INGENIERIA CONTROL E INSTRUMENTACION S.A. DE CV (ICISA) Página 1 de 18 TABLA DE TUBERIAS DIAMETRO DE TUBERIA 8 ESPESOR - SCHEDULE MAQUINARIA FABRICACION EN TALLER ced ced ced ced ced ced ced ced Grua Camion Equipo Grupo Maqui Compre REND. EN METROS Y PIEZAS 30 40 60 80 100 120 140 160 Telesc Plataf. Corte Soldar Relevo 375 TRASLADO TUBERIA AL TALLER 0.16 0.16 0.16 0.24 0.32 0.32 0.40 0.80 6% 6% TRAZO, CORTE Y BISELADO 1.20 1.20 1.60 2.00 2.40 3.20 4.80 6.40 50% PREPARA Y PUNTEO (BRIDA) 0.53 0.56 0.67 0.85 0.96 1.12 1.86 2.40 1% 1% 10% PREPARA Y PUNTEO (CODO) 0.67 0.70 0.83 1.07 1.20 1.40 2.33 3.00 1% 1% 10% PREPARA Y PUNTEO (TEE) 0.89 0.93 1.11 1.42 1.60 1.86 3.11 4.00 1% 1% 10% SOLDADURA RAIZ ABIERTA 2.66 2.80 3.33 4.26 4.80 5.59 9.32 11.99 100% PRECALENTAMIENTO CONTINUO 3.20 3.20 3.20 3.20 3.20 3.20 3.20 3.20 DONDE APLIQUE 100% RELEVADO DE ESFUERZOS 6.00 6.00 6.00 6.00 6.00 6.00 6.60 6.60 DONDE APLIQUE 100% RENDIMIENTOS EN TONELADAS 1.00 LONGITUD PROMEDIO DEL TRAMO A SOLDAR RENDIMIENTO TUBERIA ### ### ### ### ### ### 21.00 25.57 2.5% 2.5% 5% RENDIMIENTO SOLDADURA ### ### ### ### ### ### 92.34 107.70 100% INSTALACION Y MONTAJE EN PLANTA REND. EN METROS Y PIEZAS TUBERIA METRO (RECTA -RACK ) 1.04 1.04 1.04 1.09 1.14 1.30 1.46 2.08 4% 4% TUBERIA - METRO (SPOOL) 2.40 2.40 2.40 2.52 2.64 3.00 3.36 4.80 4% 4% PREPARA Y PUNTEO (BRIDA) 0.72 0.76 0.90 1.15 1.29 1.51 2.52 3.24 1% 1% 30% 30% PREPARA Y PUNTEO (CODO) 0.90 0.94 1.12 1.44 1.62 1.89 3.15 4.05 1% 1% 30% 30% PREPARA Y PUNTEO (TEE) 1.33 1.40 1.67 2.13 2.40 2.80 4.66 5.99 1% 1% 30% 30% SOLDADURA RAIZ ABIERTA 4.00 4.20 5.00 6.39 7.19 8.39 13.99 17.98 100% PRECALENTAMIENTO CONTINUO 3.52 3.52 3.52 3.52 3.52 3.52 3.52 3.52 DONDE APLIQUE 100% RELEVADO DE ESFUERZOS 6.60 6.60 6.60 6.60 6.60 6.60 7.26 7.26 DONDE APLIQUE 100% INSTALACION VALVULA 150 LBS. 2.40 4% 4% INSTALACION VALVULA 300 LBS. 2.80 4% 4% INSTALACION VALVULA 600 LBS. 3.20 4% 4% INSTALACION VALVULA 900 LBS. 5.60 4% 4% INSTALACION VALVULA 1500 LBS. 8.00 4% 4% INST,JGO ESPARRAGOS Y JUNTA 1.60 1.76 2.08 2.72 3.20 PESO POR METRO LINEAL ### ### ### ### ### ### 100.98 111.31 SUPERFICIE- METRO EN ( M2 ) ### CON MOVIMIENTOS DE TUBERIAS, PONER GRUA Y C SAMBLASTEO POR METRO LINEAL 0.41 4% 4% 35% PINTURA DE PRIMARIO ML. 0.12 5% PINTURA DE ACABADO ML. 0.19 5% RENDIMIENTOS EN TONELADAS 4.00 LONGITUD PROMEDIO DEL TRAMO A MONTAR RENDIMIENTO TUBERIA ### ### ### ### ### ### 28.78 33.64 2.5% 2.5% 5% RENDIMIENTO SOLDADURA ### ### ### ### ### ### 34.63 40.39 100% RENDIMIENTO SAMBLASTEO 3.36 2.91 2.33 1.92 1.63 1.37 1.23 1.11 35% RENDIMIENTO PINTURA 7.48 6.47 5.18 4.26 3.62 3.04 2.73 2.47 5%

Upload: hernandez-carlos

Post on 28-Oct-2015

389 views

Category:

Documents


31 download

TRANSCRIPT

Page 1: RENDIMIENTOS TUBERIAS.xls

INGENIERIA CONTROL E INSTRUMENTACION S.A. DE CV (ICISA)

Página 1 de 10

TABLA DE TUBERIAS

DIAMETRO DE TUBERIA 8 ESPESOR - SCHEDULE MAQUINARIA

FABRICACION EN TALLER ced ced ced ced ced ced ced ced Grua Camion Equipo Grupo Maqui Compre Equipo

REND. EN METROS Y PIEZAS 30 40 60 80 100 120 140 160 Telesc Plataf. Corte Soldar Relevo 375 Sambla

TRASLADO TUBERIA AL TALLER 0.16 0.16 0.16 0.24 0.32 0.32 0.40 0.80 6% 6%

TRAZO, CORTE Y BISELADO 1.20 1.20 1.60 2.00 2.40 3.20 4.80 6.40 50%

PREPARA Y PUNTEO (BRIDA) 0.53 0.56 0.67 0.85 0.96 1.12 1.86 2.40 1% 1% 10%

PREPARA Y PUNTEO (CODO) 0.67 0.70 0.83 1.07 1.20 1.40 2.33 3.00 1% 1% 10%

PREPARA Y PUNTEO (TEE) 0.89 0.93 1.11 1.42 1.60 1.86 3.11 4.00 1% 1% 10%

SOLDADURA RAIZ ABIERTA 2.66 2.80 3.33 4.26 4.80 5.59 9.32 11.99 100%

PRECALENTAMIENTO CONTINUO 3.20 3.20 3.20 3.20 3.20 3.20 3.20 3.20 DONDE APLIQUE 100%

RELEVADO DE ESFUERZOS 6.00 6.00 6.00 6.00 6.00 6.00 6.60 6.60 DONDE APLIQUE 100%

RENDIMIENTOS EN TONELADAS 1.00 LONGITUD PROMEDIO DEL TRAMO A SOLDAR

RENDIMIENTO TUBERIA 33.38 29.16 24.27 22.24 20.98 19.19 21.00 25.57 2.5% 2.5% 5%

RENDIMIENTO SOLDADURA 72.37 65.74 62.69 65.92 63.15 61.83 92.34 107.70 100%

INSTALACION Y MONTAJE EN PLANTAREND. EN METROS Y PIEZAS

TUBERIA METRO (RECTA -RACK ) 1.04 1.04 1.04 1.09 1.14 1.30 1.46 2.08 4% 4%

TUBERIA - METRO (SPOOL) 2.40 2.40 2.40 2.52 2.64 3.00 3.36 4.80 4% 4%

PREPARA Y PUNTEO (BRIDA) 0.72 0.76 0.90 1.15 1.29 1.51 2.52 3.24 1% 1% 30% 30%

PREPARA Y PUNTEO (CODO) 0.90 0.94 1.12 1.44 1.62 1.89 3.15 4.05 1% 1% 30% 30%

PREPARA Y PUNTEO (TEE) 1.33 1.40 1.67 2.13 2.40 2.80 4.66 5.99 1% 1% 30% 30%

SOLDADURA RAIZ ABIERTA 4.00 4.20 5.00 6.39 7.19 8.39 13.99 17.98 100%

PRECALENTAMIENTO CONTINUO 3.52 3.52 3.52 3.52 3.52 3.52 3.52 3.52 DONDE APLIQUE 100%

RELEVADO DE ESFUERZOS 6.60 6.60 6.60 6.60 6.60 6.60 7.26 7.26 DONDE APLIQUE 100%

INSTALACION VALVULA 150 LBS. 2.40 4% 4%

INSTALACION VALVULA 300 LBS. 2.80 4% 4%

INSTALACION VALVULA 600 LBS. 3.20 4% 4%

INSTALACION VALVULA 900 LBS. 5.60 4% 4%

INSTALACION VALVULA 1500 LBS. 8.00 4% 4%

INST,JGO ESPARRAGOS Y JUNTA 1.60 1.76 2.08 2.72 3.20

PESO POR METRO LINEAL 36.81 42.55 53.12 64.66 75.93 90.48 100.98 111.31

SUPERFICIE- METRO EN ( M2 ) 0.688 CON MOVIMIENTOS DE TUBERIAS, PONER GRUA Y CAMI.

SAMBLASTEO POR METRO LINEAL 0.41 4% 4% 35% 35%

PINTURA DE PRIMARIO ML. 0.12 5%

PINTURA DE ACABADO ML. 0.19 5%

RENDIMIENTOS EN TONELADAS 4.00 LONGITUD PROMEDIO DEL TRAMO A MONTAR

RENDIMIENTO TUBERIA 61.03 52.98 42.74 36.40 32.10 29.40 28.78 33.64 2.5% 2.5% 5%

RENDIMIENTO SOLDADURA 27.14 24.65 23.51 24.72 23.68 23.19 34.63 40.39 100%

RENDIMIENTO SAMBLASTEO 3.36 2.91 2.33 1.92 1.63 1.37 1.23 1.11 35% 35%

RENDIMIENTO PINTURA 7.48 6.47 5.18 4.26 3.62 3.04 2.73 2.47 5%

Page 2: RENDIMIENTOS TUBERIAS.xls

INGENIERIA CONTROL E INSTRUMENTACION S.A. DE CV (ICISA)

Página 2 de 10

TABLAS DE TUBERIAS

DIAMETRO DE TUBERIA 8 ESPESOR - SCHEDULE MAQUINARIA

ced ced ced ced ced ced ced ced Grua Camion Equipo Grupo Maqui Compre Equipo

30 40 60 80 100 120 140 160 Telesc Plataf. Corte Soldar Relevo 375 Sambla

REND. EN METROS Y PIEZAS CONSUMIBLES

GAS OXIGENO (M3/CORTE) 0.29 0.34 0.42 0.51 0.60 0.71 0.80 0.88

GAS ACETILENO (KGS/CORTE) 0.14 0.17 0.21 0.25 0.30 0.36 0.40 0.44

GAS ARGON (M3/JUNTA) 0.66

ELECTRODO RECUBIERTO 0.42 0.49 0.61 0.74 0.87 1.03 1.15 1.27

VARILLA DESNUDA 0.25

DISCO DESBASTE, POR BISEL 0.20 0.23 0.29 0.35 0.41 0.49 0.55 0.60

DISCO FINO (JUNTA/SOLDADURA) 0.33 0.38 0.48 0.58 0.68 0.81 0.91 1.00

PINTURA PRIMARIO ( LITRO X ML ) 0.15

PINTURA ACABADO ( LITRO X ML ) 0.23

REND. TONELADAS FABRICACION

GAS OXIGENO (M3/CORTE) 7.88 7.88 7.88 7.88 7.88 7.88 7.88 7.88

GAS ACETILENO (KGS/CORTE) 3.94 3.94 3.94 3.94 3.94 3.94 3.94 3.94

GAS ARGON (M3/JUNTA) 17.92

ELECTRODO RECUBIERTO 11.40 11.40 11.40 11.40 11.40 11.40 11.40 11.40

VARILLA DESNUDA 6.68

DISCO DESBASTE, POR BISEL 5.40 5.40 5.40 5.40 5.40 5.40 5.40 5.40

DISCO FINO (JUNTA/SOLDADURA) 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00

REND. EN TONELADAS MONTAJE

GAS OXIGENO (M3/CORTE) 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97

GAS ACETILENO (KGS/CORTE) 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98

GAS ARGON (M3/JUNTA) 4.48

ELECTRODO RECUBIERTO 2.85 2.85 2.85 2.85 2.85 2.85 2.85 2.85

VARILLA DESNUDA 1.67

DISCO DESBASTE POR BISEL 1.35 1.35 1.35 1.35 1.35 1.35 1.35 1.35

DISCO FINO (JUNTA/SOLDADURA) 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25

PINTURA PRIMARIO ( LITRO X ML ) 4.67 4.04 3.24 2.66 2.27 1.90 1.70 1.55

PINTURA ACABADO ( LITRO X ML ) 7.48 6.47 5.18 4.26 3.62 3.04 2.73 2.47

Page 3: RENDIMIENTOS TUBERIAS.xls

INGENIERIA CONTROL E INSTRUMENTACION S.A. DE CV (ICISA)

Página 3 de 10

TABLA DE TUBERIAS

DIAMETRO DE TUBERIA 8 ESPESOR - SCHEDULE MAQUINARIA

FABRICACION EN TALLER ced ced ced ced ced ced ced ced Grua Camion Equipo Grupo Maqui Compre Equipo

REND. EN METROS Y PIEZAS 30 40 60 80 100 120 140 160 Telesc Plataf. Corte Soldar Relevo 375 Sambla

TRASLADO TUBERIA AL TALLER 0.16 0.16 0.16 0.24 0.32 0.32 0.40 0.80 6% 6%

TRAZO, CORTE Y BISELADO 1.20 1.20 1.60 2.00 2.40 3.20 4.80 6.40 50%

PREPARA Y PUNTEO (BRIDA) 0.53 0.56 0.67 0.85 0.96 1.12 1.86 2.40 1% 1% 10%

PREPARA Y PUNTEO (CODO) 0.67 0.70 0.83 1.07 1.20 1.40 2.33 3.00 1% 1% 10%

PREPARA Y PUNTEO (TEE) 0.89 0.93 1.11 1.42 1.60 1.86 3.11 4.00 1% 1% 10%

SOLDADURA RAIZ ABIERTA 2.66 2.80 3.33 4.26 4.80 5.59 9.32 11.99 100%

PRECALENTAMIENTO CONTINUO 3.20 3.20 3.20 3.20 3.20 3.20 3.20 3.20 DONDE APLIQUE 100%

RELEVADO DE ESFUERZOS 6.00 6.00 6.00 6.00 6.00 6.00 6.60 6.60 DONDE APLIQUE 100%

RENDIMIENTOS EN TONELADAS 1.00 LONGITUD PROMEDIO DEL TRAMO A SOLDAR

RENDIMIENTO TUBERIA 33.38 29.16 24.27 22.24 20.98 19.19 21.00 25.57 2.5% 2.5% 5%

RENDIMIENTO SOLDADURA 72.37 65.74 62.69 65.92 63.15 61.83 92.34 107.70 100%

INSTALACION Y MONTAJE EN PLANTAREND. EN METROS Y PIEZAS

TUBERIA METRO (RECTA -RACK ) 1.04 1.04 1.04 1.09 1.14 1.30 1.46 2.08 4% 4%

TUBERIA - METRO (SPOOL) 2.40 2.40 2.40 2.52 2.64 3.00 3.36 4.80 4% 4%

PREPARA Y PUNTEO (BRIDA) 0.72 0.76 0.90 1.15 1.29 1.51 2.52 3.24 1% 1% 30% 30%

PREPARA Y PUNTEO (CODO) 0.90 0.94 1.12 1.44 1.62 1.89 3.15 4.05 1% 1% 30% 30%

PREPARA Y PUNTEO (TEE) 1.33 1.40 1.67 2.13 2.40 2.80 4.66 5.99 1% 1% 30% 30%

SOLDADURA RAIZ ABIERTA 4.00 4.20 5.00 6.39 7.19 8.39 13.99 17.98 100%

PRECALENTAMIENTO CONTINUO 3.52 3.52 3.52 3.52 3.52 3.52 3.52 3.52 DONDE APLIQUE 100%

RELEVADO DE ESFUERZOS 6.60 6.60 6.60 6.60 6.60 6.60 7.26 7.26 DONDE APLIQUE 100%

INSTALACION VALVULA 150 LBS. 2.40 4% 4%

INSTALACION VALVULA 300 LBS. 2.80 4% 4%

INSTALACION VALVULA 600 LBS. 3.20 4% 4%

INSTALACION VALVULA 900 LBS. 5.60 4% 4%

INSTALACION VALVULA 1500 LBS. 8.00 4% 4%

INST,JGO ESPARRAGOS Y JUNTA 1.60 1.76 2.08 2.72 3.20

PESO POR METRO LINEAL 36.81 42.55 53.12 64.66 75.93 90.48 100.98 111.31

SUPERFICIE- METRO EN ( M2 ) 0.688 CON MOVIMIENTOS DE TUBERIAS, PONER GRUA Y CAMI.

SAMBLASTEO POR METRO LINEAL 0.41 4% 4% 35% 35%

PINTURA DE PRIMARIO ML. 0.12 5%

PINTURA DE ACABADO ML. 0.19 5%

RENDIMIENTOS EN TONELADAS 4.00 LONGITUD PROMEDIO DEL TRAMO A MONTAR

RENDIMIENTO TUBERIA 61.03 52.98 42.74 36.40 32.10 29.40 28.78 33.64 2.5% 2.5% 5%

RENDIMIENTO SOLDADURA 27.14 24.65 23.51 24.72 23.68 23.19 34.63 40.39 100%

RENDIMIENTO SAMBLASTEO 3.36 2.91 2.33 1.92 1.63 1.37 1.23 1.11 35% 35%

RENDIMIENTO PINTURA 7.48 6.47 5.18 4.26 3.62 3.04 2.73 2.47 5%

Page 4: RENDIMIENTOS TUBERIAS.xls

INGENIERIA CONTROL E INSTRUMENTACION S.A. DE CV (ICISA)

Página 4 de 10

TABLAS DE TUBERIAS

DIAMETRO DE TUBERIA 8 ESPESOR - SCHEDULE MAQUINARIA

ced ced ced ced ced ced ced ced Grua Camion Equipo Grupo Maqui Compre Equipo

30 40 60 80 100 120 140 160 Telesc Plataf. Corte Soldar Relevo 375 Sambla

REND. EN METROS Y PIEZAS CONSUMIBLES

GAS OXIGENO (M3/CORTE) 0.29 0.34 0.42 0.51 0.60 0.71 0.80 0.88

GAS ACETILENO (KGS/CORTE) 0.14 0.17 0.21 0.25 0.30 0.36 0.40 0.44

GAS ARGON (M3/JUNTA) 0.66

ELECTRODO RECUBIERTO 0.42 0.49 0.61 0.74 0.87 1.03 1.15 1.27

VARILLA DESNUDA 0.25

DISCO DESBASTE, POR BISEL 0.20 0.23 0.29 0.35 0.41 0.49 0.55 0.60

DISCO FINO (JUNTA/SOLDADURA) 0.33 0.38 0.48 0.58 0.68 0.81 0.91 1.00

PINTURA PRIMARIO ( LITRO X ML ) 0.15

PINTURA ACABADO ( LITRO X ML ) 0.23

REND. TONELADAS FABRICACION

GAS OXIGENO (M3/CORTE) 7.88 7.88 7.88 7.88 7.88 7.88 7.88 7.88

GAS ACETILENO (KGS/CORTE) 3.94 3.94 3.94 3.94 3.94 3.94 3.94 3.94

GAS ARGON (M3/JUNTA) 17.92

ELECTRODO RECUBIERTO 11.40 11.40 11.40 11.40 11.40 11.40 11.40 11.40

VARILLA DESNUDA 6.68

DISCO DESBASTE, POR BISEL 5.40 5.40 5.40 5.40 5.40 5.40 5.40 5.40

DISCO FINO (JUNTA/SOLDADURA) 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00

REND. EN TONELADAS MONTAJE

GAS OXIGENO (M3/CORTE) 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97

GAS ACETILENO (KGS/CORTE) 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98

GAS ARGON (M3/JUNTA) 4.48

ELECTRODO RECUBIERTO 2.85 2.85 2.85 2.85 2.85 2.85 2.85 2.85

VARILLA DESNUDA 1.67

DISCO DESBASTE POR BISEL 1.35 1.35 1.35 1.35 1.35 1.35 1.35 1.35

DISCO FINO (JUNTA/SOLDADURA) 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25

PINTURA PRIMARIO ( LITRO X ML ) 4.67 4.04 3.24 2.66 2.27 1.90 1.70 1.55

PINTURA ACABADO ( LITRO X ML ) 7.48 6.47 5.18 4.26 3.62 3.04 2.73 2.47

Page 5: RENDIMIENTOS TUBERIAS.xls

INGENIERIA CONTROL E INSTRUMENTACION S.A. DE CV (ICISA)

Página 5 de 10

TABLA DE TUBERIAS

DIAMETRO DE TUBERIA 10 ESPESOR - SCHEDULE MAQUINARIA

FABRICACION EN TALLER ced ced ced ced ced ced ced ced Grua Camion Equipo Grupo Maqui Compre Equipo

REND. EN METROS Y PIEZAS 30 40 60 80 100 120 140 160 Telesc Plataf. Corte Soldar Relevo 375 Sambla

TRASLADO TUBERIA AL TALLER 0.20 0.20 0.20 0.30 0.40 0.40 0.50 1.00 6% 6%

TRAZO, CORTE Y BISELADO 1.50 1.50 2.00 2.50 3.00 4.00 6.00 8.00 50%

PREPARA Y PUNTEO (BRIDA) 0.67 0.70 0.83 1.07 1.20 1.40 2.33 3.00 1% 1% 10%

PREPARA Y PUNTEO (CODO) 0.83 0.87 1.04 1.33 1.50 1.75 2.91 3.75 1% 1% 10%

PREPARA Y PUNTEO (TEE) 1.11 1.17 1.39 1.78 2.00 2.33 3.89 5.00 1% 1% 10%

SOLDADURA RAIZ ABIERTA 3.33 3.50 4.16 5.33 5.99 6.99 11.66 14.99 100%

PRECALENTAMIENTO CONTINUO 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 DONDE APLIQUE 100%

RELEVADO DE ESFUERZOS 6.00 6.00 6.00 6.00 6.00 6.00 6.60 6.60 DONDE APLIQUE 100%

RENDIMIENTOS EN TONELADAS 1.00 LONGITUD PROMEDIO DEL TRAMO A SOLDAR

RENDIMIENTO TUBERIA 25.86 22.26 17.75 17.37 16.70 16.27 18.58 23.35 2.5% 2.5% 5%

RENDIMIENTO SOLDADURA 65.29 57.96 51.02 55.50 52.24 52.58 75.10 86.97 100%

INSTALACION Y MONTAJE EN PLANTAREND. EN METROS Y PIEZAS

TUBERIA METRO (RECTA -RACK ) 1.30 1.30 1.30 1.37 1.43 1.63 1.82 2.60 4% 4%

TUBERIA - METRO (SPOOL) 3.00 3.00 3.00 3.15 3.30 3.75 4.20 6.00 4% 4%

PREPARA Y PUNTEO (BRIDA) 0.90 0.94 1.12 1.44 1.62 1.89 3.15 4.05 1% 1% 30% 30%

PREPARA Y PUNTEO (CODO) 1.12 1.18 1.40 1.80 2.02 2.36 3.93 5.06 1% 1% 30% 30%

PREPARA Y PUNTEO (TEE) 1.67 1.75 2.08 2.66 3.00 3.50 5.83 7.49 1% 1% 30% 30%

SOLDADURA RAIZ ABIERTA 5.00 5.24 6.24 7.99 8.99 10.49 17.48 22.48 100%

PRECALENTAMIENTO CONTINUO 4.40 4.40 4.40 4.40 4.40 4.40 4.40 4.40 DONDE APLIQUE 100%

RELEVADO DE ESFUERZOS 6.60 6.60 6.60 6.60 6.60 6.60 7.26 7.26 DONDE APLIQUE 100%

INSTALACION VALVULA 150 LBS. 3.00 4% 4%

INSTALACION VALVULA 300 LBS. 3.50 4% 4%

INSTALACION VALVULA 600 LBS. 4.00 4% 4%

INSTALACION VALVULA 900 LBS. 7.00 4% 4%

INSTALACION VALVULA 1500 LBS. 10.00 4% 4%

INST,JGO ESPARRAGOS Y JUNTA 2.00 2.20 2.60 3.40 4.00

PESO POR METRO LINEAL 51.00 60.3 81.6 96.0 114.8 133.0 155.2 172.3

SUPERFICIE- METRO EN ( M2 ) 0.858 CON MOVIMIENTOS DE TUBERIAS, PONER GRUA Y CAMI.

SAMBLASTEO POR METRO LINEAL 0.51 4% 4% 35% 35%

PINTURA DE PRIMARIO ML. 0.15 5%

PINTURA DE ACABADO ML. 0.24 5%

RENDIMIENTOS EN TONELADAS 4.00 LONGITUD PROMEDIO DEL TRAMO A MONTAR

RENDIMIENTO TUBERIA 50.60 43.03 32.30 28.64 25.03 23.83 22.78 27.08 2.5% 2.5% 5%

RENDIMIENTO SOLDADURA 24.49 21.73 19.13 20.81 19.59 19.72 28.16 32.61 100%

RENDIMIENTO SAMBLASTEO 3.03 2.56 1.89 1.61 1.35 1.16 1.00 0.90 35% 35%

RENDIMIENTO PINTURA 6.73 5.69 4.21 3.57 2.99 2.58 2.21 1.99 5%

Page 6: RENDIMIENTOS TUBERIAS.xls

INGENIERIA CONTROL E INSTRUMENTACION S.A. DE CV (ICISA)

Página 6 de 10

TABLAS DE TUBERIAS

DIAMETRO DE TUBERIA 10 ESPESOR - SCHEDULE MAQUINARIA

ced ced ced ced ced ced ced ced Grua Camion Equipo Grupo Maqui Compre Equipo

30 40 60 80 100 120 140 160 Telesc Plataf. Corte Soldar Relevo 375 Sambla

REND. EN METROS Y PIEZAS CONSUMIBLES

GAS OXIGENO (M3/CORTE) 0.40 0.48 0.64 0.76 0.90 1.05 1.22 1.36

GAS ACETILENO (KGS/CORTE) 0.20 0.24 0.32 0.38 0.45 0.52 0.61 0.68

GAS ARGON (M3/JUNTA) 0.98

ELECTRODO RECUBIERTO 0.58 0.69 0.93 1.09 1.31 1.52 1.77 1.96

VARILLA DESNUDA 0.36

DISCO DESBASTE, POR BISEL 0.28 0.33 0.44 0.52 0.62 0.72 0.84 0.93

DISCO FINO (JUNTA/SOLDADURA) 0.46 0.54 0.73 0.86 1.03 1.20 1.40 1.55

PINTURA PRIMARIO ( LITRO X ML ) 0.19

PINTURA ACABADO ( LITRO X ML ) 0.29

REND. TONELADAS FABRICACION

GAS OXIGENO (M3/CORTE) 7.88 7.88 7.88 7.88 7.88 7.88 7.88 7.88

GAS ACETILENO (KGS/CORTE) 3.94 3.94 3.94 3.94 3.94 3.94 3.94 3.94

GAS ARGON (M3/JUNTA) 19.20

ELECTRODO RECUBIERTO 11.40 11.40 11.40 11.40 11.40 11.40 11.40 11.40

VARILLA DESNUDA 7.15

DISCO DESBASTE, POR BISEL 5.40 5.40 5.40 5.40 5.40 5.40 5.40 5.40

DISCO FINO (JUNTA/SOLDADURA) 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00

REND. EN TONELADAS MONTAJE

GAS OXIGENO (M3/CORTE) 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97

GAS ACETILENO (KGS/CORTE) 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98

GAS ARGON (M3/JUNTA) 4.80

ELECTRODO RECUBIERTO 2.85 2.85 2.85 2.85 2.85 2.85 2.85 2.85

VARILLA DESNUDA 1.79

DISCO DESBASTE POR BISEL 1.35 1.35 1.35 1.35 1.35 1.35 1.35 1.35

DISCO FINO (JUNTA/SOLDADURA) 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25

PINTURA PRIMARIO ( LITRO X ML ) 4.21 3.56 2.63 2.23 1.87 1.61 1.38 1.24

PINTURA ACABADO ( LITRO X ML ) 6.73 5.69 4.21 3.57 2.99 2.58 2.21 1.99

Page 7: RENDIMIENTOS TUBERIAS.xls

INGENIERIA CONTROL E INSTRUMENTACION S.A. DE CV (ICISA)

Página 7 de 10

TABLA DE TUBERIAS

DIAMETRO DE TUBERIA 12 ESPESOR - SCHEDULE MAQUINARIA

FABRICACION EN TALLER ced ced ced ced ced ced ced ced Grua Camion Equipo Grupo Maqui Compre Equipo

REND. EN METROS Y PIEZAS 30 40 60 80 100 120 140 160 Telesc Plataf. Corte Soldar Relevo 375 Sambla

TRASLADO TUBERIA AL TALLER 0.24 0.24 0.24 0.36 0.48 0.48 0.60 1.20 6% 6%

TRAZO, CORTE Y BISELADO 1.80 1.80 2.40 3.00 3.60 4.80 7.20 9.60 50%

PREPARA Y PUNTEO (BRIDA) 0.80 0.84 1.00 1.28 1.44 1.68 2.80 3.60 1% 1% 10%

PREPARA Y PUNTEO (CODO) 1.00 1.05 1.25 1.60 1.80 2.10 3.50 4.50 1% 1% 10%

PREPARA Y PUNTEO (TEE) 1.33 1.40 1.67 2.13 2.40 2.80 4.66 5.99 1% 1% 10%

SOLDADURA RAIZ ABIERTA 4.00 4.20 5.00 6.39 7.19 8.39 13.99 17.98 100%

PRECALENTAMIENTO CONTINUO 4.80 4.80 4.80 4.80 4.80 4.80 4.80 4.80 DONDE APLIQUE 100%

RELEVADO DE ESFUERZOS 6.00 6.00 6.00 6.00 6.00 6.00 6.60 6.60 DONDE APLIQUE 100%

RENDIMIENTOS EN TONELADAS 1.00 LONGITUD PROMEDIO DEL TRAMO A SOLDAR

RENDIMIENTO TUBERIA 21.81 20.00 15.02 14.90 14.65 14.81 18.38 23.30 2.5% 2.5% 5%

RENDIMIENTO SOLDADURA 61.3 58.03 45.83 48.44 44.96 44.87 67.18 75.27 100%

INSTALACION Y MONTAJE EN PLANTAREND. EN METROS Y PIEZAS

TUBERIA METRO (RECTA -RACK ) 1.56 1.56 1.56 1.64 1.72 1.95 2.18 3.12 4% 4%

TUBERIA - METRO (SPOOL) 3.60 3.60 3.60 3.78 3.96 4.50 5.04 7.20 4% 4%

PREPARA Y PUNTEO (BRIDA) 1.08 1.13 1.35 1.73 1.94 2.27 3.78 4.86 1% 1% 30% 30%

PREPARA Y PUNTEO (CODO) 1.35 1.42 1.69 2.16 2.43 2.83 4.72 6.07 1% 1% 30% 30%

PREPARA Y PUNTEO (TEE) 2.00 2.10 2.50 3.20 3.60 4.20 6.99 8.99 1% 1% 30% 30%

SOLDADURA RAIZ ABIERTA 5.99 6.29 7.49 9.59 10.79 12.59 20.98 26.97 100%

PRECALENTAMIENTO CONTINUO 5.27 5.27 5.27 5.27 5.27 5.27 5.27 5.27 DONDE APLIQUE 100%

RELEVADO DE ESFUERZOS 6.60 6.60 6.60 6.60 6.60 6.60 7.26 7.26 DONDE APLIQUE 100%

INSTALACION VALVULA 150 LBS. 3.60 4% 4%

INSTALACION VALVULA 300 LBS. 4.20 4% 4%

INSTALACION VALVULA 600 LBS. 4.80 4% 4%

INSTALACION VALVULA 900 LBS. 8.40 4% 4%

INSTALACION VALVULA 1500 LBS. 12.00 4% 4%

INST,JGO ESPARRAGOS Y JUNTA 2.40 2.64 3.12 4.08 4.80

PESO POR METRO LINEAL 65.23 72.3 109.0 132.0 160.0 187.0 208.2 238.9

SUPERFICIE- METRO EN ( M2 ) 1.017 CON MOVIMIENTOS DE TUBERIAS, PONER GRUA Y CAMI.

SAMBLASTEO POR METRO LINEAL 0.61 4% 4% 35% 35%

PINTURA DE PRIMARIO ML. 0.18 5%

PINTURA DE ACABADO ML. 0.28 5%

RENDIMIENTOS EN TONELADAS 4.00 LONGITUD PROMEDIO DEL TRAMO A MONTAR

RENDIMIENTO TUBERIA 44.82 40.64 27.67 24.07 20.95 20.04 20.27 23.89 2.5% 2.5% 5%

RENDIMIENTO SOLDADURA 22.97 21.76 17.18 18.16 16.86 16.83 25.19 28.23 100%

RENDIMIENTO SAMBLASTEO 2.81 2.53 1.68 1.39 1.14 0.98 0.88 0.77 35% 35%

RENDIMIENTO PINTURA 6.24 5.63 3.73 3.08 2.54 2.18 1.95 1.70 5%

Page 8: RENDIMIENTOS TUBERIAS.xls

INGENIERIA CONTROL E INSTRUMENTACION S.A. DE CV (ICISA)

Página 8 de 10

TABLAS DE TUBERIAS

DIAMETRO DE TUBERIA 12 ESPESOR - SCHEDULE MAQUINARIA

ced ced ced ced ced ced ced ced Grua Camion Equipo Grupo Maqui Compre Equipo

30 40 60 80 100 120 140 160 Telesc Plataf. Corte Soldar Relevo 375 Sambla

REND. EN METROS Y PIEZAS CONSUMIBLES

GAS OXIGENO (M3/CORTE) 0.51 0.57 0.86 1.04 1.26 1.47 1.64 1.88

GAS ACETILENO (KGS/CORTE) 0.26 0.28 0.43 0.52 0.63 0.74 0.82 0.94

GAS ARGON (M3/JUNTA) 1.35

ELECTRODO RECUBIERTO 0.74 0.82 1.24 1.50 1.82 2.13 2.37 2.72

VARILLA DESNUDA 0.50

DISCO DESBASTE, POR BISEL 0.35 0.39 0.59 0.71 0.86 1.01 1.12 1.29

DISCO FINO (JUNTA/SOLDADURA) 0.59 0.65 0.98 1.19 1.44 1.68 1.87 2.15

PINTURA PRIMARIO ( LITRO X ML ) 0.23

PINTURA ACABADO ( LITRO X ML ) 0.34

REND. TONELADAS FABRICACION

GAS OXIGENO (M3/CORTE) 7.88 7.88 7.88 7.88 7.88 7.88 7.88 7.88

GAS ACETILENO (KGS/CORTE) 3.94 3.94 3.94 3.94 3.94 3.94 3.94 3.94

GAS ARGON (M3/JUNTA) 20.64

ELECTRODO RECUBIERTO 11.40 11.40 11.40 11.40 11.40 11.40 11.40 11.40

VARILLA DESNUDA 7.69

DISCO DESBASTE, POR BISEL 5.40 5.40 5.40 5.40 5.40 5.40 5.40 5.40

DISCO FINO (JUNTA/SOLDADURA) 9.00 9.00 9.00 9.00 9.00 9.00 9.00 9.00

REND. EN TONELADAS MONTAJE

GAS OXIGENO (M3/CORTE) 1.97 1.97 1.97 1.97 1.97 1.97 1.97 1.97

GAS ACETILENO (KGS/CORTE) 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98

GAS ARGON (M3/JUNTA) 5.16

ELECTRODO RECUBIERTO 2.85 2.85 2.85 2.85 2.85 2.85 2.85 2.85

VARILLA DESNUDA 1.92

DISCO DESBASTE POR BISEL 1.35 1.35 1.35 1.35 1.35 1.35 1.35 1.35

DISCO FINO (JUNTA/SOLDADURA) 2.25 2.25 2.25 2.25 2.25 2.25 2.25 2.25

PINTURA PRIMARIO ( LITRO X ML ) 3.90 3.52 2.33 1.93 1.59 1.36 1.22 1.06

PINTURA ACABADO ( LITRO X ML ) 6.24 5.63 3.73 3.08 2.54 2.18 1.95 1.70

Page 9: RENDIMIENTOS TUBERIAS.xls

TABLAS DE TUBERIAS PARA RENDIMIENTOS EN TONELADAS.FABRICACIÓN Y MONTAJE, LAS CEDULAS CONSIDERADAS SON 40 Y ESTANDARPARA MAYORES DE 14"

Ite

m.

N.Juntas N.Juntas Fabrica. Fabrica. Montaje MontajeFabrica. Montaje H/H H/H H/H H/H

por por Tonelada Tonelada Tonelada ToneladaCada Cada Tubero Soldador Tubero Soldador

1 25.4 3.23 309.60 2.00 4.00 263.16 162.54 275.54 106.042 50.8 5.44 183.82 2.00 4.00 183.82 118.57 216.91 66.643 76.2 7.00 142.86 2.00 4.00 158.57 97.86 187.14 57.864 101.6 15.00 66.67 2.00 4.00 84.00 49.33 91.33 29.006 152.4 28.00 35.71 2.00 4.00 53.57 39.64 62.86 23.398 203.2 43.00 23.26 2.00 4.00 43.95 34.42 52.09 20.29

10 254.0 60.00 16.67 2.00 4.00 35.33 27.83 41.67 16.3812 304.8 65.00 15.38 2.00 4.00 36.92 27.08 43.69 15.9614 355.6 81.00 12.35 2.00 4.00 34.44 24.01 40.62 14.1416 406.4 93.00 10.75 2.00 4.00 34.30 23.71 40.43 13.9518 457.2 122.00 8.20 2.00 4.00 29.51 20.29 34.59 11.9520 508.0 155.00 6.45 2.00 4.00 25.81 18.65 30.39 12.0624 609.6 210.00 4.76 2.00 4.00 22.86 18.88 27.62 11.1226 660.4 252.00 3.97 2.00 4.00 21.23 18.85 24.33 10.3430 762.0 292.00 3.42 2.00 4.00 19.18 17.98 22.60 10.27

Diá

me

tro

P

ulg

ad

as

Diá

me

tro

M

ilim

etr

o

Pe

so

po

r M

etr

o

Me

tro

s

po

r T

on

ela

da

Page 10: RENDIMIENTOS TUBERIAS.xls

Electrodo Electrodo Oxigeno Acetileno Oxigeno Acetilenopor por por por por por

Tonelada Tonelada Tonelada Tonelada Tonelada ToneladaFabrica. Montaje Fabrica. Fabrica. Montaje Montaje

6.97 3.48 9.29 3.10 4.64 1.55