Castle GroundsRegeneration Project
Project Open Day19th April 2014
![Page 2: LCG Presentation BJ Rev 1](https://reader034.vdocuments.co/reader034/viewer/2022052219/577ccd371a28ab9e788bcce6/html5/thumbnails/2.jpg)
2
Significance of the Castle GroundsCastle Grounds Regeneration Project
The Castle Grounds are anoutstanding example of adesigned landscape and ofmajor importance in the OuterHebrides
![Page 3: LCG Presentation BJ Rev 1](https://reader034.vdocuments.co/reader034/viewer/2022052219/577ccd371a28ab9e788bcce6/html5/thumbnails/3.jpg)
3
IntroductionCastle Grounds Regeneration Project
Today’s presentation
1. Project area2. Project purpose3. Work done so far4. Project scope5. Next steps
![Page 4: LCG Presentation BJ Rev 1](https://reader034.vdocuments.co/reader034/viewer/2022052219/577ccd371a28ab9e788bcce6/html5/thumbnails/4.jpg)
4
Project Area
Castle Grounds Regeneration Project
Castle Grounds Regeneration Project
Core area
![Page 5: LCG Presentation BJ Rev 1](https://reader034.vdocuments.co/reader034/viewer/2022052219/577ccd371a28ab9e788bcce6/html5/thumbnails/5.jpg)
5
Project purpose
Restoration &conservation
Increasedpublic use
andinvolvement
Learning andskills
development
Project success:A restored, well-used place thathelps people to learn aboutheritage and the environmentand allows them to develop skillsand assist in managing the park.
Lews Castle Grounds has asustainable and secure futureas a public and natural asset
The Castle Grounds contribute toachievement of a sustainable,healthy and prosperouscommunity in the OuterHebrides
Castle Grounds Regeneration Project
![Page 6: LCG Presentation BJ Rev 1](https://reader034.vdocuments.co/reader034/viewer/2022052219/577ccd371a28ab9e788bcce6/html5/thumbnails/6.jpg)
6
Heritage Lottery Fund requirements
HLF Parks for People programmerequired project outcomes
1. Increasing the range of park users2. Conserving and improving heritage value3. Increasing the range of volunteers4. Improving skills and knowledge through
learning and training5. Improving management and maintenance
Castle Grounds Regeneration Project
![Page 7: LCG Presentation BJ Rev 1](https://reader034.vdocuments.co/reader034/viewer/2022052219/577ccd371a28ab9e788bcce6/html5/thumbnails/7.jpg)
7
3. Project work done so far
Project scoping stage completed
1. Surveys of landscape and buildings2. Ecology Survey3. Archaeological dig of Sunken Garden4. Historical research5. Consultation with the public and
interested groups6. Cost estimates prepared7. Stakeholder Group set up8. Project scope approved
Castle Grounds Regeneration Project
![Page 8: LCG Presentation BJ Rev 1](https://reader034.vdocuments.co/reader034/viewer/2022052219/577ccd371a28ab9e788bcce6/html5/thumbnails/8.jpg)
8
4. Project Scope
1. Restoration of historic features and planting2. Work to paths to improve accessibility3. Works to key buildings4. New play features5. New pedestrian bridge at Bayhead6. Better signage and information7. A programme of activities to increase use8. Improved maintenance9. Increase in volunteering
Castle Grounds Regeneration Project
Main elements of project
![Page 9: LCG Presentation BJ Rev 1](https://reader034.vdocuments.co/reader034/viewer/2022052219/577ccd371a28ab9e788bcce6/html5/thumbnails/9.jpg)
9
4. Project ScopeCastle Grounds Regeneration Project
Master plan
![Page 10: LCG Presentation BJ Rev 1](https://reader034.vdocuments.co/reader034/viewer/2022052219/577ccd371a28ab9e788bcce6/html5/thumbnails/10.jpg)
10
4. Project Scope
Restoration of historic landscapefeatures and planting
1. Sunken Garden (including new shelter)2. Matheson Memorial3. Bridges4. Bastion wall5. Fountain6. Sea wall (critical areas)7. Landscaping works to Cuddy Point8. American Arboretum9. Improve landscape around Porter’s Lodge
Castle Grounds Regeneration Project
![Page 11: LCG Presentation BJ Rev 1](https://reader034.vdocuments.co/reader034/viewer/2022052219/577ccd371a28ab9e788bcce6/html5/thumbnails/11.jpg)
11
Key historic featuresCastle Grounds Regeneration Project
![Page 12: LCG Presentation BJ Rev 1](https://reader034.vdocuments.co/reader034/viewer/2022052219/577ccd371a28ab9e788bcce6/html5/thumbnails/12.jpg)
12
Improvements to pathsCastle Grounds Regeneration Project
![Page 13: LCG Presentation BJ Rev 1](https://reader034.vdocuments.co/reader034/viewer/2022052219/577ccd371a28ab9e788bcce6/html5/thumbnails/13.jpg)
13
Works to key buildings
Porter’s Lodge
1. Replace roof2. Stonework repairs3. Basic internal repairs4. Proposed uses: displays, small exhibitions,
events
Castle Grounds Regeneration Project
![Page 14: LCG Presentation BJ Rev 1](https://reader034.vdocuments.co/reader034/viewer/2022052219/577ccd371a28ab9e788bcce6/html5/thumbnails/14.jpg)
14
Works to key buildings
Boatman’s Tower
1. Remove mansard roof2. Stonework repairs3. Internal repairs4. Proposed uses: visitor information and
services
Castle Grounds Regeneration Project
![Page 15: LCG Presentation BJ Rev 1](https://reader034.vdocuments.co/reader034/viewer/2022052219/577ccd371a28ab9e788bcce6/html5/thumbnails/15.jpg)
15
Works to key buildings
Boathouse
1. Replace with new building2. Base for water sports3. Toilets/Showers4. Information
Castle Grounds Regeneration Project
![Page 16: LCG Presentation BJ Rev 1](https://reader034.vdocuments.co/reader034/viewer/2022052219/577ccd371a28ab9e788bcce6/html5/thumbnails/16.jpg)
16
Works to key buildings
Woodlands Centre
1. Bring kitchen inside2. Move servery3. Lift to first floor4. Expand information about Castle
Grounds
Castle Grounds Regeneration Project
![Page 17: LCG Presentation BJ Rev 1](https://reader034.vdocuments.co/reader034/viewer/2022052219/577ccd371a28ab9e788bcce6/html5/thumbnails/17.jpg)
17
New play featuresCastle Grounds Regeneration Project
Adventure playarea within trees
Toddlers play area atWoodlands CentreCastle
![Page 18: LCG Presentation BJ Rev 1](https://reader034.vdocuments.co/reader034/viewer/2022052219/577ccd371a28ab9e788bcce6/html5/thumbnails/18.jpg)
18
New pedestrian bridgeCastle Grounds Regeneration Project
Location underdiscussion withStornowayPort Authority
![Page 19: LCG Presentation BJ Rev 1](https://reader034.vdocuments.co/reader034/viewer/2022052219/577ccd371a28ab9e788bcce6/html5/thumbnails/19.jpg)
19
Next steps
Develop designs and make fundingapplications: April to December 2014
1. Develop design proposals and costs2. Develop interpretation plan3. Prepare Activity Plan4. Develop Management & Maintenance Plan5. Consultation with Stakeholder Group and
public6. Funding applications
Castle Grounds Regeneration Project
If funding applications successful,works could start in late 2015