tabla de Costos Directos

CALHIDRA- AREA 1:7

UNIDAD CANTIDAD COSTO UNITARIO IMPORTETON 0.129 $ 1,480.00 $ 190.55

1.305 $ 170.00 $ 221.92

0.306 $ 2.00 $ 0.61 SUMATORIA $ 413.08

CALHIDRA- AREA 1:8

UNIDAD CANTIDAD COSTO UNITARIO IMPORTETON 0.113 $ 1,480.00 $ 167.68

1.338 $ 170.00 $ 227.37

0.300 $ 2.00 $ 0.60 SUMATORIA $ 395.66

Es un mortero de menor calidad

MEZCLA CEMENTO- CALHIDRA - ARENA

CEMENTO-CALHIDRA- AREA 1:1:4

UNIDAD CANTIDAD COSTO UNITARIO IMPORTETON 0.309 $ 1,940.00 $ 599.46 TON 0.155 $ 1,480.00 $ 228.66

1.070 $ 170.00 $ 181.90

0.350 $ 2.00 $ 0.70 SUMATORIA $ 1,010.72

CEMENTO-CALHIDRA- AREA 1:1:6

UNIDAD CANTIDAD COSTO UNITARIO IMPORTETON 0.263 $ 1,940.00 $ 509.54 TON 0.129 $ 1,480.00 $ 190.55

1.124 $ 170.00 $ 191.00

0.349 $ 2.00 $ 0.70 SUMATORIA $ 891.78

CEMENTO-CALHIDRA- AREA 1:1:8

M3

M3

M3

M3

M3

M3

M3

M3

Page 34: Tabla de Costos Directos

UNIDAD CANTIDAD COSTO UNITARIO IMPORTE

TON 0.221 $ 1,940.00 $ 429.61 TON 0.103 $ 1,480.00 $ 152.44

1.172 $ 170.00 $ 199.18

0.348 $ 2.00 $ 0.70 SUMATORIA $ 781.93

CEMENTO-CALHIDRA- AREA 1:1:10

UNIDAD CANTIDAD COSTO UNITARIO IMPORTETON 0.185 $ 1,940.00 $ 359.68 TON 0.088 $ 1,480.00 $ 129.57

1.140 $ 170.00 $ 193.72

0.344 $ 2.00 $ 0.69 SUMATORIA $ 683.66

CEMENTO-CALHIDRA- AREA 1:1:12

UNIDAD CANTIDAD COSTO UNITARIO IMPORTETON 0.155 $ 1,940.00 $ 299.73 TON 0.077 $ 1,480.00 $ 114.33

1.268 $ 170.00 $ 215.55

0.341 $ 2.00 $ 0.68 SUMATORIA $ 630.29

PASTA CEMENTO BLANCO-PALVO DE MARMOL 1:3 (UNIDAD M3)

UNIDAD CANTIDAD COSTO UNITARIO IMPORTETON 0.556 $ 1,940.00 $ 1,079.03 TON 2.205 $ 170.00 $ 374.85

0.364 $ 2.00 $ 0.73 SUMATORIA $ 1,454.61

M3

M3

M3

M3

M3

M3

M3

Page 35: Tabla de Costos Directos

CONCRETO F´C= 150 kg/cm2 HECHO EN OBRA CON AGREGADO MAXIMO DE 3/4"

CONCEPTO UNIDAD CANTIDAD COSTO UNITARIOA) CEMENTO 0.358 3% TON 0.369 $ 1,940.00

ARENA 0.497 7% M3 0.532 $ 170.00 GRAVA 0.601 7% M3 0.643 $ 235.00 AGUA 0.202 25% M3 0.253 $ 2.00

B) M. OBRACUADRILLA 5 JORNADA 1 $ 2,129.29

c)M3 1 $ 14.42

SUMATORIA

CONCRETO F´C= 200 kg/cm2 HECHO EN OBRA CON AGREGADO MAXIMO DE 3/4"

CONCEPTO UNIDAD CANTIDAD COSTO UNITARIOA) CEMENTO 0.355 3% TON 0.366 $ 1,940.00

ARENA 0.47 7% M3 0.503 $ 170.00 GRAVA 0.65 7% M3 0.696 $ 235.00 AGUA 0.195 25% M3 0.244 $ 2.00

B) M. OBRACUADRILLA 5 JORNADA 1 $ 2,129.29

c)M3 1 $ 14.42

SUMATORIA

CONCRETO F´C= 250 kg/cm2 HECHO EN OBRA CON AGREGADO MAXIMO DE 3/4"

CONCEPTO UNIDAD CANTIDAD COSTO UNITARIOA) CEMENTO 0.423 3% TON 0.436 $ 1,940.00

ARENA 0.465 7% M3 0.498 $ 170.00

HERRAMIENTA Y EQUIPO

REVOBEDORA/MIPSA/MOTOR

KOHLER 8HP

HERRAMIENTA Y EQUIPO

REVOBEDORA/MIPSA/MOTOR

KOHLER 8HP

Page 36: Tabla de Costos Directos

GRAVA 0.64 7% M3 0.685 $ 235.00 AGUA 0.19 25% M3 0.238 $ 2.00

B) M. OBRACUADRILLA 5 JORNADA 1 $ 2,129.29

c)M3 1 $ 14.42

SUMATORIA

CONCRETO F´C= 300 kg/cm2 HECHO EN OBRA CON AGREGADO MAXIMO DE 3/4"

CONCEPTO UNIDAD CANTIDAD COSTO UNITARIOA) CEMENTO 0.393 3% TON 0.405 $ 1,940.00

ARENA 0.475 7% M3 0.508 $ 170.00 GRAVA 0.74 7% M3 0.792 $ 235.00 AGUA 0.177 25% M3 0.221 $ 2.00

B) M. OBRACUADRILLA 5 JORNADA 1 $ 2,129.29

c)M3 1 $ 14.42

SUMATORIA

CONCRETO F´C= 350 kg/cm2 HECHO EN OBRA CON AGREGADO MAXIMO DE 3/4"

CONCEPTO UNIDAD CANTIDAD COSTO UNITARIOA) CEMENTO 0.377 3% TON 0.388 $ 1,940.00

ARENA 0.485 7% M3 0.519 $ 170.00 GRAVA 0.84 7% M3 0.899 $ 235.00 AGUA 0.17 25% M3 0.213 $ 2.00

B) M. OBRACUADRILLA 5 JORNADA 1 $ 2,129.29

c)M3 1 $ 14.42

HERRAMIENTA Y EQUIPO

REVOBEDORA/MIPSA/MOTOR

KOHLER 8HP

HERRAMIENTA Y EQUIPO

REVOBEDORA/MIPSA/MOTOR

KOHLER 8HP

HERRAMIENTA Y EQUIPO

REVOBEDORA/MIPSA/MOTOR

KOHLER 8HP

Page 37: Tabla de Costos Directos

SUMATORIA

CONCRETO F´C= 400 kg/cm2 HECHO EN OBRA CON AGREGADO MAXIMO DE 3/4"

CONCEPTO UNIDAD CANTIDAD COSTO UNITARIOA) CEMENTO 0.425 3% TON 0.438 $ 1,940.00

891 ARENA 0.495 7% M3 0.530 $ 170.00 928 GRAVA 0.94 7% M3 1.006 $ 235.00

AGUA 0.188 25% M3 0.235 $ 2.00

B) M. OBRACUADRILLA 5 JORNADA 1 $ 2,129.29

c)M3 1 $ 14.42

SUMATORIA

REVOBEDORA/MIPSA/MOTOR

KOHLER 8HP

HERRAMIENTA Y EQUIPO

REVOBEDORA/MIPSA/MOTOR

KOHLER 8HP

Page 38: Tabla de Costos Directos

CONCRETO F´C= 150 kg/cm2 HECHO EN OBRA CON AGREGADO MAXIMO DE 3/4" CONCRETO F´C= 100 kg/cm2 HECHO EN OBRA CON AGREGADO MAXIMO DE 3/4"

IMPORTE CONCEPTO UNIDAD CANTIDAD $ 715.36 A) CEMENTO 0.26 3% TON 0.268 $ 90.40 ARENA 0.5 8% M3 0.540 $ 151.12 GRAVA 0.68 8% M3 0.734 $ 0.51 AGUA 0.195 30% M3 0.254

B) M. OBRA $ 2,129.29 CUADRILLA 5 JORNADA 1

c) $ 14.42 M3 1

$ 3,101.10

CONCRETO F´C= 200 kg/cm2 HECHO EN OBRA CON AGREGADO MAXIMO DE 3/4"

IMPORTE $ 709.36 $ 85.49 $ 163.44 $ 0.49

$ 2,129.29

$ 14.42

$ 3,102.49

CONCRETO F´C= 250 kg/cm2 HECHO EN OBRA CON AGREGADO MAXIMO DE 3/4"

IMPORTE $ 845.24 $ 84.58

HERRAMIENTA Y

EQUIPOREVOBEDOR

A/MIPSA/MOTOR

KOHLER 8HP

Page 39: Tabla de Costos Directos

$ 160.93 $ 0.48

$ 2,129.29

$ 14.42

$ 3,234.94

CONCRETO F´C= 300 kg/cm2 HECHO EN OBRA CON AGREGADO MAXIMO DE 3/4"

IMPORTE $ 785.29 $ 86.40 $ 186.07 $ 0.44

$ 2,129.29

$ 14.42

$ 3,201.92

CONCRETO F´C= 350 kg/cm2 HECHO EN OBRA CON AGREGADO MAXIMO DE 3/4"

IMPORTE $ 753.32 $ 88.22 $ 211.22 $ 0.43

$ 2,129.29

$ 14.42

Page 40: Tabla de Costos Directos

$ 3,196.90

CONCRETO F´C= 400 kg/cm2 HECHO EN OBRA CON AGREGADO MAXIMO DE 3/4"

IMPORTE $ 849.23 $ 90.04 $ 236.36 $ 0.47

$ 2,129.29

$ 14.42

$ 3,319.82

Page 41: Tabla de Costos Directos

CONCRETO F´C= 100 kg/cm2 HECHO EN OBRA CON AGREGADO MAXIMO DE 3/4" CONCRETO F´C= 100 kg/cm2 HECHO EN OBRA CON AGREGADO MAXIMO DE 1 1/2"

COSTO UNITARIOIMPORTE CONCEPTO UNIDAD $ 1,940.00 $ 519.53 A) CEMENTO 0.254 3% TON $ 170.00 $ 91.80 ARENA 0.47 8% M3 $ 235.00 $ 172.58 GRAVA 0.7 8% M3 $ 2.00 $ 0.51 AGUA 1.9 30% M3

B) M. OBRA $ 2,129.29 $ 2,129.29 CUADRILLA 5 JORNADA

c) $ 14.42 $ 14.42 M3

SUMATORIA $ 2,928.13

HERRAMIENTA Y

EQUIPOREVOBEDOR

A/MIPSA/MOTOR

KOHLER 8HP

Page 42: Tabla de Costos Directos

CONCRETO F´C= 100 kg/cm2 HECHO EN OBRA CON AGREGADO MAXIMO DE 1 1/2"

CANTIDADCOSTO UNITARIOIMPORTE0.262 $ 1,940.00 $ 507.54 0.508 $ 170.00 $ 86.29 0.756 $ 235.00 $ 177.66 2.470 $ 2.00 $ 4.94

1 $ 2,129.29 $ 2,129.29

1 $ 14.42 $ 14.42

SUMATORIA $ 2,920.14

Page 43: Tabla de Costos Directos

REVOLVEDORA MIPSA MOTOR KOHLER8HI CON CAPACIDAD DE 1 SACOcosto de inversion $ 20,000.00

COST

OS

FIJO

S

taza de de interez anual 5%horas anualez de uso 1400 hrs. Anualesvida util 4 añosQ 100%seguro 2.50%costo almacenaje $ 480.00 anualesllantas 0fletes $ 500.00

GASTOS COSTO TOTALgasto anual combustible 2.4 $ 10.00 $ 24.00 gasto anual lubricantes 0.08 $ 35.00 $ 2.80

VIBRADORES PARA CONCRETO DE GASOLINA MOTOR COHLER MOD. DE 4 HP FLECHA FLEXIBLEcosto de inversion $ 10,070.00

COST

OS

FIJO

S

taza de de interez anual 15%horas anualez de uso 2400 hrs. Anualesvida util 3 años 20.80m3 1 jornadaQ 50%seguro 2.50%costo almacenaje $ 240.00 anualesllantas 0fletes $ 500.00

GASTOS COSTO TOTALgasto anual combustible 1.2 $ 10.00 $ 12.00 gasto anual lubricantes 0.4 $ 35.00 $ 14.00

BOMBA MODELO 10 M. MOTOR KOHLER K181 DE 8 PH A 3600 RPMcosto de inversion $ 15,960.00

COST

OS

FIJO

S

taza de de interez anual 15%horas anualez de uso 2400 hrs. Anualesvida util 2 añosQ 50%seguro 2.50%costo almacenaje $ 120.00 anualesllantas 0fletes $ 500.00

GASTOS COSTO TOTALgasto anual combustible 3 $ 10.00 $ 30.00 gasto anual lubricantes 0.1 $ 35.00 $ 3.50

COST

OS

DE

OPE

RACI

ÓN

COST

OS

DE

OPE

RACI

ÓN

COST

OS

DE

OPE

RACI

ÓN

Page 44: Tabla de Costos Directos

MALACATE DE 3/4 TONELADAS DE 12 HP costo de inversion $ 37,300.00

COST

OS

FIJO

S

taza de de interez anual 15%horas anualez de uso 2400 hrs. Anualesvida util 4 añosQ 50%seguro 2.50%costo almacenaje $ 480.00 anualesllantas 0fletes $ 500.00

GASTOS COSTO TOTALgasto anual combustible 3.6 $ 10.00 $ 36.00 gasto anual lubricantes 0.12 $ 35.00 $ 4.20

CAMION DE VOLTEO DE 8 TONELADAS 5 M3costo de inversion $ 700,000.00

COST

OS

FIJO

S

taza de de interez anual 5%horas anualez de uso 2400 hrs. Anualesvida util 5 añosQ 50%seguro 2.00%costo almacenaje anuales vida utilllantas $ 2,600.00 6 llantas 2fletes $ -

GASTOS COSTO TOTALgasto anual combustible 8 $ 10.00 $ 80.00 gasto anual lubricantes 0.1 $ 35.00 $ 3.50

MOTOCONFORMADORA HUBER F-1400,140HP,VERTEDORcosto de inversion $ 750,000.00

COST

OS

FIJO

S

taza de de interez anual 15%horas anualez de uso 2400 hrs. Anualesvida util 4 añosQ 75%seguro 2.00%costo almacenaje anuales vida utilllantas $ 4,250.00 6 LLANTAS 2fletes $ 500.00

GASTOS COSTO TOTALgasto anual combustible 28 $ 10.00 $ 280.00 gasto anual lubricantes 0.46 $ 35.00 $ 16.10

COST

OS

DE

OPE

RACI

ÓN

COST

OS

DE

OPE

RACI

ÓN

COST

OS

DE

OPE

RACI

ÓN

Page 45: Tabla de Costos Directos

TRACTOR TEREX 82-40,275 HP HIDRAULICOcosto de inversion $ 1,025,000.00

COST

OS

FIJO

S

taza de de interez anual 15%horas anualez de uso 2400 hrs. Anualesvida util 4 añosQ 75%seguro 2.00%costo almacenaje anualesllantas $ - 0 llantasfletes $ 500.00

GASTOS COSTO TOTALgasto anual combustible 55 $ 10.00 $ 550.00 gasto anual lubricantes 0.59 $ 35.00 $ 20.65

APLANADORA HUBER E 1014, 73 HP DE 10 A 14 TONcosto de inversion $ 327,500.00

COST

OS

FIJO

S

taza de de interez anual 15%horas anualez de uso 2400 hrs. Anualesvida util 4 añosQ 5%seguro 2.00%costo almacenaje anualesllantas $ - 0 llantasfletes $ 500.00

GASTOS COSTO TOTALgasto anual combustible 14.6 $ 10.00 $ 146.00 gasto anual lubricantes 0.2 $ 35.00 $ 7.00

COST

OS

DE

OPE

RACI

ÓN

COST

OS

DE

OPE

RACI

ÓN

Page 46: Tabla de Costos Directos

REVOLVEDORA MIPSA MOTOR KOHLER8HI CON CAPACIDAD DE 1 SACOINTERESES 0.71

DEPRESIACION $ 3.57 REPARACIONES $ 3.57 TOTAL $ 8.56

SEGUROS 0.36ALMASENAJE $ 0.34

COMBUSTIBLE $ 24.00 LUBRICANTE 2.8 TOTAL $ 27.51

LLANTAS $ - FLETES 0.71

GASTO TOTAL $ 36.07

VIBRADORES PARA CONCRETO DE GASOLINA MOTOR COHLER MOD. DE 4 HP FLECHA FLEXIBLEINTERESES 0.63

DEPRESIACION $ 1.40 REPARACIONES $ 0.70 TOTAL $ 2.93

SEGUROS 0.10ALMASENAJE $ 0.10

COMBUSTIBLE $ 12.00 LUBRICANTE 14 TOTAL $ 26.42

LLANTAS $ - FLETES 0.42

GASTO TOTAL $ 29.35

BOMBA MODELO 10 M. MOTOR KOHLER K181 DE 8 PH A 3600 RPMINTERESES 1.00

DEPRESIACION $ 3.33 REPARACIONES $ 1.66 TOTAL $ 6.20

SEGUROS 0.17ALMASENAJE $ 0.05

COMBUSTIBLE $ 30.00 LUBRICANTE 3.5 TOTAL $ 33.92

LLANTAS $ - FLETES 0.42

GASTO TOTAL $ 40.12

Page 47: Tabla de Costos Directos

MALACATE DE 3/4 TONELADAS DE 12 HP INTERESES 2.33

DEPRESIACION $ 3.89 REPARACIONES $ 1.94 TOTAL $ 8.75

SEGUROS 0.39ALMASENAJE $ 0.20

COMBUSTIBLE $ 36.00 LUBRICANTE 4.2 TOTAL $ 40.62

LLANTAS $ - FLETES 0.42

GASTO TOTAL $ 49.36

CAMION DE VOLTEO DE 8 TONELADAS 5 M3INTERESES 14.58

DEPRESIACION $ 58.33 REPARACIONES $ 29.17 TOTAL $ 107.92

SEGUROS 5.83ALMASENAJE $ -

COMBUSTIBLE $ 80.00 LUBRICANTE 3.5 TOTAL $ 86.75

LLANTAS $ 3.25 FLETES 0.00

GASTO TOTAL $ 194.67

MOTOCONFORMADORA HUBER F-1400,140HP,VERTEDORINTERESES 46.88

DEPRESIACION $ 78.13 REPARACIONES $ 58.59 TOTAL $ 189.84

SEGUROS 6.25ALMASENAJE $ -

COMBUSTIBLE $ 280.00 LUBRICANTE 16.1 TOTAL $ 301.83

LLANTAS $ 5.31 FLETES 0.42

GASTO TOTAL $ 491.67

Page 48: Tabla de Costos Directos

TRACTOR TEREX 82-40,275 HP HIDRAULICOINTERESES 64.06

DEPRESIACION $ 106.77 REPARACIONES $ 80.08 TOTAL $ 259.45

SEGUROS 8.54ALMASENAJE $ -

COMBUSTIBLE $ 550.00 LUBRICANTE 20.65 TOTAL $ 570.65

LLANTAS $ - FLETES

GASTO TOTAL $ 830.10

APLANADORA HUBER E 1014, 73 HP DE 10 A 14 TONINTERESES 20.47

DEPRESIACION $ 34.11 REPARACIONES $ 1.71 TOTAL $ 59.02

SEGUROS 2.73ALMASENAJE $ -

COMBUSTIBLE $ 146.00 LUBRICANTE 7 TOTAL $ 153.00

LLANTAS $ - FLETES

GASTO TOTAL $ 212.02

Page 49: Tabla de Costos Directos

UNIDAD M3RENDIMIENTO 0.5 M3/JORNADA

CONCEPTO UNIDAD ENTIDAD PRECIO UNITARIO IMPORTEMATERIALES M3 0 $ - $ - CUADRILLA N° 1 JORNADA 2 $ 242.66 $ 485.32

M30 $ - $ -

TOTAL $ 485.32

UNIDAD M3RENDIMIENTO 1.2 M3/JORNADA

CONCEPTO UNIDAD ENTIDAD PRECIO UNITARIO IMPORTEMATERIALES M3 0 $ - $ - CUADRILLA N° 1 JORNADA 0.833 $ 242.66 $ 202.22

M30 $ - $ -

TOTAL $ 202.22

DEMOLICION DE CONCRETO ARMADO

HERRAMIENTA Y EQUIPO

DEMOLICION DE MUROS DE TABIQUE

HERRAMIENTA Y EQUIPO

Page 50: Tabla de Costos Directos

UNIDAD M3RENDIMIENTO 1 M3/JORNADA

CONCEPTO UNIDAD ENTIDAD PRECIO UNITARIO IMPORTEMATERIALES M3 0 $ - $ - CUADRILLA N° 1 JORNADA 1 $ 242.66 $ 242.66

M30 $ - $ -

TOTAL $ 242.66

DEMOLICION MANUAL DE MUROS DE PIEDRA

HERRAMIENTA Y EQUIPO

Page 51: Tabla de Costos Directos

LIMPIEZA DEL TERRENO UNIDAD M2RENDIMIENTO 70 M2/JORNADA

CONCEPTO UNIDAD CANTIDAD COSTO UNITARIO IMPORTEMATERIAL M3 0 $ - $ -

CUADRILLA N° 1 JORNADA 0.014 242.66 $ 3.47

HERRAMIENTA Y EQUIPO M3 0 $ - $ -

TOTAL $ 3.47

CLAVEUNIDAD m3RENDIMIENTO 4.31 m3/jornadaDESTAJO

CONCEPTO UNIDAD CANTIDAD COSTO UNITARIO IMPORTEMATERIAL M3 0 $ - $ -

CUADRILLA N° 1 JORNADA 0.23 242.66 $ 56.30

HERRAMIENTA Y EQUIPO M3 0 $ - $ -

TOTAL $ 56.30

CLAVEUNIDAD m3RENDIMIENTO 4 m3/jornadaDESTAJO

CONCEPTO UNIDAD CANTIDAD COSTO UNITARIO IMPORTEMATERIAL M3 0 $ - $ -

CUADRILLA N° 1 JORNADA 0.25 242.66 $ 60.67

HERRAMIENTA Y EQUIPO M3 0 $ - $ -

TOTAL $ 60.67

excavacion a mano en material tipo 1 hasta una profundidad de 1.5m incluye afine de

taludes y fondo

excavacion a mano en material clase 1 hasta una profundidad de 1.50m incluye

afine de taludes y fondo

Page 52: Tabla de Costos Directos

TRASPALEO DE 1 A 3 M

CLAVEUNIDAD m3RENDIMIENTO 10.53DESTAJO

CONCEPTO UNIDAD CANTIDAD COSTO UNITARIOMATERIAL M3 0 $ -

CUADRILLA N° 1 JORNADA 0.0950 242.66

M3 0 $ -

TOTAL

CLAVEUNIDAD m3RENDIMIENTO 18DESTAJO

CONCEPTO UNIDAD CANTIDAD COSTO UNITARIOMATERIAL M3 0 $ -

CUADRILLA N° 1 JORNADA 0.0556 242.66

M3 0 $ -

TOTAL

HERRAMIENTA Y EQUIPO

traspaleo manual en terreno clase 1 de 1 a 3 mtrs.

HERRAMIENTA Y EQUIPO

Page 53: Tabla de Costos Directos

ACARREO EN CARETILLA A 100M

CLAVEUNIDAD m3

m3/jornada RENDIMIENTO 2.74DESTAJO

IMPORTE CONCEPTO UNIDAD CANTIDAD COSTO UNITARIO $ - MATERIAL M3 0 $ - $ 23.04 CUADRILLA N° 1 JORNADA 0.3650 242.66

$ - M3 0 $ -

$ 23.04 TOTAL

CLAVEUNIDAD m3

m3/jornada RENDIMIENTO 5DESTAJO

IMPORTE CONCEPTO UNIDAD CANTIDAD COSTO UNITARIO $ - MATERIAL M3 0 $ - $ 13.48 CUADRILLA N° 1 JORNADA 0.2000 242.66

$ - M3 0 $ -

$ 13.48 TOTAL

HERRAMIENTA Y EQUIPO

ACARREO EN CARETILLA A 20M sin considerar excabacion

HERRAMIENTA Y EQUIPO

Page 54: Tabla de Costos Directos

CLAVEUNIDAD m3

m3/jornada RENDIMIENTO 6.25DESTAJO

IMPORTE CONCEPTO UNIDAD CANTIDAD COSTO UNITARIO $ - AGUA M3 0.11 $ 2.00 $ 88.56 CUADRILLA N° 1 JORNADA 0.1600 242.66

$ - ACAREO M3 1.4 $ 88.56

$ 88.56 M3 0 $ -

TOTAL

CLAVEUNIDAD m3

m3/jornada RENDIMIENTO 7DESTAJO

IMPORTE CONCEPTO UNIDAD CANTIDAD COSTO UNITARIO $ - AGUA M3 0.3 $ 2.00 $ 48.53 CUADRILLA N° 1 JORNADA 0.1429 242.66

$ - ACAREO M3 1.4 $ 48.53

$ 48.53 M3 0 $ -

TOTAL

RELLENO EN MATERIAL PRODUCTO DE LA ESCABACION

COMPACTO CON PIZÓN DE MANO

HERRAMIENTA Y EQUIPO

Relleno compacto en cimentacion, con material producto de la excavación en capas no mayores de 20cm. Humedad óptima y hasta el rebote del pisón de

madera

HERRAMIENTA Y EQUIPO

Page 55: Tabla de Costos Directos

m3/jornada

IMPORTE $ 0.22 $ 38.83

$ 123.99

$ -

$ 163.03

m3/jornada

IMPORTE $ 0.60 $ 34.67

$ 67.94

$ -

$ 103.21

Page 56: Tabla de Costos Directos

CLAVEUNIDAD m2

RENIMIENTO 30.30 m2/jornadaDESTAJO

CONCEPTO UNIDAD CANTIDAD COSTO UNITARIO IMPORTE

m3 0.051 $ 2,928.13 $ 149.33

cuadrilla N° 2jornada 0.033 $ 673.30 $ 22.22

TOTAL $ 171.56

CLAVEUNIDAD m2

RENIMIENTO 35.00 m2/jornadaDESTAJO

CONCEPTO UNIDAD CANTIDAD COSTO UNITARIO IMPORTE

m3 0.103 $ 2,920.14 $ 300.77

cuadrilla N° 2jornada 0.029 $ 673.30 $ 19.24

TOTAL $ 320.01

plantilla de concreto f'c=100 kg/cm2 echo en obra, agregado maximo de

19mm de 5 cm de espesor

concreto f'c=100, incluye acarreo

herramienta y maquinaria

plantilla de concreto f'c= 100 kg/cm2 agregado max Φ1 1/2" cemento normal

en espesor de 10 cm.

concreto f'c=100, incluye acarreo

herramienta y maquinaria

Page 57: Tabla de Costos Directos

CLAVEUNIDAD m3

RENIMIENTO 2.60 m3/jornadaDESTAJO

CONCEPTO UNIDAD CANTIDAD COSTO UNITARIO IMPORTE

Piedra brazam3 0.051 $ 2,928.13 $ 149.33

m3 0.34 $ 1,219.85 $ 414.75

cuadrilla N° 2jornada 0.38 $ 673.30 $ 258.96

TOTAL $ 823.05

CLAVEUNIDAD m3

RENIMIENTO 3.00 m3/jornadaDESTAJO

CONCEPTO UNIDAD CANTIDAD COSTO UNITARIO IMPORTE

Piedra brazam3 0.051 $ 2,928.13 $ 149.33

m3 0.34 $ 929.19 $ 315.92

cuadrilla N° 2jornada 0.33 $ 673.30 $ 224.43

TOTAL $ 689.69

CLAVEUNIDAD m3

RENIMIENTO 1.50 m3/jornadaDESTAJO

CONCEPTO UNIDAD CANTIDAD COSTO UNITARIO IMPORTE

m3 0.1 $ 3,102.49 $ 310.25 m3 0 $ - $ -

cuadrilla N° 2 jornada 0.67 $ 673.30 $ 448.87

Cimentacion de mamposteria piedra braza acentada con mortero cemento-

arena 1:3

mortero cemento-arena 1:3

herramienta y maquinaria

Cimentacion de mamposteria piedra braza acentada de sección entre 0.50 y 1.00 m3/m junteando con mortero-

arena 1:5 en proporcones no mayor de 300 lts/m3 de maposteria terminada

mortero cemento-arena 1:5

herramienta y maquinaria

concreto en cimentacion f'c= 200 kg/m2 agregado Φ1 1/2" cemento normal

concreto f'c 200 kg/m2

herramienta y maquinaria

Page 58: Tabla de Costos Directos

TOTAL $ 759.12

Page 59: Tabla de Costos Directos

claveunidad toneladarendimiento 0.21 ton/jornadadestajo

Concepto Unidad Cantidad Precio Unitario Importe

ton1.065 $ 10,862.07 $ 11,568.10

kg28 $ 15.00 $ 420.00

cuadrilla N°4 jornada 4.76 $ 697.38 $ 3,320.86 total $ 15,308.96

habilitado de acero de refuerzo R42 de 3/8" de diametro (N°3) fy=

4200 kg/cm2 en cimentación

acero de refuerzo R42- 3/8"

alambre recocido N°18

Page 60: Tabla de Costos Directos

CIMBRA PARA ZAPATA

DESCRIPCIÓN

PULG

ADA

PULG

ADA

LONGITUD cm CANTIDAD PIE TABLON DESPERDICIO FACTOR DE USO

DUELA (CIMBRA DE CONTACTO) 1 4 50 8 4.37 1.2 1/5 2.50 2.62 PT/m2

BARRROTE ( YUGOS) 2 4 70 8 12.25 1.2 1/5 2.50 7.35 PT/m2

ALTURA 0.20LADOS 0.50N° LADOS 4.00

CLAVEUNIDAD M2

RENDIMIENTOCONCEPTO UNIDADA CANTIDAD COSTO UNITARIO IMPORTE

MATERIALESDuela 1"x4" (contacto) PT 2.62 $ 25.00 $ 65.62 Barrote 2"x4" (yugos) PT 7.35 $ 37.00 $ 271.92 Clavos 3" (16 clavos) Kg 0.100 $ 15.00 $ 1.50 Disel Ltrs 0.50 $ 9.60 $ 4.80

MANO DE OBRAcarpintero obra negra/ayudante JORNADA 0.01 $ 696.58 $ 6.97 carpintero obra negra/ayudante JORNADA 0.10 $ 696.58 $ 69.66

TOTAL $ 420.46

CIMBRA PARA ZAPATA

DESCRIPCIÓN LONGITUD cm CANTIDAD PIE TABLON DESPERDICIO FACTOR DE USO

DUELA (CIMBRA DE CONTACTO) 1 4 100 8 8.75 1.2 1/5 1.25 2.62 PT/m2BARRROTE ( YUGOS) 2 4 70 8 12.25 1.2 1/5 1.25 3.67 PT/m2

FACTOR DE AREA m2

CANTIDAD DE MADERA pie-tablon

CIMBRA DE ZAPATA DE 0.50 x 0.50 X 2 m A BASE DE MADEA DE

3a

PULG

ADA

PULG

ADA

FACTOR DE AREA m2

CANTIDAD DE MADERA pie-tablon

Page 61: Tabla de Costos Directos

ALTURA 0.20LADOS 1.00N° LADOS 4.00

CLAVEUNIDAD M2

RENDIMIENTOCONCEPTO UNIDADA CANTIDAD COSTO UNITARIO IMPORTE

MATERIALESDuela 1"x4" (contacto) PT 2.62 $ 25.00 $ 65.62 Barrote 2"x4" (yugos) PT 3.67 $ 37.00 $ 135.96 Clavos 3" (16 clavos) Kg 0.100 $ 15.00 $ 1.50 Disel Ltrs 0.50 $ 9.60 $ 4.80

MANO DE OBRAcarpintero obra negra/ayudante JORNADA 0.01 $ 696.58 $ 6.97 carpintero obra negra/ayudante JORNADA 0.10 $ 696.58 $ 69.66

TOTAL $ 284.50

CIMBRA DE ZAPATA DE 1 x 1 X 2 m A BASE DE MADEA DE 3a

Page 62: Tabla de Costos Directos

CIMBRA PARA COLUMNA DE 50 cm X 50 cm

DESCRIPCIÓN LONGITUD cm CANTIDAD PIE TABLON DESPERDICIO FACTOR DE USO

DUELA (CIMBRA DE CONTACTO) 1 4 100 21 22.97 1.2 1/5 1/6 0.92 PT/m2BARRROTE ( YUGOS) 2 4 300 7 45.93 1.2 1/5 1/6 1.84 PT/m2PIES 4 4 270 4 47.24 1.2 1/5 1/6 1.89 PT/m2PLOMO 1 4 150 2 3.28 1.2 1/5 1/6 0.13 PT/m2ESTACAS 2 4 40 4 3.50 1.2 1/5 1/6 0.14 PT/m2

ALTURA 3.00LADOS 0.50N° LADOS 4

CLAVEUNIDAD M2

RENDIMIENTOCONCEPTO UNIDADA CANTIDAD COSTO UNITARIO IMPORTE

MATERIALESDuela 1"x4" (contacto) PT 0.92 $ 25.00 $ 22.97 yugo 2"x4" (yugos) PT 1.84 $ 37.00 $ 67.98 pies 4" x 4" PT 1.89 $ 37.00 $ 69.92 plomos 1" x 4" PT 0.13 $ 37.00 $ 4.86 estacas 1" x 4" PT 0.14 $ 37.00 $ 5.18 clavos 2 1/2 " 42pza kg 0.10 $ 15.00 $ 1.50 clavos 3 1/2" 40 pza kg 0.10 $ 15.00 $ 1.50 alambre kg 0.075 $ 11.63 $ 0.87 Disel lit 0.05 $ 9.60 $ 0.48

MANO DE OBRAcarpintero obra negra/ayudante JORNADA 0.01 $ 696.58 $ 6.97

PULG

ADA

PULG

ADA

FACTOR DE AREA m2

CANTIDAD DE

MADERA pie-tablon

CIMBRA DE ZAPATA DE 1 x 1 X 2 m A BASE DE MADEA DE 3a

Page 63: Tabla de Costos Directos

carpintero obra negra/ayudante JORNADA 0.10 $ 696.58 $ 69.66 TOTAL $ 251.88

CIMBRA PARA COLUMNA DE 50 cm X 50 cm

DESCRIPCIÓN

PULG

ADA

PULG

ADA

LONGITUD cm CANTIDAD PIE TABLON DESPERDICIO FACTOR DE USO

DUELA (CIMBRA DE CONTACTO) 1 4 100 16 17.50 1.2 1/5 5/8 2.62 PT/m2BARRROTE ( YUGOS) 2 4 95 4 8.31 1.2 1/5 5/8 1.25 PT/m2SEPARADORES 2 4 55 2 2.41 1.2 1/5 5/8 0.36 PT/m2MADRINAS 2 4 100 4 8.75 1.2 1/5 5/8 1.31 PT/m2PIES DERECHOS 4 4 30 8 10.50 1.2 1/5 5/8 1.57 PT/m2ARRASTRES 1 4 90 4 3.94 1.2 1/5 5/8 0.59 PT/m2ALTURA 0.80LADOS 1.00N° LADOS 2

CLAVEUNIDAD M2

RENDIMIENTOCONCEPTO UNIDADA CANTIDAD COSTO UNITARIO IMPORTE

MATERIALESDuela 1"x4" (contacto) PT 2.62 $ 25.00 $ 65.62 yugo 2"x4" (yugos) PT 1.25 $ 37.00 $ 46.13 separadores 2" x 4" PT 0.36 $ 37.00 $ 13.35 madrina 2" x 4" PT 1.31 $ 37.00 $ 48.56 pies derechs 4" x 4" PT 1.57 $ 37.00 $ 58.27 arrastre de 1" x 4" kg 0.59 $ 15.00 $ 8.86 clavos 2 1/3" 40 pza kg 0.10 $ 15.00 $ 1.50 varila 1/2 $ -

FACTOR DE AREA m2

CANTIDAD DE

MADERA pie-tablon

CIMBRA DE ZAPATA DE 1 x 1 X 2 m A BASE DE MADEA DE 3a

Page 64: Tabla de Costos Directos

Disel lit 0.05 $ 9.60 $ 0.48 MANO DE OBRA

carpintero obra negra/ayudante JORNADA 0.01 $ 696.58 $ 6.97 carpintero obra negra/ayudante JORNADA 0.10 $ 696.58 $ 69.66

TOTAL $ 319.38

Page 65: Tabla de Costos Directos

ClaveUnidad m3Rendimiento 6.17 m3/jornadaDestajo

DESCRIPCIÓN UNIDAD CANTIDAD C.UNITARIO IMPORTE

m31.04 $ 3,102.49 $ 3,226.59

agua m3 0.06 $ 2.00 $ 0.12 cuadrilla N° 6 jornada 0.1621 $ 1,401.29 $ 227.11 Equipo y Herramienta m3 1 $ 154.25 $ 154.25

total $ 3,608.07

concreto resistencia normal f´c=200 kg/m2 agregado maximo de 19 mm echo en obra, vaciado en carretilla y

bote en cimentación

concreto echo en obra f´c=200 kg/m2, agregado

19mm

Page 66: Tabla de Costos Directos

ClaveUnidad mRendimiento 10 m/jornadaDestajo

DESCRIPCIÓN UNIDAD CANTIDAD C.UNITARIO IMPORTE

m30.031 $ 3,101.10 $ 96.13

madera pino de 3ra duela pt 1.617 $ 25.00 $ 40.43 acero N° 3 R42 kg 2.22 $ 10.51 $ 23.33 acero alambron N° 2 kg 0.47 $ 10.51 $ 4.94 alambre recosido N° 18 kg 0.18 $ 15.00 $ 2.70 clavos 3" kg 0.035 $ 16.00 $ 0.56 disel litros 0.3 $ 9.60 $ 2.88 cuadrilla N° 2 jornada 0.1 $ 673.30 $ 67.33 equipo y herramienta m3 0 $ -

total $ 70.77

cadena de desplante, con concreto echo en obra f´c=150 kg/m2 agregado

maximo de 19mm, vrilla del N° 2 y 3 R 42

concreto echo en obra f´c=150 kg/m2, agregado 19mm

Page 67: Tabla de Costos Directos

ClaveUnidad m2Rendimiento 10 m2/jornadaDestajo

DESCRIPCIÓN UNIDAD CANTIDAD C.UNITARIO IMPORTE

Tabique 6 x 13 x 26 pza52.58 $ 1.00 $ 52.58

mortero c-a a 1:3 m3 0.043 $ 1,219.85 $ 52.45 agua m3 0.08 $ 2.00 $ 0.16 cuadrilla N° 2 jornada 0.1 $ 673.30 $ 67.33 herramienta y eqipo m3 $ -

total $ 119.94

muro de tabique común de 6x13x26 cm acentado con mortero cemento-

arena 1:3

Page 68: Tabla de Costos Directos

ClaveUnidad m2Rendimiento 12 m2/jornadaDestajo

DESCRIPCIÓN UNIDAD CANTIDAD C.UNITARIO IMPORTE

mortero c-a 1:3 m30.32 $ 1,219.85 $ 390.35

agua m3 0.04 $ 2.00 $ 0.08 cuadrilla N° 2 jornada 0.0833 $ 673.30 $ 56.11 equipo y herramienta m3 $ -

total $ 446.54

aplanado cemento-arena 1:3 hasta 3 metros de altura