presupuesto analitico detallado

14
Proyecto Fecha 10/01/2013 Lugar PUNO - PUNO - PUNO Part. Esp. Recurso Unidad Cantidad Precio Parcial S/. S/. 2.6.2.2.2.3 MANO DE OBRA 2.6.2.2.2.3 TOPOGRAFO hh 34.92 10.00 349.20 2.6.2.2.2.3 CAPATAZ hh 10,689.85 9.63 102,943.26 2.6.2.2.2.3 OPERARIO hh 123,438.16 8.53 1,052,927.50 2.6.2.2.2.3 OFICIAL hh 67,409.81 7.55 508,944.07 2.6.2.2.2.3 PEON hh 120,837.92 6.82 824,114.61 TOTAL 2,489,278.64 2.6.2.2.2.4 MATERIALES 2.6.2.2.2.4 ACEITE PARA MOTOR GRADO 30 gln 49.1500 48.00 2,359.20 2.6.2.2.2.4 ALAMBRE NEGRO RECOCIDO # 16 kg 112.2700 5.50 617.49 2.6.2.2.2.4 ALAMBRE NEGRO RECOCIDO # 8 kg 144.5000 5.50 794.75 2.6.2.2.2.4 CLAVOS PARA MADERA C/C 2 1/2" kg 10.8000 6.00 64.80 2.6.2.2.2.4 CLAVOS PARA MADERA C/C 2" kg 6.5200 6.00 39.12 2.6.2.2.2.4 CLAVOS PARA MADERA C/C 3" kg 1,294.2900 4.50 5,824.31 2.6.2.2.2.4 CLAVOS PARA MADERA C/C 3/4" kg 5.0100 6.00 30.06 2.6.2.2.2.4 CLAVOS PARA MADERA C/C 4" kg 272.2000 4.50 1,224.90 2.6.2.2.2.4 CLAVO NEGRO PARA CEMENTO C/C 1 1/2 " kg 112.2100 6.50 729.37 2.6.2.2.2.4 CLAVOS Fo No C/C 3" kg 26.5800 6.00 159.48 2.6.2.2.2.4 CLAVOS Fo No C/C 3/4" kg 97.8500 5.50 538.18 2.6.2.2.2.4 ALAMBRE NEGRO N°16 kg 19,714.7900 5.00 98,573.95 2.6.2.2.2.4 ALAMBRE NEGRO N°8 kg 897.1500 5.00 4,485.75 2.6.2.2.2.4 PERNO HEXAGONAL P/BRIDA DE 6" INC.TUERCA und 61.3200 2.00 122.64 2.6.2.2.2.4 PERNO HEXAGONAL P/BRIDA DE 8" INC.TUERCA und 7.1300 2.50 17.83 2.6.2.2.2.4 PERNO HEXAGONAL P/BRIDA DE 10"INC.TUERCA und 28.5200 3.00 85.56 2.6.2.2.2.4 CLAVOS PARA CALAMINA kg 7.2000 6.00 43.20 2.6.2.2.2.4 SOPORTE T/ABRAZADERA P/TUB 4" und 321.0000 15.00 4,815.00 2.6.2.2.2.4 SOPORTE T/ABRAZADERA P/TUB 2" und 487.0000 18.00 8,766.00 2.6.2.2.2.4 SOPORTE T/ABRAZADERA P/TUB 6" und 10.0000 20.00 200.00 2.6.2.2.2.4 SOPORTE T/ABRAZADERA P/TUB 3" und 93.0000 31.25 2,906.25 2.6.2.2.2.4 SOPORTE T/ABRAZADERA P/TUB 2 1/2" und 67.0000 28.00 1,876.00 2.6.2.2.2.4 PERNOS 1/4" X 2 1/2" und 2,426.5500 0.60 1,455.93 2.6.2.2.2.4 CLAVOS DE FIERRO (PROMEDIO) kg 63.7400 4.50 286.83 2.6.2.2.2.4 VOLANDAS DE PRESION 3/4" pza 1,182.6900 2.00 2,365.38 2.6.2.2.2.4 TORNILLOS DE 2" und 2,119.4600 0.50 1,059.73 2.6.2.2.2.4 VENTANA METALICA APERSIANADA INCL. SUMINISTRO Y COLOCADO und 1.0000 35.00 35.00 2.6.2.2.2.4 VENTANA MET. APERSIANADA INCL. SUMINISTRO Y COLOCADO und 14.0000 50.00 700.00 2.6.2.2.2.4 TUBO DE ACERO 1 1/2" X 5.5 MTS. pza 814.4300 38.23 31,135.66 2.6.2.2.2.4 ACERO DE REFUERZO FY=4200 GRADO 60 kg 619,476.3300 3.10 1,920,376.62 2.6.2.2.2.4 ACERO DE CONSTRUCCION LISO 1/4" kg 2,012.6200 3.40 6,842.91 2.6.2.2.2.4 FIERRO CORRUGADO D=3/8" kg 21.0000 3.20 67.20 2.6.2.2.2.4 FIERRO CORRUGADO PROMEDIO kg 49.5700 2.80 138.80 MEJORAMIENTO DE LOS SERVICIOS ACADEMICOS EN LA FORMACION BASICA, INFORMATICA Y VIRTUAL DE LAS ESCUELAS PROFESIONALES DE LA UNIVERSIDAD NACIONAL DEL ALTIPLANO MATERIALES, HERRAMIENTAS Y EQUIPOS DE OBRA PRESUPUESTO ANALITICO

Upload: rene-armando-cahui-ilasaca

Post on 26-Oct-2015

107 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: PRESUPUESTO ANALITICO DETALLADO

Proyecto

Fecha 10/01/2013Lugar PUNO - PUNO - PUNO

Part. Esp. Recurso Unidad Cantidad Precio ParcialS/. S/.

2.6.2.2.2.3 MANO DE OBRA2.6.2.2.2.3 TOPOGRAFO hh 34.92 10.00 349.20

2.6.2.2.2.3 CAPATAZ hh 10,689.85 9.63 102,943.26

2.6.2.2.2.3 OPERARIO hh 123,438.16 8.53 1,052,927.50

2.6.2.2.2.3 OFICIAL hh 67,409.81 7.55 508,944.07

2.6.2.2.2.3 PEON hh 120,837.92 6.82 824,114.61

TOTAL 2,489,278.64

2.6.2.2.2.4 MATERIALES2.6.2.2.2.4 ACEITE PARA MOTOR GRADO 30 gln 49.1500 48.00 2,359.20

2.6.2.2.2.4 ALAMBRE NEGRO RECOCIDO # 16 kg 112.2700 5.50 617.49

2.6.2.2.2.4 ALAMBRE NEGRO RECOCIDO # 8 kg 144.5000 5.50 794.75

2.6.2.2.2.4 CLAVOS PARA MADERA C/C 2 1/2" kg 10.8000 6.00 64.80

2.6.2.2.2.4 CLAVOS PARA MADERA C/C 2" kg 6.5200 6.00 39.12

2.6.2.2.2.4 CLAVOS PARA MADERA C/C 3" kg 1,294.2900 4.50 5,824.31

2.6.2.2.2.4 CLAVOS PARA MADERA C/C 3/4" kg 5.0100 6.00 30.06

2.6.2.2.2.4 CLAVOS PARA MADERA C/C 4" kg 272.2000 4.50 1,224.90

2.6.2.2.2.4 CLAVO NEGRO PARA CEMENTO C/C 1 1/2 " kg 112.2100 6.50 729.37

2.6.2.2.2.4 CLAVOS Fo No C/C 3" kg 26.5800 6.00 159.48

2.6.2.2.2.4 CLAVOS Fo No C/C 3/4" kg 97.8500 5.50 538.18

2.6.2.2.2.4 ALAMBRE NEGRO N°16 kg 19,714.7900 5.00 98,573.95

2.6.2.2.2.4 ALAMBRE NEGRO N°8 kg 897.1500 5.00 4,485.75

2.6.2.2.2.4 PERNO HEXAGONAL P/BRIDA DE 6" INC.TUERCA und 61.3200 2.00 122.64

2.6.2.2.2.4 PERNO HEXAGONAL P/BRIDA DE 8" INC.TUERCA und 7.1300 2.50 17.83

2.6.2.2.2.4 PERNO HEXAGONAL P/BRIDA DE 10"INC.TUERCA und 28.5200 3.00 85.56

2.6.2.2.2.4 CLAVOS PARA CALAMINA kg 7.2000 6.00 43.20

2.6.2.2.2.4 SOPORTE T/ABRAZADERA P/TUB 4" und 321.0000 15.00 4,815.00

2.6.2.2.2.4 SOPORTE T/ABRAZADERA P/TUB 2" und 487.0000 18.00 8,766.00

2.6.2.2.2.4 SOPORTE T/ABRAZADERA P/TUB 6" und 10.0000 20.00 200.00

2.6.2.2.2.4 SOPORTE T/ABRAZADERA P/TUB 3" und 93.0000 31.25 2,906.25

2.6.2.2.2.4 SOPORTE T/ABRAZADERA P/TUB 2 1/2" und 67.0000 28.00 1,876.00

2.6.2.2.2.4 PERNOS 1/4" X 2 1/2" und 2,426.5500 0.60 1,455.93

2.6.2.2.2.4 CLAVOS DE FIERRO (PROMEDIO) kg 63.7400 4.50 286.83

2.6.2.2.2.4 VOLANDAS DE PRESION 3/4" pza 1,182.6900 2.00 2,365.38

2.6.2.2.2.4 TORNILLOS DE 2" und 2,119.4600 0.50 1,059.73

2.6.2.2.2.4 VENTANA METALICA APERSIANADA INCL. SUMINISTRO Y COLOCADO und 1.0000 35.00 35.00

2.6.2.2.2.4 VENTANA MET. APERSIANADA INCL. SUMINISTRO Y COLOCADO und 14.0000 50.00 700.00

2.6.2.2.2.4 TUBO DE ACERO 1 1/2" X 5.5 MTS. pza 814.4300 38.23 31,135.66

2.6.2.2.2.4 ACERO DE REFUERZO FY=4200 GRADO 60 kg 619,476.3300 3.10 1,920,376.62

2.6.2.2.2.4 ACERO DE CONSTRUCCION LISO 1/4" kg 2,012.6200 3.40 6,842.91

2.6.2.2.2.4 FIERRO CORRUGADO D=3/8" kg 21.0000 3.20 67.20

2.6.2.2.2.4 FIERRO CORRUGADO PROMEDIO kg 49.5700 2.80 138.80

MEJORAMIENTO DE LOS SERVICIOS ACADEMICOS EN LA FORMACION BASICA,INFORMATICA Y VIRTUAL DE LAS ESCUELAS PROFESIONALES DE LA UNIVERSIDAD

NACIONAL DEL ALTIPLANO

MATERIALES, HERRAMIENTAS Y EQUIPOS DE OBRA

PRESUPUESTO ANALITICO

Page 2: PRESUPUESTO ANALITICO DETALLADO

Proyecto

Fecha 10/01/2013Lugar PUNO - PUNO - PUNO

Part. Esp. Recurso Unidad Cantidad Precio ParcialS/. S/.

MEJORAMIENTO DE LOS SERVICIOS ACADEMICOS EN LA FORMACION BASICA,INFORMATICA Y VIRTUAL DE LAS ESCUELAS PROFESIONALES DE LA UNIVERSIDAD

NACIONAL DEL ALTIPLANO

MATERIALES, HERRAMIENTAS Y EQUIPOS DE OBRA

PRESUPUESTO ANALITICO

2.6.2.2.2.4 ACERO CORRUGADO 0 3/8" kg 1.5000 3.20 4.80

2.6.2.2.2.4 FIERRO CORRUGADO GRADO 60 kg 393.0100 3.00 1,179.03

2.6.2.2.2.4 ARENA FINA m3 412.0500 40.00 16,482.00

2.6.2.2.2.4 ARENA GRUESA m3 969.3500 35.00 33,927.25

2.6.2.2.2.4 TIERRA NEGRA DE CHACRA O TIERRA VEGETAL m3 12.0000 40.00 480.00

2.6.2.2.2.4 MALLA ELECTROSOLDADA 2.40x6.00M COCADA 10X10CM D=4.20MM m2 10,873.7900 14.00 152,233.06

2.6.2.2.2.4PLANCHA DE ACERO GALVANIZADO 1 1/6" (INCL. SUMINISTRO Y COLOCACION) GLB 1.0000 12,500.00

12,500.00

2.6.2.2.2.4 ABRAZADERA DE FIERRO GALVANIZADO C/2 OREJAS 4" KW 29.0000 25.00 725.00

2.6.2.2.2.4 ABRAZADERA DE FIERRO GALVANIZADO C/2 OREJAS 6" KW 22.0000 15.00 330.00

2.6.2.2.2.4 ABRAZADERA DE FIERRO GALVANIZADO C/2 OREJAS 8" und 44.0000 77.10 3,392.40

2.6.2.2.2.4 PIEDRA CHANCADA DE 1/2" m3 2.3900 45.00 107.55

2.6.2.2.2.4 PIEDRA CHANCADA DE 3/4" m3 0.1400 50.00 7.00

2.6.2.2.2.4 PIEDRA GRANDE DE 8" m3 187.9200 40.00 7,516.80

2.6.2.2.2.4 GRAVA PARA FILTRO DE 10 A 100 mm m3 0.4100 120.00 49.20

2.6.2.2.2.4 PIEDRA KALA GRISS m2 707.9000 158.00 111,848.20

2.6.2.2.2.4 GRAVA SELECCIONADA PARA FILTRO DE 12 mm m3 38.2800 60.00 2,296.80

2.6.2.2.2.4 GRAVA SELECCIONADA PARA FILTRO DE 1" m3 363.4100 60.00 21,804.60

2.6.2.2.2.4 ARENA GRUESA m3 141.4900 35.00 4,952.15

2.6.2.2.2.4 MATERIAL DE RELLENO m3 13.7700 30.00 413.10

2.6.2.2.2.4 TUBERIA PVC-SAP C-7.5 DE 3" X 5 m m 62.5800 8.00 500.64

2.6.2.2.2.4 TUBERIA PVC SAP C-10 S/P DE 2 1/2" X 5 m m 104.5800 8.00 836.64

2.6.2.2.2.4 REDUCCION PVC SAP C-10 R 3/4" A 1/2" KW 3.0000 5.00 15.00

2.6.2.2.2.4 REDUCCION PVC SAP S/P DE 2½" und 1.0000 25.00 25.00

2.6.2.2.2.4 REDUCCION PVC SAP S/P DE 2" und 1.0000 20.00 20.00

2.6.2.2.2.4 REDUCCION PVC SAP S/P DE 1 1/2" und 1.0000 15.00 15.00

2.6.2.2.2.4 MATERIAL AFIRMADO m3 1,544.5100 35.00 54,057.85

2.6.2.2.2.4 CONDUCTOR DE COBRE DESNUDO 25 mm2, TEMPLE BLANDO m 150.0000 7.00 1,050.00

2.6.2.2.2.4 TAPON PVC-SAL 4" KW 32.0000 5.80 185.60

2.6.2.2.2.4 TAPON PVC-SAL 4" und 4.0000 5.80 23.20

2.6.2.2.2.4 CONECTOR DE COBRE TIPO ANDERSON, PARA VARILLA Ø 3/4" pza 6.0000 10.00 60.00

2.6.2.2.2.4 CABLE 4 mm2 NH80 m 28,388.3600 2.60 73,809.74

2.6.2.2.2.4 CABLE 6 mm2 NH80 m 2,600.0000 2.60 6,760.00

2.6.2.2.2.4 CABLE 10 mm2 NH80 m 4,300.0000 5.20 22,360.00

2.6.2.2.2.4 CABLE 16 mm2 NH80 m 2,600.0000 7.50 19,500.00

2.6.2.2.2.4 CABLE 25 mm2 NH80 m 1,300.0000 12.50 16,250.00

2.6.2.2.2.4 CABLE 35 mm2 NH80 m 200.0000 18.00 3,600.00

2.6.2.2.2.4 CABLE 50 mm2 NH80 m 2,600.0000 22.00 57,200.00

2.6.2.2.2.4 CABLE 70 mm2 NH80 m 700.0000 32.00 22,400.00

2.6.2.2.2.4 CABLE 2.5 mm2 NH80 m 7,300.0000 2.20 16,060.00

2.6.2.2.2.4 DUCTO DE VACIO 1/2" und 1.0000 20.00 20.00

2.6.2.2.2.4 INODORO TIPO RAPID JET FLUX COLOR BLANCO und 107.0000 450.00 48,150.00

2.6.2.2.2.4 TRAMPA "P" DE BRONCE DE 6" und 1.0000 10.00 10.00

2.6.2.2.2.4 LAVATORIO OVALIN SONNET COLOR BLANCO pza 93.0000 110.00 10,230.00

Page 3: PRESUPUESTO ANALITICO DETALLADO

Proyecto

Fecha 10/01/2013Lugar PUNO - PUNO - PUNO

Part. Esp. Recurso Unidad Cantidad Precio ParcialS/. S/.

MEJORAMIENTO DE LOS SERVICIOS ACADEMICOS EN LA FORMACION BASICA,INFORMATICA Y VIRTUAL DE LAS ESCUELAS PROFESIONALES DE LA UNIVERSIDAD

NACIONAL DEL ALTIPLANO

MATERIALES, HERRAMIENTAS Y EQUIPOS DE OBRA

PRESUPUESTO ANALITICO

2.6.2.2.2.4POLIESTIRENO EXPANDIDO PARA TECHO 100X34X20CM DENSIDAD 9 - 12 KG/M3 m3 1,476.0700 150.75

222,517.55

2.6.2.2.2.4URINARIO FLUXOMETRO DE DESCARGA REDUCIDA TIPO CADET COLOR BLANCO. pza 31.0000 300.00

9,300.00

2.6.2.2.2.4 JABONERA DE VOLTEO P/JABON LIQUIDO und 107.0000 50.00 5,350.00

2.6.2.2.2.4 PAPELERA C/EJE 15x15 BLANCA und 107.0000 37.50 4,012.50

2.6.2.2.2.4 LLAVE CORPORATION DE 1/2" und 4.0000 30.00 120.00

2.6.2.2.2.4 REGISTRO DE BRONCE DE 4" und 2.0000 15.00 30.00

2.6.2.2.2.4 JUNTA WATER STOP DE NEOPRENE 10 PULG. m 143.3300 25.00 3,583.25

2.6.2.2.2.4 LUMINARIA DE EMERGENCIA CON DOS FAROS DE 20 W und 209.0000 120.00 25,080.00

2.6.2.2.2.4LUMINARIA TIPO REJILLA ALUMINIZADA DE 4x28W PARA EMPOTRAR EN CIELO RASODECORATIVO DE 0.61x0.61 M

und 1,680.0000 150.00252,000.00

2.6.2.2.2.4 SPOT LIGHT P/TECHO C/PROTECTOR, LAMP. AHORR. 18W pza 1,452.0000 35.00 50,820.00

2.6.2.2.2.4 SPOT LIGHT CIRCULAR C/VIDRIO SERIGRAFIADO 2x26W und 10.0000 50.00 500.00

2.6.2.2.2.4 SPOT LIGHT CIRCULAR C/VIDRIO SERIGRAFIADO 2x18W und 273.0000 50.00 13,650.00

2.6.2.2.2.4 REFLECTOR LUXIOD EX (INTEGRADO), C/LAMP. HALOG. METAL. 150W und 44.0000 120.00 5,280.00

2.6.2.2.2.4 TABLERO MONOFASICO DE 8 POLOS und 11.0000 200.00 2,200.00

2.6.2.2.2.4 TABLERO MONOFASICO DE 12 POLOS und 18.0000 320.00 5,760.00

2.6.2.2.2.4 TABLERO TRIFASICO DE 8 POLOS und 1.0000 300.00 300.00

2.6.2.2.2.4 TABLERO TRIFASICO DE 12 POLOS und 1.0000 350.00 350.00

2.6.2.2.2.4 TABLERO TRIFASICO DE 70 POLOS und 1.0000 500.00 500.00

2.6.2.2.2.4 TABLERO TRIFASICO DE 10 POLOS und 1.0000 300.00 300.00

2.6.2.2.2.4 TABLERO MONOFASICO DE 10 POLOS und 4.0000 220.00 880.00

2.6.2.2.2.4 TABLERO MONOFASICO DE 6 POLOS und 15.0000 200.00 3,000.00

2.6.2.2.2.4 TABLERO TRIFASICO DE 60 POLOS und 4.0000 500.00 2,000.00

2.6.2.2.2.4 TABLERO TRIFASICO DE 27 POLOS und 14.0000 400.00 5,600.00

2.6.2.2.2.4 TABLERO TRIFASICO DE 20 POLOS und 1.0000 400.00 400.00

2.6.2.2.2.4 TABLERO TRIFASICO DE 16 POLOS und 28.0000 350.00 9,800.00

2.6.2.2.2.4 TABLERO MONOFASICO DE 20 POLOS und 1.0000 200.00 200.00

2.6.2.2.2.4 TOMACORRIENTE DOBLE PLANO BAKELITA C/TIERRA und 566.0000 8.00 4,528.00

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETICO DE 2x30Ax240V und 2.0000 26.00 52.00

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETICO 3X30AX220V und 1.0000 30.00 30.00

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETICO DE 3x80Ax220V und 2.0000 95.00 190.00

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETICO DE 2x10Ax220V und 119.0000 35.00 4,165.00

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETICO DE 2x15Ax220V und 128.0000 35.00 4,480.00

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETICO DE 2x30Ax220V und 56.0000 35.00 1,960.00

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETICO DE 2x25Ax220V und 73.0000 35.00 2,555.00

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETIC DE 3x25Ax220V und 32.0000 50.00 1,600.00

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETIC DE 3x30Ax220V und 110.0000 60.00 6,600.00

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETIC DE 3x35Ax220V und 26.0000 65.00 1,690.00

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETIC DE 3x50Ax220V und 2.0000 75.00 150.00

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETIC DE 3x70Ax220V und 26.0000 85.00 2,210.00

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETIC DE 3x120Ax220V und 3.0000 120.00 360.00

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETIC DE 3x150Ax220V und 26.0000 150.00 3,900.00

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETIC DE 3x250Ax220V und 3.0000 180.00 540.00

Page 4: PRESUPUESTO ANALITICO DETALLADO

Proyecto

Fecha 10/01/2013Lugar PUNO - PUNO - PUNO

Part. Esp. Recurso Unidad Cantidad Precio ParcialS/. S/.

MEJORAMIENTO DE LOS SERVICIOS ACADEMICOS EN LA FORMACION BASICA,INFORMATICA Y VIRTUAL DE LAS ESCUELAS PROFESIONALES DE LA UNIVERSIDAD

NACIONAL DEL ALTIPLANO

MATERIALES, HERRAMIENTAS Y EQUIPOS DE OBRA

PRESUPUESTO ANALITICO

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETIC DE 3x1000Ax220V und 2.0000 700.00 1,400.00

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETICO DE 3x1800x220V und 2.0000 2,100.00 4,200.00

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETIC DE 3x2200Ax220V und 1.0000 2,500.00 2,500.00

2.6.2.2.2.4 INTERRUPTOR TERMOMAGNETICO 2x20Ax220V und 120.0000 35.00 4,200.00

2.6.2.2.2.4 CAJA RECTANG GALV PESADA 4"x2 1/8"x2 1/8" und 2,714.0000 6.00 16,284.00

2.6.2.2.2.4 CAJA DE PASO GALV. 12"x12"x6" C/TAPA Y CHAPA und 556.0000 15.00 8,340.00

2.6.2.2.2.4 CAJA OCTOGONAL GALV. PESADO 4"x4"x2 1/2" und 7,032.0000 5.00 35,160.00

2.6.2.2.2.4 TAPA CIEGA CIRCULAR pza 549.0000 2.00 1,098.00

2.6.2.2.2.4 INTERRUPTOR SIMPLE pza 261.0000 6.00 1,566.00

2.6.2.2.2.4 INTERRUPTOR DOBLE pza 79.0000 7.00 553.00

2.6.2.2.2.4TOMACORRIENTE DOBLE PLANO BAKELITA C/TIERRA EMPOTRADO UNIVERSAL pza 960.0000 18.00

17,280.00

2.6.2.2.2.4 INTERRUPTOR CONMUTADOR 3 VIAS SIMPLE pza 57.0000 18.00 1,026.00

2.6.2.2.2.4 INTERRUPTOR CONMUTADOR 3 VIAS DOBLE pza 128.0000 22.00 2,816.00

2.6.2.2.2.4 CONTACTOR ELECTROMAGNETICO 2 x 30 A x 240 V, 60 HZ. und 2.0000 35.00 70.00

2.6.2.2.2.4 LADRILLO KING KONG MECANIZADO 10X14X24 und 155,710.1700 1.20 186,852.20

2.6.2.2.2.4 LADRILLO P/TECHO DE 15x30x30 CM 8 HCOS. und 773.2300 2.50 1,933.08

2.6.2.2.2.4CONCRETO PREMEZCLADO F'c=280 kg/cm2 CON CEMENTO PORTLAND TIPO I m3 4,985.2500 420.00

2,093,805.00

2.6.2.2.2.4CONCRETO PREMEZCLADO F'c=350 kg/cm2 CON CEMENTO PORTLAND TIPO I m3 133.3600 520.00

69,347.20

2.6.2.2.2.4 SERVICIO DE BOMBA PARA CONCRETO PREMEZCLADO m3 5,081.9000 38.00 193,112.20

2.6.2.2.2.4SERVICIO DE ALQUILER DE GRUA TORRE ALCANCE DE 75M DE ALTURA, CARGACRITICA DE 1.50 TON CON BRAZO EXTENDIDO A 35M

mes 12.0000 28,500.00342,000.00

2.6.2.2.2.4 CEMENTO PORTLAND TIPO I (42.5KG) BOL 476.1900 21.80 10,380.94

2.6.2.2.2.4 ADOQUIN DE CONCRETO DE 10 X 20 CM m2 50.9000 60.00 3,054.00

2.6.2.2.2.4 ADITIVO IMPERMEABILIZANTE PARA CONCRETO ARMADO gln 840.2400 35.00 29,408.40

2.6.2.2.2.4 ADITIVO IMPERMEABILIZANTE BITUMINOSO gln 83.7000 50.00 4,185.00

2.6.2.2.2.4 CERAMICO 30x30 m2 92.3300 24.00 2,215.92

2.6.2.2.2.4 CERAMICO BLANCO DE 40x40 m2 1,268.9400 26.00 32,992.44

2.6.2.2.2.4 PORCELANATO DE 60X60 CM m2 5,630.2600 53.00 298,403.78

2.6.2.2.2.4 PORCELANATO COLOR BEIGE DE 60X10 CM pza 5,399.9800 12.00 64,799.76

2.6.2.2.2.4 PORCELANATO COLOR BLANCO DE 60X10 CM pza 224.1800 12.00 2,690.16

2.6.2.2.2.4 PICAPORTE DE ALUMINIO DE 3" pza 16.7400 6.00 100.44

2.6.2.2.2.4 BISAGRAS DE FIERRO DE 1 1/2" pza 34.6800 2.00 69.36

2.6.2.2.2.4 BISAGRAS DE FIERRO DE 1 1/2" und 104.0500 2.20 228.91

2.6.2.2.2.4 BISAGRA ALUMINIZADA CAPUCHINA 4"x4" pza 1,095.0000 4.10 4,489.50

2.6.2.2.2.4 PICAPORTE DE ALUMINIO DE 3" und 50.2300 7.65 384.26

2.6.2.2.2.4 PICAPORTE DE ALUMINIO DE 6" und 142.0000 15.30 2,172.60

2.6.2.2.2.4 CERRADURA DE PERILLA DE BAÑO pza 47.0000 34.00 1,598.00

2.6.2.2.2.4 CERRADURA DOS GOLPES C/SEGURO Y LLAVE EXT. pza 249.0000 52.00 12,948.00

2.6.2.2.2.4 TORNILLO DE ENC. pza 1,182.6900 1.00 1,182.69

2.6.2.2.2.4 TORNILLO WAFER PUNTA BROCA 8x13 mll 15.4400 50.00 772.00

2.6.2.2.2.4 CLAVOS (FIJACION POLVORA) 1" cto 61.7800 7.50 463.35

2.6.2.2.2.4 TORNILLO AUTOROSCANT GYPLAC/SPB P. FINA 6 X 32 MM mll 114.2800 18.96 2,166.75

Page 5: PRESUPUESTO ANALITICO DETALLADO

Proyecto

Fecha 10/01/2013Lugar PUNO - PUNO - PUNO

Part. Esp. Recurso Unidad Cantidad Precio ParcialS/. S/.

MEJORAMIENTO DE LOS SERVICIOS ACADEMICOS EN LA FORMACION BASICA,INFORMATICA Y VIRTUAL DE LAS ESCUELAS PROFESIONALES DE LA UNIVERSIDAD

NACIONAL DEL ALTIPLANO

MATERIALES, HERRAMIENTAS Y EQUIPOS DE OBRA

PRESUPUESTO ANALITICO

2.6.2.2.2.4 MECHA NARANJA m 105.0000 0.90 94.50

2.6.2.2.2.4 MECHA O GUIA p 97.9200 1.20 117.50

2.6.2.2.2.4 FULMINANTE O DETONANTE und 32.6400 1.00 32.64

2.6.2.2.2.4 FULMINANTE und 105.0000 0.90 94.50

2.6.2.2.2.4 DINAMITA EN CARTUCHO und 32.6400 2.00 65.28

2.6.2.2.2.4 DINAMITA kg 26.2500 9.00 236.25

2.6.2.2.2.4 VIGUETA PRETENSADA PREFABRICADA FC= 350 - 400 KG/CM2 m 25,945.3500 21.00 544,852.35

2.6.2.2.2.4 CERA PARA PISO gln 116.7100 26.00 3,034.46

2.6.2.2.2.4 YESO EN BOLSAS DE 25 KG BOL 65.5300 6.00 393.18

2.6.2.2.2.4 CARBON VEGETAL kg 300.0000 5.00 1,500.00

2.6.2.2.2.4 CINTA TEFLON pza 0.3000 1.00 0.30

2.6.2.2.2.4 CANASTILLA DE 3" und 1.0000 25.00 25.00

2.6.2.2.2.4 ACOPLE RIGIDO RANURADO 2 1/2" pza 208.0000 10.00 2,080.00

2.6.2.2.2.4 ACOPLE RIGIDO RANURADO 3" pza 1.0000 12.50 12.50

2.6.2.2.2.4 ACOPLE RIGIDO RANURADO 4" pza 39.0000 15.00 585.00

2.6.2.2.2.4 ACOPLE RIGIDO RANURADO 2" pza 1.0000 1.00 1.00

2.6.2.2.2.4 CINTA TEFLON und 3.9600 1.00 3.96

2.6.2.2.2.4 SOLDADURA CELLOCORD 1/8" kg 33.4900 9.50 318.16

2.6.2.2.2.4 SOLDADURA OVERCORD 1/8" kg 377.9400 9.50 3,590.43

2.6.2.2.2.4 SOLDADURA CELLOCORD PUNTO AZUL 1/8" kg 54.4300 13.50 734.81

2.6.2.2.2.4 PLACA DE YESO CARTON ESTANDAR RH DE 1/2" 1.22X2.44 M pza 2,162.1300 40.00 86,485.20

2.6.2.2.2.4BALDOSA ACUSTICA 61 x 61 CM, E = 5/8" INCL. PERFILERIA DE FIJACION, ACCESORIOSE INSTALACION

m2 10,301.8900 48.00494,490.72

2.6.2.2.2.4 BARRENO 5' X 1/8" und 0.7100 780.00 553.80

2.6.2.2.2.4 VARILLA DE COBRE D=3/4" x L=2.40m und 6.0000 250.00 1,500.00

2.6.2.2.2.4 IMPERMEABILIZANTE gln 16.7000 20.00 334.00

2.6.2.2.2.4 PORCELANA kg 299.9400 5.20 1,559.69

2.6.2.2.2.4 PASTA PARA JUNTA HANILTON'S kg 185.3300 16.14 2,991.23

2.6.2.2.2.4 ADITIVO DESMOLDEADOR DE ENCOFRADOS gln 790.8200 35.00 27,678.70

2.6.2.2.2.4 PINTURA BARNIZ gln 34.4100 45.00 1,548.45

2.6.2.2.2.4CRISTAL TEMPLADO TRANSPARENTE SIST. MODUGLASS DE 6mm (INC. ACCESORIOS EINSTALACION SEGUN DETALLE DE PLANO)

p2 15,541.2300 27.00419,613.21

2.6.2.2.2.4CRISTAL TEMPLADO TRANSPARENTE SIST. MODUGLASS DE 10mm (INC. ACCESORIOSE INSTALACION SEGUN PLANO DE DETALLE)

p2 2,053.7400 42.0086,257.08

2.6.2.2.2.4 FORMICA NOGAL 4' x 8' pln 241.2800 58.00 13,994.24

2.6.2.2.2.4 RELE TEMPORIZADOR, 16(4) A, 240 V, 60 HZ. und 2.0000 50.00 100.00

2.6.2.2.2.4 CENTRAL DE CONTROL REMOTO und 1.0000 250.00 250.00

2.6.2.2.2.4 MODULO DE CONTROL ARRANQUE Y PARADA und 1.0000 300.00 300.00

2.6.2.2.2.4 LAVADERO ACERO INOXIDABLE 20" x 39" C/ACCESORIOS und 2.0000 150.00 300.00

2.6.2.2.2.4 PEGAMENTO PARA PVC AGUA FORDUIT gln 72.0600 26.00 1,873.56

2.6.2.2.2.4 PEGAMENTO PLASTICO P/PVC gln 18.4100 32.00 589.12

2.6.2.2.2.4 PEGAMENTO PARA PVC 1/4 GLN und 0.0100 8.00 0.08

2.6.2.2.2.4 PEGAMENTO PARA PVC L 8.6700 6.00 52.02

2.6.2.2.2.4 CINTA AISLANTE ELECTRICA 3M-1700 rll 315.9000 5.00 1,579.50

2.6.2.2.2.4 CINTA PARA JUNTA ROLLO X 150 m. rll 30.8900 5.00 154.45

Page 6: PRESUPUESTO ANALITICO DETALLADO

Proyecto

Fecha 10/01/2013Lugar PUNO - PUNO - PUNO

Part. Esp. Recurso Unidad Cantidad Precio ParcialS/. S/.

MEJORAMIENTO DE LOS SERVICIOS ACADEMICOS EN LA FORMACION BASICA,INFORMATICA Y VIRTUAL DE LAS ESCUELAS PROFESIONALES DE LA UNIVERSIDAD

NACIONAL DEL ALTIPLANO

MATERIALES, HERRAMIENTAS Y EQUIPOS DE OBRA

PRESUPUESTO ANALITICO

2.6.2.2.2.4 FRAGUA kg 154.2700 5.40 833.06

2.6.2.2.2.4 OCRE kg 162.1100 10.00 1,621.10

2.6.2.2.2.4 OCRE ROJO kg 25.4500 10.00 254.50

2.6.2.2.2.4 NIVEL DIA 0.5000 5.00 2.50

2.6.2.2.2.4 TEODOLITO DIA 0.5000 10.00 5.00

2.6.2.2.2.4 MANOMETRO 0 A 300 LB/PUL2 I/ACCESORIOS und 3.0000 35.00 105.00

2.6.2.2.2.4 MACROMEDIDOR DE AGUA POTABLE C/ROSCA Q 3" und 1.0000 1,500.00 1,500.00

2.6.2.2.2.4 GABINETE CONTRAINCENDIO INCL/ACCESORIOS und 15.0000 250.00 3,750.00

2.6.2.2.2.4 THOR GEL (DOSIS DE 5 KG) DOS 6.0000 15.00 90.00

2.6.2.2.2.4 ADITIVO IMPERMEABILIZANTE gln 384.0000 40.00 15,360.00

2.6.2.2.2.4 CONEXION PARA MANGUERA und 1.0000 20.00 20.00

2.6.2.2.2.4 CORDEL m 4.4700 0.50 2.24

2.6.2.2.2.4 LIJA und 115.7300 1.60 185.17

2.6.2.2.2.4 TAPONES DE MORTERO YESO-CEMENTO und 74.6300 20.00 1,492.60

2.6.2.2.2.4 CINTA TEFLON und 151.8800 1.00 151.88

2.6.2.2.2.4 TRIPLAY LUPUNA 1.20X2.40m x 19 mm pln 226.7600 130.00 29,478.80

2.6.2.2.2.4 TAPA DE CONCRETO ARMADO 0.45 X 0.60 M und 3.0000 60.00 180.00

2.6.2.2.2.4 FLETE TRANSPORTE LOCAL kg 3,511.0800 1.50 5,266.62

2.6.2.2.2.4 LANA DE VIDRIO BLK 231.6600 85.00 19,691.10

2.6.2.2.2.4 HORMIGON m3 626.4600 25.00 15,661.50

2.6.2.2.2.4 HORMIGON (PUESTO EN OBRA) m3 0.6300 30.00 18.90

2.6.2.2.2.4 COLA SINTETICA FULLER gln 238.7500 23.80 5,682.25

2.6.2.2.2.4 LIJAR # 50 ABRALIT m 0.8500 10.00 8.50

2.6.2.2.2.4 ENERGIA ELECTRICA mes 24.0000 400.00 9,600.00

2.6.2.2.2.4 HOJA DE SIERRA pza 69.2200 4.00 276.88

2.6.2.2.2.4 LIJA DE FIERRO # 80 pza 108.7700 1.60 174.03

2.6.2.2.2.4 LIJA PARA MADERA und 837.5400 1.60 1,340.06

2.6.2.2.2.4 EMPAQUETADURA DE JEBE ENLONADO DE 6" und 4.3400 5.00 21.70

2.6.2.2.2.4 EMPAQUETADURA DE JEBE ENLONADO DE 8" und 0.5100 8.00 4.08

2.6.2.2.2.4 EMPAQUETADURA DE JEBE ENLONADO DE 10" und 2.0200 10.00 20.20

2.6.2.2.2.4 AGUA m3 53.2700 1.00 53.27

2.6.2.2.2.4 AGUA PARA LA OBRA INC. CONEXION mes 24.0000 350.00 8,400.00

2.6.2.2.2.4 TIZA BOL 1.2500 5.00 6.25

2.6.2.2.2.4 GUANO DE OVINO m3 12.0000 10.00 120.00

2.6.2.2.2.4 INSTALACION DE ASCENSOR INCLUYE M.O. Y ACCESORIOS est 4.0000 7,750.00 31,000.00

2.6.2.2.2.4 ARENADO,LABOR PINTADO TUBO FIERRO 2" m 171.2000 2.50 428.00

2.6.2.2.2.4 CANALETA PLUVIAL GALV. INCL/TRANSPORTE Y COLOCACION m 8.9300 25.00 223.25

2.6.2.2.2.4 TAPA METALICA EN BOTADERO DE BASURA und 15.0000 40.00 600.00

2.6.2.2.2.4 CERAMICO ALTO TRANSITO T-4 40 x 40 cm m2 660.0300 28.00 18,480.84

2.6.2.2.2.4 PARQUETON VETEADO m2 6,127.2000 60.00 367,632.00

2.6.2.2.2.4 MADERA NACIONAL P/ENCOFRADO-CARP p2 2,379.1100 5.00 11,895.55

2.6.2.2.2.4 MADERA TORNILLO p2 20,647.4100 5.00 103,237.05

2.6.2.2.2.4 RODON DE MADERA 3/4" x 3/4" m 2,356.3200 2.90 6,833.33

2.6.2.2.2.4 CONTRAZOCALO DE MADERA 4" x 3/4" m 2,311.4300 8.00 18,491.44

Page 7: PRESUPUESTO ANALITICO DETALLADO

Proyecto

Fecha 10/01/2013Lugar PUNO - PUNO - PUNO

Part. Esp. Recurso Unidad Cantidad Precio ParcialS/. S/.

MEJORAMIENTO DE LOS SERVICIOS ACADEMICOS EN LA FORMACION BASICA,INFORMATICA Y VIRTUAL DE LAS ESCUELAS PROFESIONALES DE LA UNIVERSIDAD

NACIONAL DEL ALTIPLANO

MATERIALES, HERRAMIENTAS Y EQUIPOS DE OBRA

PRESUPUESTO ANALITICO

2.6.2.2.2.4 MADERA AGUANO p2 13,030.6000 5.00 65,153.00

2.6.2.2.2.4 MADERA CEDRO CEPILLADO p2 771.9400 5.30 4,091.28

2.6.2.2.2.4 REGLA DE MADERA p2 14.2900 5.00 71.45

2.6.2.2.2.4 ANDAMIO DE MADERA p2 138.4200 5.00 692.10

2.6.2.2.2.4 LISTONES DE MADERA 1/2"X2"X7' pza 2,573.6000 5.65 14,540.84

2.6.2.2.2.4 LISTONES DE MADERA 1 1/4"X4"X7' pza 1,286.8000 9.35 12,031.58

2.6.2.2.2.4 LISTONES DE MADERA 1 3/4"X6"X7' pza 643.4000 13.85 8,911.09

2.6.2.2.2.4 MADERA TORNILLO CEPILLADA p2 1.2500 5.00 6.25

2.6.2.2.2.4 MELAMINE DE 18 MM pza 138.7400 136.98 19,004.61

2.6.2.2.2.4 MELAMINA DE 9 MM pza 2.7200 110.00 299.20

2.6.2.2.2.4 TRIPLAY DE 4'x8'x 12 mm pln 2.3900 230.00 549.70

2.6.2.2.2.4 TABLERO AGLOMERADO FINO DE MADERA 4MM pln 482.5500 52.50 25,333.88

2.6.2.2.2.4 PASAMANOS DE CEDRO CIRCULAR D=3" m 941.9100 28.00 26,373.48

2.6.2.2.2.4MUEBLES DE MELAMINA BAJO Y ALTO P/KITCHENETTE (INCL. SUMINISTRO YCOLOCADO)

GLB 1.0000 1,750.001,750.00

2.6.2.2.2.4 MADERA TORNILLO INC.CORTE P/ENCOFRADO p2 1,828.8600 4.50 8,229.87

2.6.2.2.2.4 LAVATORIO TIPO MALIBU CON PEDESTAL COLOR BLANCO und 14.0000 120.00 1,680.00

2.6.2.2.2.4ASCENSOR DE PUERTAS AUTOMATICA Y APERTURA CENTRAL C/ ACCESORIOS und 4.0000 139,514.00

558,056.00

2.6.2.2.2.4SECADOR AUTOMATICO DE MANOS C/PANEL DE HIERRO 220V/50HZ, 2200 W. und 32.0000 250.00

8,000.00

2.6.2.2.2.4 TEE DE FIERRO GALVANIZADO DE 4" KW 1.0000 30.00 30.00

2.6.2.2.2.4 UNION SIMPLE DE FIERRO GALVANIZADODE 3" KW 3.0000 35.00 105.00

2.6.2.2.2.4 UNION UNIVERSAL DE FIERRO GALVANIZADO DE 3" KW 4.0000 40.00 160.00

2.6.2.2.2.4 TARUGOS DE MADERA pza 6,434.0000 1.50 9,651.00

2.6.2.2.2.4 TAPA C/MARCO FºFº DE BUZON D=0.60m und 6.0000 220.00 1,320.00

2.6.2.2.2.4 TAPA C/MARCO FºFº DE BUZON D=0.90m und 1.0000 320.00 320.00

2.6.2.2.2.4 FIERRO ANGULAR 3/4" x 3/4" x 1/8" x 6m pza 18.8800 35.00 660.80

2.6.2.2.2.4 TEE REDUCCION RANURADO 4"x4"x2 1/2" pza 16.0000 60.00 960.00

2.6.2.2.2.4 PLATINA DE FIERRO 1/8" x 3/4" x 6m pza 5.5600 15.00 83.40

2.6.2.2.2.4 PLATINA DE FIERRO 3/16" x 2" x 6m pza 155.8000 32.00 4,985.60

2.6.2.2.2.4 PLATINA DE FIERRO 3/16" x 3" x 6m pza 106.2300 40.00 4,249.20

2.6.2.2.2.4 TUBO CUADRADO 1"X1" E=2MM m 796.5400 5.41 4,309.28

2.6.2.2.2.4 PLATINA DE FIERRO 1/4" X 1 1/2" X 6 M. pza 69.0800 25.00 1,727.00

2.6.2.2.2.4 PLATINA 1" X 1/8" m 124.3800 2.30 286.07

2.6.2.2.2.4 PLATINA DE FIERRO 1/ 8" X 3"X 6 M. pza 4.6600 26.00 121.16

2.6.2.2.2.4 RIEL 65 X 25 mm. E= 0.45mm. L=3.00 m. und 1,081.0700 8.50 9,189.10

2.6.2.2.2.4 PARANTE METALICO 64 X38 mm.(2 1/2"X 1 5/8") E= 0.45 mm. L= 3.00 m pza 3,110.3800 10.45 32,503.47

2.6.2.2.2.4 ESQUINERO METALICO 30 X 30 X 0.40 MM X2.40 M. pza 247.1000 6.95 1,717.35

2.6.2.2.2.4 ANGULAR 1 1/4"*1 1/4"*3/16"x6M m 15.5500 6.00 93.30

2.6.2.2.2.4 ANGULAR 1" * 1 * 1/8" m 342.8600 3.83 1,313.15

2.6.2.2.2.4 ANGULAR 1 1/4"*1 1/4"*1/8"x6M pza 46.6400 24.20 1,128.69

2.6.2.2.2.4ESTRUCTURA METALICA CURVA EN FACHADA PRINCIPAL REVESTIDA CONREYNOBOND(INC ACCESORIOS E INSTALACION)

GLB 1.0000 90,000.0090,000.00

2.6.2.2.2.4 TUBERIA SCH-40 O 2½" m 186.2000 25.00 4,655.00

Page 8: PRESUPUESTO ANALITICO DETALLADO

Proyecto

Fecha 10/01/2013Lugar PUNO - PUNO - PUNO

Part. Esp. Recurso Unidad Cantidad Precio ParcialS/. S/.

MEJORAMIENTO DE LOS SERVICIOS ACADEMICOS EN LA FORMACION BASICA,INFORMATICA Y VIRTUAL DE LAS ESCUELAS PROFESIONALES DE LA UNIVERSIDAD

NACIONAL DEL ALTIPLANO

MATERIALES, HERRAMIENTAS Y EQUIPOS DE OBRA

PRESUPUESTO ANALITICO

2.6.2.2.2.4 BIPODE DE SUJECION und 2,316.5700 6.50 15,057.71

2.6.2.2.2.4 CANOPLA DE ALUMINIO DE 2" pza 689.9600 5.00 3,449.80

2.6.2.2.2.4 CANTONERA DE ALUMINIO C/ ANCLAJE 2" 11/2" 6mts var 230.4100 43.00 9,907.63

2.6.2.2.2.4 VALVULA ANGULAR C/REDUCCION HEMBRA-MACHO 2½" pza 15.0000 18.00 270.00

2.6.2.2.2.4 THINER gln 32.5200 16.00 520.32

2.6.2.2.2.4 BREA kg 166.8900 3.29 549.07

2.6.2.2.2.4 VALVULA REDUCTORA DE PRESION ROSCADA 2 1/2", ACERO INOXIDABLE pza 2.0000 75.00 150.00

2.6.2.2.2.4 PINTURA LATEX gln 128.3200 42.50 5,453.60

2.6.2.2.2.4 PINTURA ESMALTE SINTETICO gln 9.7800 30.00 293.40

2.6.2.2.2.4 PINTURA LATEX VENCELATEX gln 442.0700 42.50 18,787.98

2.6.2.2.2.4 PINTURA LATEX SUPERMATE gln 38.1200 42.50 1,620.10

2.6.2.2.2.4 PINTURA ANTICORROSIVA gln 32.9400 35.00 1,152.90

2.6.2.2.2.4 PINTURA ANTICORROSIVA EPOX-USO NAVAL gln 12.9800 50.00 649.00

2.6.2.2.2.4 LACA ACRILICA gln 7.0800 45.00 318.60

2.6.2.2.2.4 BARNIZ DD PARA PISOS CPP gln 175.0600 140.00 24,508.40

2.6.2.2.2.4 PINTURA ACRILICA 1/4 GLN und 7.0800 35.00 247.80

2.6.2.2.2.4 PINTURA ESMALTE gln 16.7100 45.00 751.95

2.6.2.2.2.4 PINTURA SELLADOR gln 32.8400 25.00 821.00

2.6.2.2.2.4 PINTURA IMPRIMANTE gln 704.1600 22.50 15,843.60

2.6.2.2.2.4 BRIDA DE ACERO P/ SOLDAR-ANCLAJES DE 4" und 1.0000 80.00 80.00

2.6.2.2.2.4 BRIDA ACERO P/SOLDAR-ROMPE AGUA DE 4" und 1.0000 80.00 80.00

2.6.2.2.2.4 BRIDA ACERO P/SOLDAR-ROMPE AGUA DE 6" und 3.0000 120.00 360.00

2.6.2.2.2.4 BRIDA ACERO P/SOLDAR-ROMPE AGUA DE 8" und 1.0000 160.00 160.00

2.6.2.2.2.4 BRIDA ACERO P/SOLDAR-ROMPE AGUA DE 10" und 1.0000 200.00 200.00

2.6.2.2.2.4 CALAMINA GALVANIZADA ( 3mm) pln 306.0000 28.00 8,568.00

2.6.2.2.2.4 BRIDA ACERO P/SOLDAR-ROMPE AGUA DE 3" und 2.0000 70.00 140.00

2.6.2.2.2.4 BRIDA ACERO P/SOLDAR-ROMPE AGUA DE 2 1/2" und 2.0000 60.00 120.00

2.6.2.2.2.4 PUERTA METALICA C/REJILLA und 1.0000 220.00 220.00

2.6.2.2.2.4PUERTA METALICA ANTIFUEGO P-5 1.20 X 2.10 (INC/ACCESORIOS E INSTALACION) und 18.0000 4,200.00

75,600.00

2.6.2.2.2.4PUERTA METALICA ANTIFUEGO P-7 2.00 X 2.10 (INC/ ACCESORIOS Y MONTAJE) und 1.0000 6,750.00

6,750.00

2.6.2.2.2.4 EQUIPO DE BOMBEO CENTRIFUGO MULTIETAPA HP=20 HDT=115MCA und 1.0000 25,000.00 25,000.00

2.6.2.2.2.4 EQUIPO DE BOMBEO CENTRIFUGO MULTIETAPA HP=12.5 HDT=90MCA und 2.0000 28,000.00 56,000.00

2.6.2.2.2.4 TEKNOPOR DE 1" x 4' x 8' pln 842.6300 12.00 10,111.56

2.6.2.2.2.4 LUMINARIA DECORATIVA 20 W und 40.0000 80.00 3,200.00

2.6.2.2.2.4ABRAZADERA METALICA ACERO INOX. CON TIRAFONDO Y DOS OREJAS TORNILLOS, 11/2"

pza 4.0000 35.00140.00

2.6.2.2.2.4ABRAZADERA METALICA ACERO INOX. CON TIRAFONDO Y DOS OREJAS TORNILLOS,2"

pza 12.0000 32.00384.00

2.6.2.2.2.4ABRAZADERA METALICA ACERO INOX. CON TIRAFONDO Y DOS OREJAS TORNILLOS, 21/2"

pza 59.0000 28.001,652.00

2.6.2.2.2.4 TUBO FIERRO GALVANIZADO Ø 1" x 6.40m und 452.6200 65.00 29,420.30

2.6.2.2.2.4 TUBO FIERRO GALVANIZADO Ø 1 1/2" x 6.40m und 5.2500 80.00 420.00

2.6.2.2.2.4 TUBO FIERRO GALVANIZADO Ø 2" x 6.40m und 264.0300 115.00 30,363.45

Page 9: PRESUPUESTO ANALITICO DETALLADO

Proyecto

Fecha 10/01/2013Lugar PUNO - PUNO - PUNO

Part. Esp. Recurso Unidad Cantidad Precio ParcialS/. S/.

MEJORAMIENTO DE LOS SERVICIOS ACADEMICOS EN LA FORMACION BASICA,INFORMATICA Y VIRTUAL DE LAS ESCUELAS PROFESIONALES DE LA UNIVERSIDAD

NACIONAL DEL ALTIPLANO

MATERIALES, HERRAMIENTAS Y EQUIPOS DE OBRA

PRESUPUESTO ANALITICO

2.6.2.2.2.4 TUBO DE F°G° Ø 3" x 5 m. pza 18.9000 180.00 3,402.00

2.6.2.2.2.4 TUBO DE F°G° Ø 4" x 5 m. pza 17.8500 220.00 3,927.00

2.6.2.2.2.4 CODO DE Fo. GALV. ISO-I DE 2 1/2" x 900 und 4.0000 35.00 140.00

2.6.2.2.2.4 CODO DE Fo. GALV. ISO-I DE 4" x 900 und 5.0000 50.00 250.00

2.6.2.2.2.4 CODO DE Fo. GALVANIZADO DE 1/2" x 90° und 4.0000 15.00 60.00

2.6.2.2.2.4 CODO DE Fo. GALVANIZADO DE 3" x 450 und 2.0000 40.00 80.00

2.6.2.2.2.4 TEE DE Fo. GALV. ISO-I DE 2 1/2" und 1.0000 40.00 40.00

2.6.2.2.2.4 TEE DE Fo. GALV. DE 3" und 2.0000 60.00 120.00

2.6.2.2.2.4 UNION SIMPLE DE Fo. GALV. DE 3" und 1.0000 50.00 50.00

2.6.2.2.2.4 UNION UNIVERSAL DE Fo. GALV. DE 1" und 2.0000 30.00 60.00

2.6.2.2.2.4 UNION UNIVERSAL DE Fo. GALV. DE 1 1/4" und 4.0000 35.00 140.00

2.6.2.2.2.4 UNION UNIVERSAL DE Fo. GALV. DE 1 1/2" und 92.0000 40.00 3,680.00

2.6.2.2.2.4 UNION UNIVERSAL DE Fo. GALV. DE 2 1/2" und 8.0000 50.00 400.00

2.6.2.2.2.4 REDUCCION DE PVC SAP C-10 DE 4" x 2" und 62.0000 5.80 359.60

2.6.2.2.2.4 REDUCCION DE PVC SAP C-10 DE 6" x 4" und 16.0000 8.00 128.00

2.6.2.2.2.4 REDUCCION CONCENTRICA ACERO INOXD MACHO-MACHO 2 1/2"-1 1/2" und 15.0000 36.00 540.00

2.6.2.2.2.4 REDUCCION CONCENTRICA ACERO INOXD MACHO-MACHO 4"-3" und 1.0000 45.00 45.00

2.6.2.2.2.4 REDUCCION DE Fo. GALV. DE 2 1/2" x 1/2" und 1.0000 40.00 40.00

2.6.2.2.2.4 NIPLE DE Fo Go DE 1/2" x 1 1/2" und 4.0000 15.00 60.00

2.6.2.2.2.4 NIPLE ADAPTADOR HD RANURA C/ROSCA MACHO 2 1/2" und 15.0000 10.00 150.00

2.6.2.2.2.4 TUB.SCHELUDE 40 DE 4"(100MM) m 84.3900 40.00 3,375.60

2.6.2.2.2.4 KIT DE DESCARGA INDIRECTA D=1" PARA INODORO und 93.0000 20.00 1,860.00

2.6.2.2.2.4 KIT DE DESCARGA INDIRECTA D=3/4" PARA URINARIO und 31.0000 18.00 558.00

2.6.2.2.2.4 UNION SIMPLE DE PVC C-10 C/R ø = 2 1/2" und 4.0000 18.00 72.00

2.6.2.2.2.4 UNION SIMPLE DE PVC C-10 C/R ø = 2" und 6.0000 15.00 90.00

2.6.2.2.2.4 UNION SIMPLE DE PVC C-10 C/R ø = 1 1/2" und 2.0000 12.00 24.00

2.6.2.2.2.4 NIPLE DE F° GALV. DE 1/2" X 2" pza 4.0000 15.00 60.00

2.6.2.2.2.4 NIPLE DE F° GALV. DE 1" X 4" pza 2.0000 35.00 70.00

2.6.2.2.2.4 NIPLE DE F° GALV. DE 3" X 6" pza 2.0000 50.00 100.00

2.6.2.2.2.4 NIPLE ROSCADO DE FºGº 2 1/2" x 6" pza 16.0000 36.00 576.00

2.6.2.2.2.4 NIPLE ROSCADO DE FºGº 1 1/2" x 4" pza 92.0000 30.00 2,760.00

2.6.2.2.2.4 NIPLE ROSCADO DE FºGº 1 1/4" x 4" pza 4.0000 25.00 100.00

2.6.2.2.2.4 NIPLE DE F° GALV. DE 4" X 6" pza 2.0000 80.00 160.00

2.6.2.2.2.4 TIRAFON 3" und 775.0100 1.00 775.01

2.6.2.2.2.4 TEE DE F°GALV.CON REDUCCION DE 3" A 2" pza 1.0000 40.00 40.00

2.6.2.2.2.4 ESCALERA TIPO MARINERA H=1.60M pza 1.0000 250.00 250.00

2.6.2.2.2.4 ESCALERA TIPO MARINERA H=2.0M pza 1.0000 350.00 350.00

2.6.2.2.2.4 ESCALERA TIPO MARINERA H=1.95M pza 1.0000 300.00 300.00

2.6.2.2.2.4 ESCALERA TIPO MARINERA H=7.0M pza 1.0000 1,250.00 1,250.00

2.6.2.2.2.4 IMPERMEABLE CON CAPUCHA TIPO CAPOTIN COLOR AMARILLO und 120.0000 50.00 6,000.00

2.6.2.2.2.4 CORTAVIENTO PARA CASCO und 120.0000 8.00 960.00

2.6.2.2.2.4 CHALECO REFLECTIVO und 100.0000 45.00 4,500.00

2.6.2.2.2.4 ZAPATOS DE SEGURIDAD PUNTA DE ACERO PAR 80.0000 75.00 6,000.00

2.6.2.2.2.4 ARNES DE SEGURIDAD CON DOBLE LINEA DE VIDA INC. pza 50.0000 350.00 17,500.00

Page 10: PRESUPUESTO ANALITICO DETALLADO

Proyecto

Fecha 10/01/2013Lugar PUNO - PUNO - PUNO

Part. Esp. Recurso Unidad Cantidad Precio ParcialS/. S/.

MEJORAMIENTO DE LOS SERVICIOS ACADEMICOS EN LA FORMACION BASICA,INFORMATICA Y VIRTUAL DE LAS ESCUELAS PROFESIONALES DE LA UNIVERSIDAD

NACIONAL DEL ALTIPLANO

MATERIALES, HERRAMIENTAS Y EQUIPOS DE OBRA

PRESUPUESTO ANALITICO

2.6.2.2.2.4 OVEROL DE DRILL COLOR AZUL und 150.0000 60.00 9,000.00

2.6.2.2.2.4 SEÑALIZACION KW 20.0000 15.00 300.00

2.6.2.2.2.4 SUMIDERO DE BRONCE 2" und 49.0000 3.00 147.00

2.6.2.2.2.4 CAJA DE REGISTRO CONCRETO PREFABRICADO 18" x 24" KW 3.0000 60.00 180.00

2.6.2.2.2.4 LUMINARIA C/DIFUSOR TRANSPARENTE 2x36 W und 84.0000 150.00 12,600.00

2.6.2.2.2.4 TUB. FIERRO FUNDIDO BB CENT. 10" 250MM m 4.0400 50.00 202.00

2.6.2.2.2.4 TUB. FIERRO FUNDIDO BB CENT. 6" m 8.6900 30.00 260.70

2.6.2.2.2.4 TUB. FIERRO FUNDIDO BB CENT. 8" m 1.0100 40.00 40.40

2.6.2.2.2.4 CODO Fo.Fo. C/BRIDA C-125 ANSI 8"x900 pza 1.0000 40.00 40.00

2.6.2.2.2.4 CODO FO.FO. B.B. DE 10" und 2.0000 60.00 120.00

2.6.2.2.2.4 CODO Fo.Fo. C/BRIDA C-125 ANSI 8"x450 pza 2.0000 50.00 100.00

2.6.2.2.2.4 TEE FO.FO. BRIDADA 6" X 6" pza 1.0000 40.00 40.00

2.6.2.2.2.4 TRANSICION Fo.Fo. C/BRIDA C-125 ANSI 3" pza 1.0000 25.00 25.00

2.6.2.2.2.4 TRANSICION Fo.Fo. BB 4" pza 1.0000 35.00 35.00

2.6.2.2.2.4 YEE FO.FO. BRIDADA DE 8" X 6" pza 2.0000 120.00 240.00

2.6.2.2.2.4 UNION FLEXIBLE TIPO DRESSER DE 8" und 4.0000 120.00 480.00

2.6.2.2.2.4 UNION FLEXIBLE TIPO DRESSER DE 10" und 2.0000 160.00 320.00

2.6.2.2.2.4 ABRAZADERA C/TUERCA TIPO "U" 6" pza 6.3500 9.00 57.15

2.6.2.2.2.4 ABRAZADERA C/TUERCA TIPO "U" 4" pza 277.1500 9.00 2,494.35

2.6.2.2.2.4 ABRAZADERA C/TUERCA TIPO "U" 2" pza 369.4500 7.00 2,586.15

2.6.2.2.2.4 TEE DE F° F° Ø 8" pza 1.0000 80.00 80.00

2.6.2.2.2.4 TUB. PVC SAP PRESION C-10 R 1/2" x 5m und 15.0300 10.50 157.82

2.6.2.2.2.4 TUB. PVC SAP PRESION C-10 R 3/4" x 5m und 16.9500 13.90 235.61

2.6.2.2.2.4 TUB. PVC SAP PRESION C-10 R 1" x 5m und 18.1100 20.50 371.26

2.6.2.2.2.4 TUB. PVC SAP PRESION C-10 R. 1 1/4"x5m und 69.0100 37.00 2,553.37

2.6.2.2.2.4 TUB. PVC SAP PRESION C-10 R 1 1/2" x 5m und 61.1700 45.00 2,752.65

2.6.2.2.2.4 TUB. PVC SAP PRESION C-10 R. 2" x 5m und 7.5600 14.00 105.84

2.6.2.2.2.4 TUB. PVC SAP PRESION P/AGUA C-10 R 1/2" m 214.8300 2.20 472.63

2.6.2.2.2.4 TUB. PVC SAP PRESION C-10 R. DE 1 1/4" m 186.0000 7.50 1,395.00

2.6.2.2.2.4 TUB. PVC SAP PRESION C-10 R. DE 1" m 62.0000 5.00 310.00

2.6.2.2.2.4 TUB. PVC SAP PRESION C-10 R. DE 2 1/2" und 5.6700 20.00 113.40

2.6.2.2.2.4 TUERCA DE SUJECION CABEZA DE COCHE pza 474.4900 1.00 474.49

2.6.2.2.2.4 REDUCCION SP PVC SAP P/AGUA 3/4" A 1/2" und 63.0000 3.50 220.50

2.6.2.2.2.4 REDUCCION SP PVC SAP P/AGUA 1" A 3/4" und 31.0000 5.00 155.00

2.6.2.2.2.4 REDUCCION SP PVC SAP P/AGUA 1" A 1/2" und 2.0000 4.00 8.00

2.6.2.2.2.4 REDUCCION SP PVC SAP P/AGUA 1 1/4" A 1" und 95.0000 6.00 570.00

2.6.2.2.2.4 REDUCCION SP PVC SAP P/AGUA 1 1/2" A 1" und 15.0000 5.00 75.00

2.6.2.2.2.4 REDUCCION SP PVC SAP P/AGUA 2" A 1 1/2" und 14.0000 8.00 112.00

2.6.2.2.2.4 REDUCCION SP PVC SAP P/AGUA 1 1/2" A 1/2" und 1.0000 6.00 6.00

2.6.2.2.2.4 REDUCCION SP PVC SAP P/AGUA 1 1/2" A 3/4" und 19.0000 6.00 114.00

2.6.2.2.2.4 REDUCCION SP PVC SAP P/AGUA 1 1/4" A 1/2" und 2.0000 8.00 16.00

2.6.2.2.2.4 REDUCCION SP PVC SAP P/AGUA 1 1/4" A 3/4" und 15.0000 8.00 120.00

2.6.2.2.2.4 REDUCCION SP PVC SAP P/AGUA 2 1/2" A 1 1/2" und 5.0000 15.00 75.00

2.6.2.2.2.4 TAPON HEMBRA SP PVC SAP P/AGUA DE 1" und 31.0000 0.80 24.80

Page 11: PRESUPUESTO ANALITICO DETALLADO

Proyecto

Fecha 10/01/2013Lugar PUNO - PUNO - PUNO

Part. Esp. Recurso Unidad Cantidad Precio ParcialS/. S/.

MEJORAMIENTO DE LOS SERVICIOS ACADEMICOS EN LA FORMACION BASICA,INFORMATICA Y VIRTUAL DE LAS ESCUELAS PROFESIONALES DE LA UNIVERSIDAD

NACIONAL DEL ALTIPLANO

MATERIALES, HERRAMIENTAS Y EQUIPOS DE OBRA

PRESUPUESTO ANALITICO

2.6.2.2.2.4 TAPON HEMBRA SP PVC SAP P/AGUA DE 1 1/4" und 93.0000 3.00 279.00

2.6.2.2.2.4 CODO DE 90°C/R PVC SAP P/AGUA DE 1/2" und 13.8400 2.50 34.60

2.6.2.2.2.4 TEE SP PVC SAP P/AGUA DE 1/2" und 30.0000 2.50 75.00

2.6.2.2.2.4 TEE SP PVC SAP P/AGUA DE 3/4" und 34.0000 4.00 136.00

2.6.2.2.2.4 TEE SP PVC SAP P/AGUA DE 1" und 47.0000 5.00 235.00

2.6.2.2.2.4 TEE SP PVC SAP P/AGUA DE 1 1/4" und 172.0000 8.00 1,376.00

2.6.2.2.2.4 TEE SP PVC SAP P/AGUA DE 1 1/2" und 52.0000 10.00 520.00

2.6.2.2.2.4 TEE SP PVC SAP P/AGUA DE 2" und 14.0000 15.00 210.00

2.6.2.2.2.4 TEE SP PVC SAP P/AGUA DE 2 1/2" und 7.0000 20.00 140.00

2.6.2.2.2.4 CODOS PVC SAP SIMPLE PRESION 3" X 45 pza 3.0000 25.00 75.00

2.6.2.2.2.4 CODOS PVC SAP SIMPLE PRESION 3" X 22.5º pza 4.0000 30.00 120.00

2.6.2.2.2.4 CODOS PVC SAP SIMPLE PRESION 3" X 90° pza 1.0000 25.00 25.00

2.6.2.2.2.4 TUB. PVC SAL P/DESAGUE DE 2" x 3 m und 190.5600 7.90 1,505.42

2.6.2.2.2.4 TUB. PVC SAL P/DESAGUE DE 3" x 3 m und 30.3800 13.00 394.94

2.6.2.2.2.4 TUB. PVC SAL P/DESAGUE DE 4" x 3 m und 145.4900 16.40 2,386.04

2.6.2.2.2.4 TUB. PVC SAL P/DESAGUE DE 6" x 5 m und 22.1200 90.00 1,990.80

2.6.2.2.2.4 TUB. PVC SAL P/DESAGUE DE 8" x 5 m und 0.3500 23.00 8.05

2.6.2.2.2.4 TUB. PVC SAL P/DESAGUE DE 6" x 3 m und 75.2100 28.00 2,105.88

2.6.2.2.2.4 TUBERIA PVC UF ISO 4422 C-7.5 Ø 110 MM m 146.5900 20.00 2,931.80

2.6.2.2.2.4 TUBERIA PVC UF ISO 4422 C-7.5 Ø 250 MM m 42.6800 35.00 1,493.80

2.6.2.2.2.4 CODO DE 90° PVC SAL DE 2" und 656.0000 1.80 1,180.80

2.6.2.2.2.4 CODO DE 90 PVC SAL DE 3" und 14.0000 4.00 56.00

2.6.2.2.2.4 CODO DE 900 PVC SAL DE 6" und 4.0000 8.00 32.00

2.6.2.2.2.4 CODO DE 45° PVC SAL DE 2" und 109.0000 3.00 327.00

2.6.2.2.2.4 CODO DE 45° PVC SAL DE 4" und 157.0000 5.50 863.50

2.6.2.2.2.4 CODO DE 90 PVC SAL DE 8" und 1.0000 12.00 12.00

2.6.2.2.2.4 TEE SANITARIA DOB C/REDUC PVC SAL 4"A2" und 2.0000 8.00 16.00

2.6.2.2.2.4 TRAMPA "P" PVC SAL DE 2" und 98.0000 5.00 490.00

2.6.2.2.2.4 TRAMPA "P" PVC SAL DE 4" und 8.0000 7.50 60.00

2.6.2.2.2.4 TRAMPA "P" PVC SAL DE 6" und 1.0000 12.00 12.00

2.6.2.2.2.4 TAPON HEMBRA PVC SAP ROSCADO 1/2" pza 95.0000 2.00 190.00

2.6.2.2.2.4 TAPON HEMBRA PVC SAP ROSCADO 3/4" pza 31.0000 2.50 77.50

2.6.2.2.2.4 TAPON HEMBRA PVC SAP ROSCADO 1" pza 93.0000 3.00 279.00

2.6.2.2.2.4 TAPON HEMBRA PVC SAP ROSCADO 4" pza 1.0000 12.00 12.00

2.6.2.2.2.4 REDUCCION PVC SAL P/DESAGUE DE 6" A 4" und 3.0000 35.00 105.00

2.6.2.2.2.4 SOMBRERO DE VENTILACION PVC SAL DE 8" und 0.0000 15.00 0.00

2.6.2.2.2.4 CODO RANURADO HD 2 1/2" x 45° pza 64.0000 10.00 640.00

2.6.2.2.2.4 CODO RANURADO HD 2 1/2" x 90° pza 32.0000 10.00 320.00

2.6.2.2.2.4 CODO RANURADO HD 4" x 45° pza 2.0000 25.00 50.00

2.6.2.2.2.4 CODO RANURADO HD 4" x 90° pza 1.0000 25.00 25.00

2.6.2.2.2.4 YEE PVC SAL DOBLE DE 4" und 45.0000 11.00 495.00

2.6.2.2.2.4 YEE PVC SAL 4" und 115.0000 8.80 1,012.00

2.6.2.2.2.4 YEE PVC SAL 2" und 22.0000 2.80 61.60

2.6.2.2.2.4 YEE PVC SAL C/REDUCCION 4" a 2" und 93.0000 5.80 539.40

Page 12: PRESUPUESTO ANALITICO DETALLADO

Proyecto

Fecha 10/01/2013Lugar PUNO - PUNO - PUNO

Part. Esp. Recurso Unidad Cantidad Precio ParcialS/. S/.

MEJORAMIENTO DE LOS SERVICIOS ACADEMICOS EN LA FORMACION BASICA,INFORMATICA Y VIRTUAL DE LAS ESCUELAS PROFESIONALES DE LA UNIVERSIDAD

NACIONAL DEL ALTIPLANO

MATERIALES, HERRAMIENTAS Y EQUIPOS DE OBRA

PRESUPUESTO ANALITICO

2.6.2.2.2.4 CONEXION A LA RED GENERAL DE DESAGUE GLB 1.0000 1,500.00 1,500.00

2.6.2.2.2.4 CODO PVC SAP 6" X 90° pza 2.1000 30.00 63.00

2.6.2.2.2.4 CODO PVC SAP 1/2" X 90° und 97.0000 1.00 97.00

2.6.2.2.2.4 CODO PVC SAP C-10 1/2" X 90° pza 142.0000 1.00 142.00

2.6.2.2.2.4 CODO PVC SAP C-10 3/4" X 90° pza 70.0000 2.00 140.00

2.6.2.2.2.4 CODO CON VENTILACION PVC 4"X2"X90° pza 97.6500 5.70 556.61

2.6.2.2.2.4 CODO PVC SAP C-10 1" X 90° pza 103.0000 1.50 154.50

2.6.2.2.2.4 CODO PVC SAP C-10 1 1/2" X 90° pza 209.0000 2.50 522.50

2.6.2.2.2.4 CODO PVC SAP C-10 1 1/4" X 90° pza 273.0000 3.50 955.50

2.6.2.2.2.4 CODO PVC SAP C-10, 2 1/2" pza 2.1000 6.00 12.60

2.6.2.2.2.4 UNION PVC SAP (AGUA) 1" pza 93.0000 2.00 186.00

2.6.2.2.2.4 UNION PVC SAP (AGUA) 3/4" pza 31.0000 2.50 77.50

2.6.2.2.2.4 TUBERIA CRIBADA PVC SAL D=4" m 0.3500 24.50 8.58

2.6.2.2.2.4 TUBO PVC SAL 4" X 3M pza 0.7000 15.00 10.50

2.6.2.2.2.4 CODOS PVC SAL 4" X 90° pza 2.1000 5.00 10.50

2.6.2.2.2.4 CODOS PVC SAL 4" X 45° pza 13.6500 5.00 68.25

2.6.2.2.2.4 TEE PVC SAL 2" X 2" pza 158.0000 2.00 316.00

2.6.2.2.2.4 TEE PVC SAL 3" X 2" pza 0.0000 3.50 0.00

2.6.2.2.2.4 TEE SANITARIA DE 4X4" PVC SAL und 126.0000 5.50 693.00

2.6.2.2.2.4 TEE SANITARIA DE 2 x 2" PVC SAL und 126.0000 2.80 352.80

2.6.2.2.2.4 TEE SANITARIA DE 3 x 3" PVC SAL und 28.0000 5.00 140.00

2.6.2.2.2.4 TEE SANITARIA DE 6X6" PVC SAL und 17.0000 12.00 204.00

2.6.2.2.2.4 TEE PVC SAL 8" X 4" und 0.0000 8.00 0.00

2.6.2.2.2.4 YEE PVC SAL DE 4" X 4" pza 7.3500 8.00 58.80

2.6.2.2.2.4 REDUCCION PVC SAL 3" A 2" pza 42.0000 2.50 105.00

2.6.2.2.2.4 REDUCCION PVC SAL 4" A 3" pza 0.0000 12.00 0.00

2.6.2.2.2.4 REDUCCION PVC 2 1/2" A 2" pza 2.0000 8.00 16.00

2.6.2.2.2.4 REDUCCION PVC SAL 1 1/2" A 1 1/4" pza 33.0000 5.00 165.00

2.6.2.2.2.4 SOMBRERO DE VENTILACION PVC SAL 6" pza 3.0000 15.00 45.00

2.6.2.2.2.4 TUBO PVC SAP (LUZ) (E/C) 3/4" X 3 M. pza 7,173.8600 5.00 35,869.30

2.6.2.2.2.4 UNION PRESION ROSCA PVC SAP 1 1/2" pza 94.0000 5.00 470.00

2.6.2.2.2.4 UNION PRESION ROSCA PVC SAP 1 1/4" pza 4.0000 7.00 28.00

2.6.2.2.2.4 UNION PRESION ROSCA PVC SAP 1" pza 2.0000 4.00 8.00

2.6.2.2.2.4 UNION PRESION ROSCA PVC SAP 2 1/2" pza 4.0000 13.00 52.00

2.6.2.2.2.4 TUBO PVC SEL (E/C) 1" x 3.00 M pza 24.0000 16.50 396.00

2.6.2.2.2.4 CURVAS PVC SEL D=1" pza 24.0000 1.50 36.00

2.6.2.2.2.4 CURVAS PVC SEL (ELECTRICO) Ø 3/4" pza 4,117.3800 0.25 1,029.35

2.6.2.2.2.4 VALVULA MARIPOSA DE 10" pza 1.0000 350.00 350.00

2.6.2.2.2.4 VALVULA COMPUERTA DE BRONCE DE 1" und 1.0000 25.00 25.00

2.6.2.2.2.4 VALVULA COMPUERTA DE BRONCE DE 1 1/4" und 2.0000 35.00 70.00

2.6.2.2.2.4 VALVULA COMPUERTA DE BRONCE DE 1 1/2" und 46.0000 40.00 1,840.00

2.6.2.2.2.4 VALVULA COMPUERTA DE BRONCE DE 2 1/2" und 1.0000 60.00 60.00

2.6.2.2.2.4 VALVULA COMPUERTA DE BRONCE DE 3" und 4.0000 120.00 480.00

2.6.2.2.2.4 VALVULA COMPUERTA DE BRONCE DE 4" und 2.0000 180.00 360.00

Page 13: PRESUPUESTO ANALITICO DETALLADO

Proyecto

Fecha 10/01/2013Lugar PUNO - PUNO - PUNO

Part. Esp. Recurso Unidad Cantidad Precio ParcialS/. S/.

MEJORAMIENTO DE LOS SERVICIOS ACADEMICOS EN LA FORMACION BASICA,INFORMATICA Y VIRTUAL DE LAS ESCUELAS PROFESIONALES DE LA UNIVERSIDAD

NACIONAL DEL ALTIPLANO

MATERIALES, HERRAMIENTAS Y EQUIPOS DE OBRA

PRESUPUESTO ANALITICO

2.6.2.2.2.4 VALVULA COMPUERTA DE BRONCE DE 2 1/2" und 5.0000 80.00 400.00

2.6.2.2.2.4 VALVULA CONTROL RETENCION 10" und 1.0000 350.00 350.00

2.6.2.2.2.4 VALVULA CONTROL RETENCION 8" und 3.0000 240.00 720.00

2.6.2.2.2.4 VALVULA FLOTADORA 3" C/BOLA DE COBRE und 1.0000 50.00 50.00

2.6.2.2.2.4 VALVULA DE ALIVIO B.B. C/PILOTO 6" und 1.0000 60.00 60.00

2.6.2.2.2.4 REGISTRO ROSCADO DE BRONCE DE 4" pza 33.0000 8.00 264.00

2.6.2.2.2.4 SUMIDERO DE BRONCE DE 6" pza 1.0000 20.00 20.00

2.6.2.2.2.4 VALVULA DE AIRE DOBLE EFECTO 2" C/R und 4.0000 80.00 320.00

2.6.2.2.2.4 VALVULA MARIPOSA B.B. DE 8" und 2.0000 220.00 440.00

2.6.2.2.2.4 ESPEJO DE CRISTAL E=4 mm p2 1,014.9300 4.80 4,871.66

2.6.2.2.2.4CRISTAL TEMPLADO COLOR GRISS 6 MM. (INC. ACCESORIOS E INSTALACION SEGUNPLANO DE DETALLE)

p2 2,509.5200 30.0075,285.60

2.6.2.2.2.4PLACA REYNOBOND SILVER METALIC E=6MM, SIST. MURO CORTINA (INC. ACC. E INST.PLANO DETALLE)

p2 18,528.6500 22.00407,630.30

2.6.2.2.2.4CRISTAL TEMPLADO COLOR GRISS 6 MM. SISTEMA MURO CORTINA (INC.ACCESORIOS E INSTALACION SEGUN PLANO DE DETALLE)

p2 41,492.6300 33.001,369,256.79

2.6.2.2.2.4 AGREGADO GRUESO (MATERIAL ZARANDEADO) m3 10.3800 40.00 415.20

2.6.2.2.2.4 CEMENTO PORTLAND TIPO IP (42.5KG) BOL 83,680.6300 22.30 1,866,078.05

14,490,680.59COMBUSTIBLE

2.6.2.2.2.4 PETROLEO gln 644.0500 13.00 8,372.65

2.6.2.2.2.4 GASOLINA 84 OCTANOS gln 1,386.9200 13.50 18,723.42

27,096.07

2.6.2.2.2.5 SERVICIOS2.6.2.2.2.5 OFICINA PARA RESIDENCIA DE OBRA GLB 1.0000 1,500.00 1,500.00

2.6.2.2.2.5 ENCOFRADO PREFABRICADO PARA COLUMNA INC ACCESORIOS m2 3,238.7900 35.00 113,357.65

2.6.2.2.2.5 ENCOFRADO PREFABRICADO PARA PLACA INC ACCESORIOS m2 5,193.9100 20.00 103,878.20

2.6.2.2.2.5ENCOFRADO PREFABRICADO PARA SOPORTE DE LOSA PREFABRICADA INC.ACCESORIOS

m2 10,563.1100 20.00211,262.20

2.6.2.2.2.5ENCOFRADO PREFABRICADO PARA SOPORTE DE VIGAS INC. ACCESORIOS m2 8,726.3900 45.00

392,687.55

2.6.2.2.2.5ENCOFRADO PREFABRICADO PARA PLACA DE ASCENSOR INC ACCESORIOS m2 3,065.1000 40.00

122,604.00

2.6.2.2.2.5 COMPACTADORA VIBRATORIA TIPO PLANCHA 7 HP HE 1,514.9200 10.00 15,149.20

2.6.2.2.2.5 VIBRADOR DE CONCRETO 4 HP 1" HE 2,076.3800 6.25 12,977.38

2.6.2.2.2.5 ANDAMIO METALICO (0.80 m - 3.00 m) he 14,422.9300 5.00 72,114.65

2.6.2.2.2.5 PIEDRA ESMERIL pza 11.8700 30.00 356.10

2.6.2.2.2.5 CASCO AMARILLO und 200.0000 12.00 2,400.00

2.6.2.2.2.5 CIZALLA P/FIERRO CONST. HASTA 3/4" HE 10,296.7200 5.00 51,483.60

2.6.2.2.2.5 GUANTES DE JEBE PAR 500.0000 12.00 6,000.00

2.6.2.2.2.5 GUANTES DE CUERO PAR 400.0000 12.00 4,800.00

2.6.2.2.2.5 PROTECTOR DE OIDOS pza 100.0000 8.00 800.00

Page 14: PRESUPUESTO ANALITICO DETALLADO

Proyecto

Fecha 10/01/2013Lugar PUNO - PUNO - PUNO

Part. Esp. Recurso Unidad Cantidad Precio ParcialS/. S/.

MEJORAMIENTO DE LOS SERVICIOS ACADEMICOS EN LA FORMACION BASICA,INFORMATICA Y VIRTUAL DE LAS ESCUELAS PROFESIONALES DE LA UNIVERSIDAD

NACIONAL DEL ALTIPLANO

MATERIALES, HERRAMIENTAS Y EQUIPOS DE OBRA

PRESUPUESTO ANALITICO

2.6.2.2.2.5 BOTAS DE JEBE NUEVAS PAR 100.0000 30.00 3,000.00

2.6.2.2.2.5 LENTES DE PROTECCION pza 200.0000 10.00 2,000.00

2.6.2.2.2.5 MEZCLADORA CONCRETO TROMPO 8HP-9P3 hm 1,879.3500 10.00 18,793.50

2.6.2.2.2.5 MEZCLADORA DE CONCRETO DE 9 -11P3 hm 66.0700 10.00 660.70

2.6.2.2.2.5 WINCHE ELECTRICO 3.6 HP DE DOS BALDES hm 1.0700 10.00 10.70

2.6.2.2.2.5 CAMION CISTERNA 4x2 (AGUA) 122 HP 1,500 hm 2.5200 350.00 882.00

2.6.2.2.2.5 CAMION VOLQUETE 4x2 140-210 HP 6 M3 hm 18.6600 120.00 2,239.20

2.6.2.2.2.5 MOTOBOMBA 10 HP 4" hm 0.0300 250.00 7.50

2.6.2.2.2.5 MEDIDAS DE MITIGACION DE IMPACTO AMBIENTAL GLB 1.0000 37,500.00 37,500.00

2.6.2.2.2.5 CAMION CISTERNA 4X2 (AGUA) 1,500 GAL. hm 4.0000 80.00 320.00

2.6.2.2.2.5 SOLDADORA hm 265.8000 5.00 1,329.00

2.6.2.2.2.5 MOTOSOLDADORA DE 250 AMPERIOS hm 306.6700 10.00 3,066.70

2.6.2.2.2.5 ESMERIL hm 101.0300 5.00 505.15

2.6.2.2.2.5 CEPILLADORA PISOS DE PARQUET hm 466.8300 5.00 2,334.15

2.6.2.2.2.5 BALDE DE PRUEBA (TUBERIA) hm 37.3100 150.00 5,596.50

2.6.2.2.2.5 COMPRES.AIRE 425P3 A.C.SERIE ARP 168579 und 12.4800 5.00 62.40

2.6.2.2.2.5 COMPRESORA NEUMATICA 196 HP 600-690 PCM hm 3.2300 150.00 484.50

2.6.2.2.2.5 COMPRESORA NEUMATICA 87 HP 250-330 PCM hm 0.2200 80.00 17.60

2.6.2.2.2.5 COMPACTADOR VIBR. TIPO PLANCHA 4 HP hm 100.4100 10.00 1,004.10

2.6.2.2.2.5 CARGADOR S/LLANTAS 100-115 HP 2-2.25 YD3 hm 6.1100 160.00 977.60

2.6.2.2.2.5 CARGADOR S/LLANTAS 125-155 HP 3 YD3. hm 0.1000 180.00 18.00

2.6.2.2.2.5 RETROEXCAVADOR S/ORUGA 80-110HP 0.5-1.3Y hm 3.6800 240.00 883.20

2.6.2.2.2.5 TRACTOR DE ORUGAS DE 140-160 HP hm 0.1000 240.00 24.00

2.6.2.2.2.5 TRACTOR DE ORUGAS DE 190-240 HP hm 10.3600 260.00 2,693.60

2.6.2.2.2.5 MARTILLO NEUMATICO DE 21 Kg. hm 12.9300 50.00 646.50

2.6.2.2.2.5 MARTILLO NEUMATICO 29 KG C/BARRENO-ACCS hm 0.4400 50.00 22.00

2.6.2.2.2.5 VIBRADOR DE CONCRETO 4 HP 2.40" hm 12.8500 10.00 128.50

2.6.2.2.2.5 VIBRADOR DE 3/4" - 2" CONCRETO hm 35.3600 10.00 353.60

2.6.2.2.2.5 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 hm 57.1800 10.00 571.80

2.6.2.2.2.5 MEZCLADORA CONCRETO TROMPO 8 HP 9 P3 hm 0.0700 10.00 0.70

2.6.2.2.2.5 TEODOLITO hm 34.9200 8.00 279.36

2.6.2.2.2.5 NIVEL TOPOGRAFICO hm 34.9200 5.00 174.60

2.6.2.2.2.5 MIRA TOPOGRAFICA DE 4M hm 34.9200 2.00 69.84

1,198,027.532.6.2.2.2.6 OTROS2.6.2.2.2.6 HERRAMIENTAS MANUALES %MO 97,680.90

TOTAL 18,302,763.72