pert cpm trabajo
DESCRIPTION
DIAGRAMA DE PER-CPM DE UNA LOSA DEPORTIVA EN EL CUAL VEMOS LOS TIEMPOS QUE DURARATRANSCRIPT
![Page 1: Pert Cpm Trabajo](https://reader031.vdocuments.co/reader031/viewer/2022013113/577c835a1a28abe054b4a92b/html5/thumbnails/1.jpg)
ACTIVIDAD DESCRIPCION PREDECESOR DURACION
A CARTEL DE IDENTF. DE LA OBRA 1
B TRAZO NIVEL Y REPLANTEO A 1
C LIMPIEZA DE TERRENO B 1
D EXCAVAC. PARA CIMIENTOS B,C 4
E ELIMINACION DE MATERIAL EXEDENTE B,C 3
F RELLENO CON MATERIAL DE PRESTAMO E 2
G COMPACTACION DE TERRENO F 2
H CONCRETO SIMPLE FC =175 KG/CM2 I 3
I ENCOFRADO Y DESENCOFRADO G 3J RELLENO DE JUNTAS H 2K PINTADO DE LINEAS J 2L ARCOS Y ELEMENTOS METALICOS J,K 2
![Page 2: Pert Cpm Trabajo](https://reader031.vdocuments.co/reader031/viewer/2022013113/577c835a1a28abe054b4a92b/html5/thumbnails/2.jpg)
B 1 C 11 2 2 31 2 2 3
A 10 10 1
E 4 F 23 7 7 93 7 7 9A
B C
D
![Page 3: Pert Cpm Trabajo](https://reader031.vdocuments.co/reader031/viewer/2022013113/577c835a1a28abe054b4a92b/html5/thumbnails/3.jpg)
D 33 623 26
G 2 I 39 11 11 149 11 11 14
I
E
GF
![Page 4: Pert Cpm Trabajo](https://reader031.vdocuments.co/reader031/viewer/2022013113/577c835a1a28abe054b4a92b/html5/thumbnails/4.jpg)
H 3 J 2 K14 17 17 19 1914 17 17 19 19
L 221 2324 26
H J
L
![Page 5: Pert Cpm Trabajo](https://reader031.vdocuments.co/reader031/viewer/2022013113/577c835a1a28abe054b4a92b/html5/thumbnails/5.jpg)
FIN 026 2626 26
22121
K
L