reporte concentrado de ensayes en campo Obra: "Construcción del Alcantarillado Sanitario (1ª Etapa)" Contrato: CAEV-APAZU-FR- Lugar: Hueyapan de Ocampo, mpio. De Hueyapan de Ocampo, Ver. Estimación FINIQUITO UBICACIÓN ENTRE POZOS HORARIOS PRESIONES DE PRUEBA VO PRELLENADO INICIO PRUEBA FIN PRUEBA INICIAL FINAL DIFERENCIA AGREGADA 1 ZARGOZA 224 223 97.00 95.80 200 6-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs 0.05 MPa 0.05 MPa 0.00 MPa x 0.75 lts ZARGOZA 223 222 35.40 34.20 200 7-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs 0.05 MPa 0.05 MPa 0.00 MPa x 0.00 lts ZARGOZA 222 221 73.85 72.65 200 8-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs 0.05 MPa 0.05 MPa 0.00 MPa x 0.00 lts ZARGOZA 221 220 88.75 87.55 200 10-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs 0.05 MPa 0.05 MPa 0.00 MPa x 0.50 lts ZARGOZA 220 218 66.52 65.32 200 11-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs 0.05 MPa 0.05 MPa 0.00 MPa x 0.00 lts 2 ZARGOZA 218 217 74.00 72.80 200 12-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs 0.05 MPa 0.05 MPa 0.00 MPa x 0.00 lts ZARGOZA 217 211 74.00 72.80 200 13-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs 0.05 MPa 0.05 MPa 0.00 MPa x 0.00 lts MATAMOROS 218 219 98.77 97.57 200 14-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs 0.05 MPa 0.05 MPa 0.00 MPa x 0.00 lts MATAMOROS 219 216 38.80 37.60 200 15-Nov-08 13.00 hrs 13.15 hrs 13.30 hrs 0.05 MPa 0.05 MPa 0.00 MPa x 0.35 lts 3 RAYON 216 213 108.88 107.68 200 17-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs 0.05 MPa 0.05 MPa 0.00 MPa x 0.80 lts RAYON 213 209 75.20 74.00 200 18-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs 0.05 MPa 0.05 MPa 0.00 MPa x 0.80 lts RAYON 209 207 72.50 71.30 200 19-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs 0.05 MPa 0.05 MPa 0.00 MPa x 0.00 lts RAYON 207 208 108.29 107.09 200 21-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs 0.05 MPa 0.05 MPa 0.00 MPa x 0.50 lts 4 CORREGIDORA 215 214 59.70 58.50 200 22-Nov-08 13.00 hrs 13.15 hrs 13.30 hrs 0.05 MPa 0.05 MPa 0.00 MPa x 0.75 lts CORREGIDORA 214 213 94.00 92.80 200 24-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs 0.05 MPa 0.05 MPa 0.00 MPa x 0.30 lts CORREGIDORA 213 212 62.33 61.13 200 25-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs 0.05 MPa 0.05 MPa 0.00 MPa x 0.00 lts CORREGIDORA 212 211 62.32 61.12 200 26-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs 0.05 MPa 0.05 MPa 0.00 MPa x 0.30 lts INDEPENDENCIA SUR 187 203 46.77 45.57 200 27-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs 0.05 MPa 0.05 MPa 0.00 MPa x 0.80 lts Probó: Verificó por la Contratante: Verificó por el Ayuntamiento: Ing. Luis Eduardo Sánchez García Arq. Raymundo Jiménez de la Garza Ing. Vicente López Hernández Arq. Fco ~ PRUEBAS DE HERMETICIDAD ~ MUESTRA No. LONG. BRUTA LONG. NETA DIÁMETRO Ø (mm) FECHA PRUEBA

Upload: ingenieroiluminado

Post on 28-Nov-2015

16 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Pruebas Hermeticidad

reporte concentrado de ensayes en campo

Obra: "Construcción del Alcantarillado Sanitario (1ª Etapa)" Contrato: CAEV-APAZU-FR-2008-30-IR

Lugar: Hueyapan de Ocampo, mpio. De Hueyapan de Ocampo, Ver. Estimación FINIQUITO

UBICACIÓNHORARIOS PRESIONES DE PRUEBA VOLÚMENES DE AGUA

PRELLENADO INICIO PRUEBA FIN PRUEBA INICIAL FINAL DIFERENCIA AGREGADA PERMITIDA DIFERENCIA

1

ZARGOZA 224 223 97.00 95.80 200 6-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.75 lts 1.21 lts 0.46 lts x

ZARGOZA 223 222 35.40 34.20 200 7-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.00 lts 0.43 lts 0.43 lts x

ZARGOZA 222 221 73.85 72.65 200 8-Nov-08 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.00 lts 0.92 lts 0.92 lts x

ZARGOZA 221 220 88.75 87.55 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.50 lts 1.10 lts 0.60 lts x

ZARGOZA 220 218 66.52 65.32 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.00 lts 0.82 lts 0.82 lts x

###

2

ZARGOZA 218 217 74.00 72.80 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.00 lts 0.92 lts 0.92 lts x

ZARGOZA 217 211 74.00 72.80 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.00 lts 0.92 lts 0.92 lts x

MATAMOROS 218 219 98.77 97.57 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.00 lts 1.23 lts 1.23 lts x

MATAMOROS 219 216 38.80 37.60 200 ### 13.00 hrs 13.15 hrs 13.30 hrs ### ### 0.00 MPa x 0.35 lts 0.47 lts 0.12 lts x

###

3

RAYON 216 213 108.88 107.68 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.80 lts 1.36 lts 0.56 lts x

RAYON 213 209 75.20 74.00 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.80 lts 0.93 lts 0.13 lts x

RAYON 209 207 72.50 71.30 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.00 lts 0.90 lts 0.90 lts x

RAYON 207 208 108.29 107.09 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.50 lts 1.35 lts 0.85 lts x

###

4

CORREGIDORA 215 214 59.70 58.50 200 ### 13.00 hrs 13.15 hrs 13.30 hrs ### ### 0.00 MPa x 0.75 lts 0.74 lts -0.01 lts x

CORREGIDORA 214 213 94.00 92.80 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.30 lts 1.17 lts 0.87 lts x

CORREGIDORA 213 212 62.33 61.13 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.00 lts 0.77 lts 0.77 lts x

CORREGIDORA 212 211 62.32 61.12 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.30 lts 0.77 lts 0.47 lts x

INDEPENDENCIA SUR 187 203 46.77 45.57 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.80 lts 0.57 lts -0.23 lts x

###

Probó: Verificó por la Contratante: Verificó por el Ayuntamiento: Vo. Bo.

Ing. Luis Eduardo Sánchez García Arq. Raymundo Jiménez de la Garza Ing. Vicente López Hernández Arq. Fco. Pio Valdes Pizzano

~ PRUEBAS DE HERMETICIDAD ~

MUESTRA No.

ENTRE POZOS

LONG. BRUTA

LONG. NETA

DIÁMETRO Ø (mm)

FECHA PRUEBA

U30
Eulalio Rios:
Page 2: Pruebas Hermeticidad

reporte concentrado de ensayes en campo

Obra: "Construcción del Alcantarillado Sanitario (1ª Etapa)" Contrato: CAEV-APAZU-FR-2008-30-IR

Lugar: Hueyapan de Ocampo, mpio. De Hueyapan de Ocampo, Ver. Estimación FINIQUITO

UBICACIÓNHORARIOS PRESIONES DE PRUEBA VOLÚMENES DE AGUA

PRELLENADO INICIO PRUEBA FIN PRUEBA INICIAL FINAL DIFERENCIA AGREGADA PERMITIDA DIFERENCIA

~ PRUEBAS DE HERMETICIDAD ~

MUESTRA No.

ENTRE POZOS

LONG. BRUTA

LONG. NETA

DIÁMETRO Ø (mm)

FECHA PRUEBA

Contratista Supervisor de Obra C.A.E.V. Director de Obras Públicas Jefe del Dpto Construccion CAEV

5

INDEPENDENCIA SUR 203 202 87.90 86.70 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.50 lts 1.09 lts 0.59 lts x

INDEPENDENCIA SUR 202 201 87.90 86.70 200 ### 13.00 hrs 13.15 hrs 13.30 hrs ### ### 0.00 MPa x 0.30 lts 1.09 lts 0.79 lts x

PROL. ZARAGOZA 201 198 113.92 112.72 200 2-Dec-08 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.00 lts 1.42 lts 1.42 lts x

PROL. ZARAGOZA 198 197 16.40 15.20 200 3-Dec-08 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.00 lts 0.19 lts 0.19 lts x

PROL. ZARAGOZA 197 196 122.34 121.14 200 4-Dec-08 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.75 lts 1.53 lts 0.78 lts x

###

6

BENITO JUAREZ 192 191 62.50 61.30 200 5-Dec-08 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.85 lts 0.77 lts -0.08 lts x

BENITO JUAREZ 191 190 72.40 71.20 200 6-Dec-08 13.00 hrs 13.15 hrs 13.30 hrs ### ### 0.00 MPa x 0.50 lts 0.90 lts 0.40 lts x

BENITO JUAREZ 190 189 72.40 71.20 200 8-Dec-08 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.30 lts 0.90 lts 0.60 lts x

BENITO JUAREZ 189 199 71.85 70.65 200 9-Dec-08 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.00 lts 0.89 lts 0.89 lts x

BENITO JUAREZ 199 198 71.85 70.65 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.25 lts 0.89 lts 0.64 lts x

###

7

BENITO JUAREZ 198 197 15.20 14.00 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.00 lts 0.18 lts 0.18 lts x

BENITO JUAREZ 197 206 97.10 95.90 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.80 lts 1.21 lts 0.41 lts x

PROL. RAYON 206 205 116.70 115.50 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 1.00 lts 1.46 lts 0.46 lts x

PRIV. ZARAGOZA 205 204 18.10 16.90 200 ### 10.00 hrs 10.15 hrs 10.30 hrs ### ### 0.00 MPa x 0.50 lts 0.21 lts -0.29 lts x

PRIV. ZARAGOZA 204 196 109.30 108.10 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.50 lts 1.36 lts 0.86 lts x

###

Probó: Verificó por la Contratante: Verificó por el Ayuntamiento: Vo. Bo.

Page 3: Pruebas Hermeticidad

reporte concentrado de ensayes en campo

Obra: "Construcción del Alcantarillado Sanitario (1ª Etapa)" Contrato: CAEV-APAZU-FR-2008-30-IR

Lugar: Hueyapan de Ocampo, mpio. De Hueyapan de Ocampo, Ver. Estimación FINIQUITO

UBICACIÓNHORARIOS PRESIONES DE PRUEBA VOLÚMENES DE AGUA

PRELLENADO INICIO PRUEBA FIN PRUEBA INICIAL FINAL DIFERENCIA AGREGADA PERMITIDA DIFERENCIA

~ PRUEBAS DE HERMETICIDAD ~

MUESTRA No.

ENTRE POZOS

LONG. BRUTA

LONG. NETA

DIÁMETRO Ø (mm)

FECHA PRUEBA

Ing. Luis Eduardo Sánchez García Arq. Raymundo Jiménez de la Garza Ing. Vicente López Hernández Arq. Fco. Pio Valdes Pizzano

Contratista Supervisor de Obra C.A.E.V. Director de Obras Públicas Jefe del Dpto Construccion CAEV

8

PRIV. ZARAGOZA 196 195 59.30 58.10 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.30 lts 0.73 lts 0.43 lts x

ZARGOZA 236 224 46.47 45.27 200 ### 10.00 hrs 10.15 hrs 10.30 hrs ### ### 0.00 MPa x 0.00 lts 0.57 lts 0.57 lts x

BENITO JUAREZ 264 192 23.57 22.37 200 ### 13.00 hrs 13.15 hrs 13.30 hrs ### ### 0.00 MPa x 0.00 lts 0.28 lts 0.28 lts x

CORREGIDORA 262 191 39.04 37.84 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.00 lts 0.48 lts 0.48 lts x

CORREGIDORA 179 193 67.08 65.88 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.50 lts 0.83 lts 0.33 lts x

CORREGIDORA 193 191 67.08 65.88 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.25 lts 0.83 lts 0.58 lts x

CORREGIDORA 226 211 64.65 63.45 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.00 lts 0.80 lts 0.80 lts x

###

9

ZARGOZA 211 210 125.65 124.45 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.25 lts 1.57 lts 1.32 lts x

ZARGOZA 210 206 21.26 20.06 200 ### 10.00 hrs 10.15 hrs 10.30 hrs ### ### 0.00 MPa x 0.00 lts 0.25 lts 0.25 lts x

MINA 207 206 108.50 107.30 200 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.50 lts 1.35 lts 0.85 lts x

MINA 188 189 68.22 67.02 300 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.50 lts 1.26 lts 0.76 lts x

###

10

MINA 189 194 117.60 116.40 300 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.00 lts 2.19 lts 2.19 lts x

INDEPENDENCIA 195 194 4.44 3.24 200 ### 10.00 hrs 10.15 hrs 10.30 hrs ### ### 0.00 MPa x 0.00 lts 0.04 lts 0.04 lts x

MINA 194 206 14.40 13.20 300 ### 13.00 hrs 13.15 hrs 13.30 hrs ### ### 0.00 MPa x 0.25 lts 0.25 lts 0.00 lts x

INDEPENDENCIA 206 280 73.70 72.50 300 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.50 lts 1.36 lts 0.86 lts x

INDEPENDENCIA 280 281 76.80 75.60 300 ### 17.00 hrs 17.15 hrs 17.30 hrs ### ### 0.00 MPa x 0.25 lts 1.42 lts 1.17 lts x

###

Probó: Verificó por la Contratante: Verificó por el Ayuntamiento: Vo. Bo.

Page 4: Pruebas Hermeticidad

reporte concentrado de ensayes en campo

Obra: "Construcción del Alcantarillado Sanitario (1ª Etapa)" Contrato: CAEV-APAZU-FR-2008-30-IR

Lugar: Hueyapan de Ocampo, mpio. De Hueyapan de Ocampo, Ver. Estimación FINIQUITO

UBICACIÓNHORARIOS PRESIONES DE PRUEBA VOLÚMENES DE AGUA

PRELLENADO INICIO PRUEBA FIN PRUEBA INICIAL FINAL DIFERENCIA AGREGADA PERMITIDA DIFERENCIA

~ PRUEBAS DE HERMETICIDAD ~

MUESTRA No.

ENTRE POZOS

LONG. BRUTA

LONG. NETA

DIÁMETRO Ø (mm)

FECHA PRUEBA

Ing. Luis Eduardo Sánchez García Arq. Raymundo Jiménez de la Garza Ing. Vicente López Hernández Arq. Fco. Pio Valdes Pizzano

Contratista Supervisor de Obra C.A.E.V. Director de Obras Públicas Jefe del Dpto Construccion CAEV

Muestra No. Tramos Probados Total de Tramos Aceptados Total de Tramos Rechazados % De Aceptación Status de la muestra Observaciones

1 5 5 0 100.00% Se acepta al 100% La sig. muestra se probará al 50%

2 4 4 0 100.00% Se acepta al 100% La sig. muestra se probará al 50%

3 4 4 0 100.00% Se acepta al 100% La sig. muestra se probará al 50%

4 5 3 2 60.00% Se repararon las juntas La sig. muestra se probará al 100%

5 5 5 0 100.00% Se acepta al 100% La sig. muestra se probará al 50%

6 5 4 1 80.00% Se repararon las juntas La sig. muestra se probará al 100%

7 5 4 1 80.00% Se repararon las juntas La sig. muestra se probará al 100%

8 7 7 0 100.00% Se acepta al 100% La sig. muestra se probará al 50%

9 4 4 0 100.00% Se acepta al 100% La sig. muestra se probará al 50%

10 5 5 0 100.00% Se acepta al 100% La sig. muestra se probará al 50%

Se Acepta

Se Rechaza

Nota:

Probó: Verificó por la Contratante: Verificó por el Ayuntamiento: Vo. Bo.

A pesar de que la norma nos permite probar el 50 % de una muestra si en la anterior el porcentaje de tramos rechazados fue menor del 5%, la Contratante en acuerdo con el Contratista y el H. Ayuntamiento de Hueyapan de Ocampo, Ver. decidieron ensayar el 10 % de los tramos instalados a fin de despejar cualquier duda que pudiera existir sobre la hermeticidad del sistema.

Page 5: Pruebas Hermeticidad

reporte concentrado de ensayes en campo

Obra: "Construcción del Alcantarillado Sanitario (1ª Etapa)" Contrato: CAEV-APAZU-FR-2008-30-IR

Lugar: Hueyapan de Ocampo, mpio. De Hueyapan de Ocampo, Ver. Estimación FINIQUITO

UBICACIÓNHORARIOS PRESIONES DE PRUEBA VOLÚMENES DE AGUA

PRELLENADO INICIO PRUEBA FIN PRUEBA INICIAL FINAL DIFERENCIA AGREGADA PERMITIDA DIFERENCIA

~ PRUEBAS DE HERMETICIDAD ~

MUESTRA No.

ENTRE POZOS

LONG. BRUTA

LONG. NETA

DIÁMETRO Ø (mm)

FECHA PRUEBA

Ing. Luis Eduardo Sánchez García Arq. Raymundo Jiménez de la Garza Ing. Vicente López Hernández Arq. Fco. Pio Valdes Pizzano

Contratista Supervisor de Obra C.A.E.V. Director de Obras Públicas Jefe del Dpto Construccion CAEV