metrado de cargas
DESCRIPTION
ExamenTRANSCRIPT
-
E 0.60 - Per
rea Tributaria = 4.85 m Ancho (b) = 0.25 m
Peralte (h) = 0.50 m
Altura Losa (hf) = 0.15 m
1) CALCULO DE LA CARGA MUERTA (Distribuida [Wd])
Concreto Armado Peso Aligerado = 2.400 Ton/m3 4.85 m 0.15 m = 1.75 Ton/m
Acabados Peso Acabados = 0.100 Ton/m2 4.85 m = 0.49 Ton/mTabiquera Peso Tabiquera = 0.150 Ton/m2 4.85 m = 0.73 Ton/m
Concreto Armado Peso Viga = 2.400 Ton/m3 0.25 m 0.50 m = 0.30 Ton/m
Otros = Ton/m2 = 0.00 Ton/m
CARGA MUERTA (Distribuida) = 3.26 Ton/m
2.1) CALCULO DE LA CARGA VIVA (CV1)
Otros 1 Sobrecarga = 0.300 Ton/m2 4.85 m 1.46 Ton/m
CARGA VIVA (CV1)= 1.46 Ton/m
2.2) CALCULO DE LA CARGA VIVA (CV2)
Otros 2 Sobrecarga = 0.400 Ton/m2 4.85 m 1.94 Ton/m
CARGA VIVA (CV2)= 1.94 Ton/m
1.2) CALCULO DE LA CARGA MUERTA (Puntual vOLADO [Pd])
Alto Muro (h) = 1.20 m Ancho Muro = 0.15 m MURO DE SOGA
Albailera Parapeto = 1.800 Ton/m3 4.85 m 1.20 m 0.15 = 1.57 TonConcreto Armado Viga borde = 2.400 Ton/m3 4.85 m 0.50 m 0.15 = 0.87 Ton
CARGA MUERTA (Puntual Volado) = 2.44 Ton
METRADO DE CARGAS [VOLADO]
-
1.3) CALCULO DE LA CARGA MUERTA (Puntual MURO[Pd])
Alto Muro (h) = 1.20 m Ancho Muro = 0.25 m MURO DE CABEZA
Albailera Parapeto = 1.800 Ton/m3 4.85 m 1.20 m 0.25 = 2.62 Ton
Viga secundaria = 2.400 Ton/m3 4.85 m 0.50 m 0.25 = 1.46 Ton
CARGA MUERTA (Puntual Muro) = 4.07 Ton
1.3) CALCULO DE LA CARGA MUERTA (Puntual VIGA SECUNDARIA[Pd])
Alto Muro (h) = 1.20 m Ancho Muro = 0.25 m MURO DE CABEZA
Viga secundaria = 2.400 Ton/m3 4.85 m 0.50 m 0.25 = 1.46 Ton
CARGA MUERTA (Puntual vIGA) = 1.46 Ton
3.1) CALCULO DE LA CARGA DE DISEO (Tramo Normal)
W1 = 1.5 3.26 Ton/m + 1.8 1.46 Ton/m
W1 = 7.51 Ton/m
3.2) CALCULO DE LA CARGA DE DISEO (Tramo del Volado)
W2 = 1.5 3.26 Ton/m + 1.8 1.94 Ton/m
W2 = 8.38 Ton/m
3.3) CALCULO DE LA CARGA DE DISEO (Carga Puntual)
Pu = 1.5 2.44 Ton Pm = 1.5 4.07 Ton Pvs = 1.5 1.46
Pu = 3.67 Ton Pm = 6.11 Ton Pvs = 2.18 Ton
-
4) MODELO FINAL
Pu = 2.18 Ton Pu = 3.67 Ton
Pm = 6.11 Ton
Ton/mW2 =W1 = 7.51 Ton/m
8.38