    Purple Line Extension

    Section 1 Advisory Group October 29, 2013

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    2/30

    Approved Project

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    3/30

    Approved Project - Schedule

    Planned Schedule Forecasted Schedule

    Sect ion 1 Sect ion 2 Sect ion 3

    Length 3.9 Miles 2.6 Miles 2.9 Miles

    New Stations

    Wilshire/La Brea

    Wilshire/Fairfax

    Wilshire/La Cienega

    Wilshire/Rodeo

    Century City

    Westwood/UCLA

    Westwood/VA

    Hospital

    Pre-Construction

    ActivitiesCurrent - 2014 2017 - 2018 2025 - 2027

    Construction 2014 - 2023 2019 - 2026 2027 - 2035

    Operations 2023 2026 2035

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    4/30

    Section 1 Advisory Group Role

    Comprised of representatives from communities in the

    project area including residents, businesses, property

    owners, key institutions and associations

    Representatives suggested by city officials and other key

    organizations

    Serves as a conduit between Metro and the community

    Become knowledgeable about the project to provide

    information to the community

    Provide information, feedback and suggestions from the

    community to Metro May occasionally meet as sub-groups

    Meet quarterly for duration of project (8 - 10 years)

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    5/30

    Feedback from June 6th SAG Meeting

    Your #1 Issue: Understanding Construction

    Impacts to you/your organization

    Abilit y to communicate with those you represent

    Your top construction questions: Traffic

    Dust, debris, noise

    Support for businesses during construction

    Visibility/access to businesses and museums

    Project Area Discount Program

    Security around construction sites

    Bus access near construction sites

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    6/30

    How to Share Project Information with

    Your Stakeholders

    Forward construction notices

    Encourage your stakeholders to:

    Check project site frequently Follow us on social media

    Subscribe to e-blast notification list

    Place the project widget on your web page

    (in development)

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    7/30

    Your Feedback from June 6th SAG Meeting

    Your Other Issues:

    Station and station-area appearance after

    construction Entrances

    Plazas

    Streetscapes

    Station art program Appropriate treatment of fossils

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    8/30

    Tonights Agenda

    Project Update and Schedule

    Subway Construction Overview

    Pre-Construction Surveys

    Business Profiles

    Discussion

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    9/30

    Project Update andSchedule

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    10/30

    Pre-Construction:

    Master Cooperative Agreement (MCA) Agreements between Metro and the Cities of Los Angeles

    and Beverly Hills

    Spells out each partys roles and responsibilities including:

    Process for permit review and approvals

    Time-frame for each party to act

    Reimbursement to City for staff time

    More efficient for both parties with multiple interactions

    over long, complicated project City of Los Angeles: Signed MCA in place

    Beverly Hills: Draft MCA being evaluated

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    11/30

    Pre-Construction:

    Utility Relocation

    Utility relocations:

    Clear the way for station

    construction

    Ensure continued utility service

    Typical process:

    Maintain at least 2 lanes of traffic

    in each direction along Wilshire

    Blvd

    Truck/crew leave and lanesreopen at the end of each work

    period

    Limited, day-by-day lane closures

    Typical cross-section of underground utilities

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    12/30

    Section 1 Update La Brea Station

    Advanced Utility RelocationMetro Contractors (through 2014):

    Work underway along Wilshire Blvd at S. Detroit St.,

    S. Sycamore Ave. and S. Orange Dr. Current work hours: 8PM - 6AM (Sunday Thursday)

    Los Angeles Department of Water and Power

    Will complete connections in early 2014

    Work during day-time and night-time hours

    Metro Construction Relations working with DWP Public Affairs to set

    standard for outreach Detailed work activities will be shared as they are further defined

    o Specific locations, times, hours, what to expect

    A30

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    13/30

    Slide 12

    A30 Fix bullet spacing.Administrator, 10/28/2013

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    14/30

    Section 1 Update Fairfax Station

    Exploratory Shaft

    Will provide data about unique

    soil conditions and information to

    Design/Builder for tunnels andunderground station design and

    construction

    Contractor began site

    construction activities in April

    2013

    18 W x 38 L X 70 D excavationwill be complete by 2014

    9-month data gathering period

    will begin in January 2014

    Advanced Utility Relocation

    Fiber optic duct banks relocation

    activity anticipated in early 2014

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    15/30

    Section 1 Update La Cienega Station

    Tie Back Investigations Metro contractors are performing investigations

    for existing underground anchors (tiebacks)

    located under Wilshire Blvd near Le Doux Road Work consists of:

    5 Borings

    October 21 October 31, 2013

    Monday Friday: 10AM -3PM and

    Sunday: 8AM - 6PM

    Access to homes and businesses maintained

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    16/30

    Subway Construction Overview

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    17/30

    Subway Construction Overview

    Tunnels: Pressurized twin tunnel boring machines (TBMs)

    maintain ground pressure

    Concrete tunnel liners installed as TBM proceeds

    Little surface activity

    Stations: Excavated from the ground down

    Initial surface activity (~2 years): Utility relocation (8 - 12 months)

    Pile installation (30 - 44 weeks) Decking installation (15 - 20 weekends)

    Station construction continues below ground (~5years)

    Tunnel Boring Machines breaking through

    Station Excavation

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    18/30

    Station Box Construction:

    Soldier Pile Installation

    Initial excavation support

    Piles installed around the perimeter of

    the station box

    3 diameter hole is augured to 90 depth Steel pile is lifted and placed into the hole

    Hole is back-filled with concrete

    Work occurs behind k-rail

    Heavy equipment stays on the street

    until all piles are installed

    Sidewalks remain open

    2 lanes of traffic remain open in each

    direction

    Business access maintainedSoldier pile installation in Hollywood duringMetro Red Line construction (1995)

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    19/30

    Station Box Construction:

    Initial Excavation and Decking Installation

    Deck

    Beam

    Concrete

    Decking

    Requires full street

    closure

    Generally over a series of

    weekends

    Crews work around theclock from Friday evening

    to Monday morning

    Business access and

    sidewalks maintained

    Streets reopen in time forMonday morning rush

    hour

    Placement of beams for deck installation

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    20/30

    Station Box Construction:

    Below Concrete Deck

    Completed decking at

    Hollywood/HighlandStation

    Street reopens fully with concrete

    decking

    Little difference from driving on aregularly paved street

    Station construction continues

    beneath concrete decking for

    about 5 years

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    21/30

    Extended Work Hours

    Extended Work Hours Will:

    Minimize overall duration of most significant construction impacts

    Maximize efficiency

    Complete Section 1 in early 2023

    Peak Hour: Street construction during AM & PM peak periods

    Night-t ime Work: Overnight work within designated noise limits

    (not seeking variance to noise limits)

    Holiday Moratorium: Construction during non-holiday periods between

    Thanksgiving and New Years

    Provided Presentations to:

    Beverly Hills Chamber of Commerce

    Mid-City West Community Council

    Greater Wilshire Neighborhood Council

    Brookside Homeowners Association

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    22/30

    Schedule of Major Construction Activities

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    23/30

    Pre-Construction Surveys

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    24/30

    Pre-Construction Surveys

    What is a Pre-Construction Survey?

    Provides a detailed record of the existing building conditions prior to

    start of construction

    Performed on buildings facing Wilshire Blvd along the alignment

    Surveys include:

    Pictures of property

    Copies will be made available to property owners, if requested

    Design Builder will conduct surveys

    Construction Relations will begin outreach this Fall

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    25/30

    Business Profiles

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    26/30

    Business Profiles - Goals

    Metro Construction Relations will conduct business profile

    surveys along Section 1 of the Purple Line Extension

    Helps Metro understand business operations:

    Hours of operation

    Delivery schedules

    Ingress/Egress

    Parking

    Customer Base

    Conduct thorough interviews

    Coordinate construction activities

    A29

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    27/30

    Slide 25

    A29 Fix bullets indentsAdministrator, 10/25/2013

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    28/30

    Business Profiles - Continued

    Every business facing the project alignment will

    be visited

    Profiles will consider tenants access and

    operational needs Profiles will serve to understand business

    needs in relationship to construction

    Data will be used to coordinate activities with

    the least impact possible

    Business profiles to begin later this Fall/early

    Winter

  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    29/30

    Stay in Touch

    metro.net/purplelineext

    [email protected]

    Infoline: 213.922.6934

    Twitter.com/purplelineext

    Facebook.com/purplelineext

    mailto:[email protected]:[email protected]
  • 7/27/2019 Oct 2013 Mtg Presentation_102513.pdf

    30/30

    Discussion