SIMB. I.U.C. INC. % Ir ( Mes Valorizacion ) lo ( Mes Presupuesto ) Ir / lo
1 2 3 4 = (3) x ( 2 ) 5 6 = (5) x (2) 7 = (4) / (6)
J 47.0000 0.3520 1.0000 258.9400 258.9400 258.9400 258.9400 1.0000
L 17.0000 0.0790 1.0000 271.4700 271.4700 285.9000 285.9000 0.9495
C 21.0000 0.2550 1.0000 294.3600 294.3600 277.5100 277.5100 1.0607
P/M 5.0000 0.1130 0.7430 173.8800 129.1928 173.8800 129.1928 1.000043.0000 0.1130 0.2570 322.2400 82.8157 320.8800 82.4662 1.0042
0.1130 212.0085 211.6590 1.0017
H 38.0000 0.0710 1.0000 253.2400 253.2400 235.7200 235.7200 1.0743
GGU 39.0000 0.1300 1.0000 238.6200 238.6200 263.3500 263.3500 0.9061
K8 = (1) x (7)
0.3520
0.0750
0.2705
0.1132
0.0763
0.1178
FORMULA POLINOMICA
K = A Jr + 0.42 Mr + B Er + 0.14 Gur + 0.08 Cr + 0.08 Lr SI A = 3BJo Mo Eo Guo Co Lo B = 3B
COSTO TOTAL: ENTONCES = B + 0.42 + 3BS/. 3090000.00 4B = 0.28
B = 0.07
K = 0.21 Jr + 0.42 Mr + 0.07 Er + 0.14 Gur + 0.08 Cr + 0.08 LrJo Mo Eo Guo Co Lo
0.14 + 0.08 + 0.08 ENTONCES SI: SIN I.G.V. CON I.G.V.0.28 COSTO DE OBRA: 3593023.256 4239767.4420.07 COSTO DE MANO DE OBRA: 754534.884 890351.1628
COSTO DE MATERIALES: 2083953.488 2459065.116COSTO EQUIPO Y HERRAMIENTAS: 251511.628 296783.7209
COSTO G.G.U.: 503023.256 593567.4419
ST: 3593023.256I.G.V. (18%): 646744.186
PRESUPUESTO DE OBRA: 4239767.442