cronograma de obra

2160
 PROYECT FECHA D FECHA TE TIEMPO ITEM

Upload: ray-mundo

Post on 07-Oct-2015

12 views

Category:

Documents


0 download

DESCRIPTION

Cronograma para obras

TRANSCRIPT

CRONOGRAMA 2014CRONOGRAMA VALORIZADO DE AVANCE DE OBRA AL 2015

PROYECTO : COSECHA DE AGUA Y REPRESAMIENTOS DE AGUAS PLUVIALES - DISTRITO DE OROPESA - QUISPICANCHI - CUSCO

FECHA DE INICIO DE OBRA : 05 DE DICIEMBRE DEL 2014FECHA TEORICA DE CULMINACION DE OBRA : 05 DE ABRIL DEL 2015TIEMPO DE EJECUCION : 04 MESES (120 DIAS CALENDARIO).ITEMDESCRIPCIONEJECUTADO 2014%PROGRAMADO 2015%PRESUPUESTO TOTAL%PRESUPUESTO TOTALENERO - 2015FEBRERO - 2015MARZO - 2015ABRIL - 2015

01OBRAS E INSTALACIONES PROVISIONALES PARA TODA LA OBRA6,000.0014,850.1720,850.1720,850.17

01.01CARTEL DE OBRA0.000%840.17100%840.17100%840.17XX100.00%840.1701.02MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y/O HERRAMIENTA1,500.00100%0.000%1,500.00100%1,500.00

01.03EQUIPO DE PROTECCION INDIVIDUAL4,500.00100%0.000%4,500.00100%4,500.00

01.04ELAB. IMPLEMENTACION ADMINISTRACION PLAN DE SEGURIDAD0.000%14,010.00100%14,010.00100%14,010.00XXXXX100.00%1401002SECTOR HUASAO22,513.9142%31,638.5858%54,152.49100%54,152.49

02.01FORESTACION Y REFORESTACION994.708%11,921.8192%12,916.51100%12,916.51

02.01.01LIMPIEZA DE TERRENO MANUAL38.30100%0.000%38.30100%38.30

02.01.02ADQUISICION DE PLANTONES0.000%8,415.00100%8,415.00100%8,415.00XXXXXXXXXXXX41.67%41.67%16.67%3506.253506.251402.502.01.03EXCAVACION A MANO EN TERRENO NORMAL365.7918%1,646.0382%2,011.82100%2,011.82XXXXXXXXXXXX41.67%41.67%16.67%685.8458333333685.8458333333274.338333333302.01.04EXCAVACION EN TERRENO ROCA SUELTA5.611%456.7899%462.39100%462.39XXXXXXXXXXXX41.67%41.67%16.67%190.325190.32576.1302.01.05PLANTACIONES EN ESPECIES NATIVAS585.0029%1,404.0071%1,989.00100%1,989.00XXXXXXXXXXXX41.67%41.67%16.67%58558523402.02PRACTICAS MECANICAS DE CONSERVACION21,519.2152%19,716.7748%41,235.98100%41,235.98

02.02.01ZANJAS DE INFILTRACION21,519.2152%19,716.7748%41,235.98100%41,235.98

02.02.02.01TRAZO NIVELACION Y REPLANTEO3.573%124.2097%127.77100%127.77XXX100.00%124.202.02.02.02LIMPIEZA DE TERRENO MANUAL160.007%2,128.0093%2,288.00100%2,288.00XXXX50.00%50.00%1064106402.02.02.03EXCAVACION A MANO EN TERRENO NORMAL19,835.8055%16,221.6545%36,057.45100%36,057.45XXXXXXXXXX50.00%50.00%8110.8258110.82502.02.02.04EXCAVACION EN TERRENO ROCA SUELTA1,519.8455%1,242.9245%2,762.76100%2,762.76XXXXXXXXXX50.00%50.00%621.46621.4603SECTOR PATABAMBA21,501.7151%20,553.1949%42,054.90100%42,054.90

03.01PRACTICAS MECANICAS DE CONSERVACION21,501.7151%20,553.1949%42,054.90100%42,054.90

03.01.01ZANJAS DE INFILTRACION21,501.7151%20,553.1949%42,054.90100%42,054.90

03.01.01.01TRAZO NIVELACION Y REPLANTEO65.2350%65.0450%130.27100%130.27XXX66.67%33.33%43.3621.6803.01.01.02LIMPIEZA DE TERRENO MANUAL1,166.7250%1,166.7250%2,333.44100%2,333.44XXXXXX33.33%33.33%33.33%388.9066666667388.9066666667388.906666666703.01.01.03EXCAVACION A MANO EN TERRENO NORMAL18,827.2051%17,946.3649%36,773.56100%36,773.56XXXXXXXXXXXX16.67%41.67%41.67%2991.067477.657477.6503.01.01.04EXCAVACION EN TERRENO ROCA SUELTA1,442.5651%1,375.0749%2,817.63100%2,817.63XXXXXXXXXXXX16.67%41.67%41.67%229.1783333333572.9458333333572.945833333304SECTOR CHINICARA ALTO9,993.7810%93,981.7790%103,975.55100%103,975.55

04.01FORESTACION Y REFORESTACION0.000%15,263.54100%15,263.54100%15,263.54

04.01.01LIMPIEZA DE TERRENO MANUAL0.000%112.64100%112.64100%112.64XX100.00%112.6404.01.02ADQUISICION DE PLANTONES0.000%9,900.00100%9,900.00100%9,900.00XXXXXXXX25.00%25.00%25.00%25.00%247524752475247504.01.03EXCAVACION A MANO EN TERRENO NORMAL0.000%2,366.85100%2,366.85100%2,366.85XXXXXXXXXXXXXXXXXXXX25.00%25.00%25.00%25.00%591.7125591.7125591.7125591.712504.01.04EXCAVACION EN TERRENO ROCA SUELTA0.000%544.05100%544.05100%544.05XXXXXXXXXXXXXXXXXXXX25.00%25.00%25.00%25.00%136.0125136.0125136.0125136.012504.01.05PLANTACIONES EN ESPECIES NATIVAS0.000%2,340.00100%2,340.00100%2,340.00XXX100.00%234004.02PRACTICAS MECANICAS DE CONSERVACION9,993.7811%78,718.2389%88,712.01100%88,712.01

04.02.01ZANJAS DE INFILTRACION9,993.7814%63,081.0386%73,074.81100%73,074.81

04.02.01.01TRAZO NIVELACION Y REPLANTEO15.640%17,895.46100%17,911.10100%17,911.10XXX100.00%17895.4604.02.01.02LIMPIEZA DE TERRENO MANUAL422.4013%2,784.9687%3,207.36100%3,207.36XX100.00%2784.9604.02.01.03EXCAVACION A MANO EN TERRENO NORMAL8,875.6818%41,670.3182%50,545.99100%50,545.99XXXXX100.00%41670.3104.02.01.04EXCAVACION EN TERRENO ROCA SUELTA680.0648%730.3052%1,410.36100%1,410.36XXXXX100.00%730.304.02.02MANTENIMIENTO DE ZANJA DE INFILTRACION0.000%15,637.20100%15,637.20100%15,637.20

04.02.02.01EXCAVACION A MANO EN TERRENO NORMAL0.000%15,637.20100%15,637.20100%15,637.20XX100.00%15637.205SECTOR PUCARA Y GALERIAS46,047.5340%69,164.8760%115,212.40100%115,212.40

05.01FORESTACION Y REFORESTACION1,541.695%30,235.2995%31,776.98100%31,776.98

05.01.01LIMPIEZA DE TERRENO MANUAL30.7245%36.8655%67.58100%67.58XXX100.00%36.8605.01.02ADQUISICION DE PLANTONES0.000%5,940.00100%5,940.00100%5,940.00XXX33.33%66.67%1980396005.01.03EXCAVACION A MANO EN TERRENO NORMAL710.053%21,479.1597%22,189.20100%22,189.20XXXXXXXXXX50.00%50.00%10739.57510739.57505.01.04EXCAVACION EN TERRENO ROCA SUELTA98.925%2,077.2895%2,176.20100%2,176.20XXXXXXXXXX50.00%50.00%1038.641038.6405.01.05PLANTACIONES EN ESPECIES NATIVAS702.0050%702.0050%1,404.00100%1,404.00XXXXXXXXXX50.00%50.00%35135105.02PRACTICAS MECANICAS DE CONSERVACION39,189.1451%37,146.2349%76,335.37100%76,335.37

05.02.01ZANJAS DE INFILTRACION25,059.1441%35,639.0359%60,698.17100%60,698.17

05.02.01.01TRAZO NIVELACION Y REPLANTEO14.390%14,378.11100%14,392.50100%14,392.50XX100.00%14378.1105.02.01.02LIMPIEZA DE TERRENO MANUAL160.006%2,417.2894%2,577.28100%2,577.28XXX100.00%2417.2805.02.01.03EXCAVACION A MANO EN TERRENO NORMAL23,113.7557%17,502.5743%40,616.32100%40,616.32XXXXX100.00%17502.5705.02.01.04EXCAVACION EN TERRENO ROCA SUELTA1,771.0057%1,341.0743%3,112.07100%3,112.07XXXXX100.00%1341.0705.02.02MANTENIMIENTO DE ZANJA DE INFILTRACION14,130.0090%1,507.2010%15,637.20100%15,637.20

05.02.02.01EXCAVACION A MANO EN TERRENO NORMAL14,130.0090%1,507.2010%15,637.20100%15,637.20XX100.00%1507.205.03FLETES5,250.0075%1,750.0025%7,000.00100%7,000.00

05.03.01FLETES TERRESTRE Y RURAL5,250.0075%1,750.0025%7,000.00100%7,000.00XXXXXXXXXXXXXXXXXXXXXXXXXXX18.52%18.52%18.52%18.52%18.52%7.41%324.0740740741324.0740740741324.0740740741324.0740740741324.0740740741129.629629629605.04MITIGACION DE IMPACTO AMBIENTAL66.7067%33.3533%100.05100%100.05

05.04.01ELIMINACION DE DESECHOS A BOTADEROS66.7067%33.3533%100.05100%100.05XXXXXXX71.43%28.57%23.82142857149.5285714286

*Nota:*Nota:*Nota:*Nota:Se esta considerando para la Programacion de Obra Valorizado c/r al Costo DirectoTOTAL COSTO DIRECTO106056.9331.54%230188.5868.46%336245.51336245.51077876.514074074177896.374074074146837.801574074116933.72240740748518.04133597882126.12653439150PORCENTAJE PROGRAMADO SEMANAL0.00%23.16%23.17%13.93%5.04%2.53%0.63%0.00%PORCENTAJE PROGRAMADO MENSUAL23.16%37.10%7.57%0.63%PROGRAMADO MENSUAL77876.5140740741124734.17564814825451.76374338622126.1265343915ACUMULADO POR MES 201577876.5140740741202610.689722222228062.453465608230188.580.3470831717PORCENTAJE ACUMULADO MENSUAL23.16%60.26%67.83%68.46%

LEYENDA:LEYENDA:54.70%PROGRAMADO:EJECUTADO:

32%68%

58,326.76462,950.25471,130.9785,813.2082,757.35195,825.19175,420.2043,386.6410,333.95413,805.006,760.00339471393,000.00385511930092020-29861831.42018 ESTRUCTURAS 019 ARQUITECTURA 020 INST. SANITARIAS 021 INST. ELECTRICAS 022 CERCO PERIMETRICO 023 AREAS EXTERIORES024 TANQUE CISTERNA ELEVADO 025 IMPACTO AMBIENTAL 026 EQUIPAMIENTO027 PROGRAMA IEC 028 CAPACITACION

CRONOGRAMA 2018CRONOGRAMA VALORIZADO DE AVANCE DE OBRA AL 2015

PROYECTO : COSECHA DE AGUA Y REPRESAMIENTOS DE AGUAS PLUVIALES - DISTRITO DE OROPESA - QUISPICANCHI - CUSCO

FECHA DE INICIO DE OBRA : 05 DE ENERO DEL 2014RESPONSABLE: ING. MARCO ANTONIO HERVAS PONCEFECHA TEORICA DE CULMINACION DE OBRA : 02 DE ENERO DEL 2016TIEMPO DE EJECUCION : 36 MESES (1080 DIAS CALENDARIO)M1M2M3M4M5M6M7M8M9M10M11M12.ITEMDESCRIPCIONPRESUPUESTO - 2013%PRESUPUESTO -2014%PRESUPUESTO - 2015%PRESUPUESTO - 2016%PRESUPUESTO TOTAL%PRESUPUESTO TOTALENERO - 2014FEBRERO - 2014MARZO - 2014ABRIL - 2014MAYO - 2014JUNIO - 2014JULIO - 2014AGOSTO - 2014SEPTIEMBRE - 2014OCTUBRE - 2014NOVIEMBRE 2014DICIEMBRE - 2014

SISTEMA DE AGUA POTABLE309,003.66188,693.902,252,302.440.002,750,000.002,750,000.00

01OBRAS PROVISIONALES5,371.283,799.8458,512.200.0067,683.3267,683.32xxxxxXXXXXXXXXXXXXXX25.00%25.00%25.00%25.00%Aceptar949.9606949.9606949.9606949.96063799.8424Aceptar01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M650.00100%0.000%0.000%0.000%650.00100%650.00Presupuesto extendidoAceptar0Presupuesto extendido01.02 ALMACEN Y GUARDIANIA (ALQUILADO)1,800.00100%0.000%0.000%0.000%1,800.00100%1,800.00Presupuesto extendidoAceptar0Presupuesto extendido01.03 CINTA DE SEGURIDAD1,033.2012%803.8910%6,513.3378%0.000%8,350.42100%8,350.42Presupuesto extendidoAceptar0Presupuesto extendido01.04 AGUA PARA HUMEDECER TERRENO0.000%46.9730%109.5970%0.000%156.56100%156.56Presupuesto extendidoPresupuesto extendido0Presupuesto extendido01.05 PUENTES PEATONALES PROVISIONALES0.000%461.3410%4,152.0690%0.000%4,613.40100%4,613.40Presupuesto extendidoPresupuesto extendidoPresupuesto extendido01.06 TRANQUERAS DE MADERA 1.20X1.10M P/DESVIO TRANSITO VEHICULAR1,888.0827%236.013%4,956.2170%0.000%7,080.30100%7,080.30Presupuesto extendidoAceptar0Presupuesto extendido01.07 PUESTA EN OPERACION DEL SISTEMA0.000%337.995%6,421.8895%0.000%6,759.87100%6,759.87Presupuesto extendidoPresupuesto extendido0Presupuesto extendido01.08 LIMPIEZA FINAL DE OBRA0.000%1,913.645%36,359.1395%0.000%38,272.77100%38,272.77Presupuesto extendidoPresupuesto extendido0Presupuesto extendido02LINEAS DE CONDUCCION147,061.2912,855.68229,782.490.00389,699.45389,699.45XXXXXXXXXXXXXXXXXXXXPresupuesto extendido25.00%25.00%25.00%25.00%Aceptar3213.918753213.918753213.918753213.9187512855.675Aceptar02.01 TRABAJOS PRELIMINARESPresupuesto extendidoPresupuesto extendido0Presupuesto extendido02.01.01 TRAZO NIVELACION Y REPLANTEO4,544.86100%0.000%0.000%0.000%4,544.86100%4,544.86Presupuesto extendidoAceptarPresupuesto extendido02.02 MOVIMIENTO DE TIERRASPresupuesto extendidoPresupuesto extendido0Presupuesto extendido02.02.01 EXCAVACION MANUAL T-COMPACTADO P/TUB 90 mm HASTA 1.50M.112,044.2499%1,250.171%0.000%0.000%113,294.41100%113,294.41Presupuesto extendidoAceptarPresupuesto extendido02.02.02 REFINE Y NIVELACION DE ZANJAS T.COMPACT P/TUB. 90 mm.0.000%449.585%8,542.0495%0.000%8,991.62100%8,991.62Presupuesto extendidoPresupuesto extendidoPresupuesto extendido02.02.03 CAMA DE APOYO CON ARENA GRUESA P/TUB. DE 63 - 110mm T.N.0.000%1,778.715%33,795.4195%0.000%35,574.12100%35,574.12Presupuesto extendidoPresupuesto extendido0Presupuesto extendido02.02.04 RELLENO COMPACTADO ZANJAS P/TUB. 63mm (2") a 110mm (4") H=1.50M0.000%2,803.755%53,271.2695%0.000%56,075.01100%56,075.01Presupuesto extendidoPresupuesto extendido0Presupuesto extendido02.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON TRANSPORTE0.000%225.175%4,278.2495%0.000%4,503.41100%4,503.41Presupuesto extendidoAceptar0Aceptar02.03 TUBERIAS Y ACCESORIOSAceptarAceptar0Aceptar02.03.01 TUBERIA PVC C-5 U.F. 63mm (2")0.000%98.515%1,871.6095%0.000%1,970.10100%1,970.10AceptarAceptarAceptar02.03.02 TUBERIA PVC C-5 U.F. 110mm (4")0.000%57.945%1,100.9595%0.000%1,158.89100%1,158.89AceptarAceptar0Aceptar02.03.03 TUBERIA PVC C-10 U.F. 110mm (4")1,987.502%2,002.303%75,806.2195%0.000%79,796.01100%79,796.01AceptarAceptar0Aceptar02.03.04 CODO PVC C-5 P/AGUA 63mm x 22.5 UF0.000%2.505%47.5095%0.000%50.00100%50.00AceptarAceptar0Aceptar02.03.05 CODO PVC C-5 P/AGUA 63mm x 45 UF0.000%6.505%123.5095%0.000%130.00100%130.00AceptarAceptar0Aceptar02.03.06 CODO PVC C-5 P/AGUA 63mm x 90 UF0.000%1.355%25.6595%0.000%27.00100%27.00AceptarAceptar0Aceptar02.03.07 REDUCCIN PVC P/AGUA C-5 63 mm x 2" S/P0.000%11.105%210.9095%0.000%222.00100%222.00AceptarAceptar0Aceptar02.03.08 UNION DE REPARACION PVC 63 mm. C-50.000%8.405%159.6095%0.000%168.00100%168.00AceptarAceptar0Aceptar02.03.09 CODO PVC C-5 P/AGUA 110mm x 11.25 UF0.000%1.355%25.6595%0.000%27.00100%27.00AceptarAceptar0Aceptar02.03.10 REDUCCIN PVC P/AGUA C-5 110 mm x 4" S/P0.000%2.255%42.7595%0.000%45.00100%45.00AceptarAceptar0Aceptar02.03.11 UNION DE REPARACION PVC 110 mm. C-50.000%2.205%41.8095%0.000%44.00100%44.00AceptarAceptar0Aceptar02.03.12 CODO PVC C-10 P/AGUA 110mm x 11.25 UF0.000%85.755%1,629.2595%0.000%1,715.00100%1,715.00AceptarAceptarAceptar02.03.13 CODO PVC C-10 P/AGUA 110mm x 22.50 UF0.000%91.585%1,739.9395%0.000%1,831.50100%1,831.50AceptarAceptar0Aceptar02.03.14 CODO PVC C-10 P/AGUA 110mm x 45 UF0.000%17.505%332.5095%0.000%350.00100%350.00AceptarAceptar0Aceptar02.03.15 REDUCCIN PVC P/AGUA C-10 110 mm x 4" S/P0.000%12.205%231.8095%0.000%244.00100%244.00AceptarAceptar0Aceptar02.03.16 UNION DE REPARACION PVC 110 mm. C-100.000%12.405%235.6095%0.000%248.00100%248.00AceptarAceptar0Aceptar02.03.17 UNION MECANICA DE AMPLIO RANGO 4" (100mm)0.000%40.005%760.0095%0.000%800.00100%800.00AceptarAceptarAceptar02.03.18 LUBRICANTE PARA TUBERIA DE UNION FLEXIBLE0.000%4.575%86.7895%0.000%91.35100%91.35AceptarAceptar0Aceptar02.03.19 LUBRICANTE PARA ACCESORIOS DE UNION FLEXIBLE0.000%0.835%15.8295%0.000%16.65100%16.65AceptarAceptar0Aceptar02.04 INSTALACION TUBERIAS Y ACCESORIOSAceptarAceptar0Aceptar02.04.01 INSTALAC.TUBERIA P.V.C. DE 63mm A 110mm0.000%346.595%6,585.1395%0.000%6,931.72100%6,931.72AceptarAceptar0Aceptar02.04.02 INSTALAC. DE ACCESORIOS PVC /RED AGUA POTABLE DE 63mm A 110mm0.000%120.295%2,285.5595%0.000%2,405.84100%2,405.84AceptarAceptar0Aceptar02.05 PRUEBA HIDRAULICA Y DESINFECCIONAceptarAceptar0Aceptar02.05.01 PRUEBA A ZANJA TAPADA Y DESINFECCION DE TUBERIA HASTA 110mm0.000%42.065%799.0695%0.000%841.12100%841.12AceptarAceptarAceptar02.06 CAMARA DE VALVULAS DE AIRE Y PURGAAceptarAceptar0Aceptar02.06.01 CAMARA PARA VALVULA DE AIRE TIPO8,835.6480%552.235%1,656.6815%0.000%11,044.55100%11,044.55AceptarAceptarAceptar02.06.02 ACCESORIOS PARA VALVULA DE AIRE TIPO0.000%636.565%12,094.6995%0.000%12,731.25100%12,731.25AceptarAceptar0Aceptar02.06.03 CAMARA DE VALVULA DE PURGA TIPO9,751.5280%609.475%1,828.4115%0.000%12,189.40100%12,189.40AceptarAceptar0Aceptar02.06.04 ACCESORIOS PARA VALVULA DE PURGA 0.000%224.935%4,273.5895%0.000%4,498.50100%4,498.50AceptarAceptar0Aceptar02.07 PASE AEREOAceptarAceptar0Aceptar02.07.01 PASE AEREO TUBERIA F.G. 4" CON COLUMNAS Y CABLE L=12 ML2,874.3930%479.065%6,227.8565%0.000%9,581.30100%9,581.30AceptarAceptarAceptar02.07.02 PASE AEREO TUBERIA F.G. 4" CON COLUMNAS Y CABLE L=26 ML7,023.1440%877.895%9,656.8155%0.000%17,557.84100%17,557.84AceptarAceptar0Aceptar03REDES DE DISTRIBUCION138,158.60146,574.111,839,420.130.002,124,152.842,124,152.84xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxAceptar14.71%14.71%14.71%11.76%14.71%14.71%14.71%Aceptar21555.015617647121555.015617647121555.015617647117244.012494117621555.015617647121555.015617647121555.0156176471146574.1062Aceptar03.01 TRABAJOS PRELIMINARESAceptarAceptar0Aceptar03.01.01 TRAZO NIVELACION Y REPLANTEO1,709.7012%1,744.7913%10,363.4775%0.000%13,817.96100%13,817.96AceptarAceptar0Aceptar03.01.02 TRAZO NIVELACION Y REPLANTEO DURANTE LA EJECUCION0.000%8,315.6335%15,443.3165%0.000%23,758.94100%23,758.94AceptarAceptar0Aceptar03.01.03 DEMOLICION DE PAVIMENTO DE CONCRETO DE 8"89,687.9651%23,615.0914%61,009.3435%0.000%174,312.39100%174,312.39AceptarAceptar0Aceptar03.01.04 DEMOLICION DE VEREDA0.000%4,106.555%78,024.3795%0.000%82,130.92100%82,130.92AceptarAceptarAceptar03.01.05 REPOSICION DE PAVIMENTO DE CONCRETO DE 8"0.000%28,998.035%550,962.6195%0.000%579,960.64100%579,960.64AceptarAceptarAceptar03.01.06 REPOSICION DE VEREDA0.000%8,793.415%167,074.8395%0.000%175,868.24100%175,868.24AceptarAceptar0Aceptar03.02 MOVIMIENTO DE TIERRASAceptarAceptar0Aceptar03.02.01 EXCAVACION MANUAL T-COMPACTADO P/TUB 90 mm HASTA 1.50M.41,760.1812%44,353.5613%258,341.2275%0.000%344,454.96100%344,454.96AceptarAceptar0Aceptar03.02.02 REFINE Y NIVELACION DE ZANJAS T.COMPACT P/TUB. 90 mm.0.000%1,366.895%25,970.8295%0.000%27,337.70100%27,337.70AceptarAceptar0Aceptar03.02.03 CAMA DE APOYO CON ARENA GRUESA P/TUB. DE 63 - 110mm T.N.0.000%5,407.895%102,749.9795%0.000%108,157.86100%108,157.86AceptarAceptar0Aceptar03.02.04 RELLENO COMPACTADO ZANJAS P/TUB. 63mm (2") a 110mm (4") H=1.50M0.000%8,524.395%161,963.4295%0.000%170,487.81100%170,487.81AceptarAceptar0Aceptar03.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON TRANSPORTE5,000.7615%3,555.0310%25,667.3775%0.000%34,223.16100%34,223.16AceptarAceptar0Aceptar03.03 CRUCE PUENTEAceptarAceptar0Aceptar03.03.01 TUBERIA FIERRO GALVANIZADO 2"0.000%8.022%393.0498%0.000%401.06100%401.06AceptarAceptar0Aceptar03.03.02 TUBERIA FIERRO GALVANIZADO 3"0.000%16.692%817.6198%0.000%834.30100%834.30AceptarAceptar0Aceptar03.03.03 UNION MECANICA MAXIFIT 2" (50mm)0.000%4.802%235.2098%0.000%240.00100%240.00AceptarAceptar0Aceptar03.03.04 UNION MECANICA MAXIFIT 3" (80mm)0.000%6.402%313.6098%0.000%320.00100%320.00AceptarAceptar0Aceptar03.03.05 ANCLAJE 0.000%26.682%1,307.0998%0.000%1,333.77100%1,333.77AceptarAceptar0Aceptar03.03.06 INSTALACION TUBERIA FG DE 2"0.000%2.762%135.1898%0.000%137.94100%137.94AceptarAceptar0Aceptar03.03.07 INSTALACION TUBERIA FG DE 3"0.000%5.012%245.5598%0.000%250.56100%250.56AceptarAceptar0Aceptar03.04 TUBERIAS Y ACCESORIOSAceptarAceptar0Aceptar03.04.01 TUBERIA PVC C-10 U.F. 63mm (2")0.000%1,849.632%90,631.6398%0.000%92,481.25100%92,481.25AceptarAceptar0Aceptar03.04.02 TUBERIA PVC C-10 U.F. 90mm (3")0.000%912.832%44,728.7898%0.000%45,641.61100%45,641.61AceptarAceptar0Aceptar03.04.03 CRUZ DE PVC C-10 DE 63 mm U.F.0.000%16.082%787.9298%0.000%804.00100%804.00AceptarAceptar0Aceptar03.04.04 CRUZ DE PVC C-10 DE 90 mm U.F.0.000%14.722%721.2898%0.000%736.00100%736.00ERROR:#REF!AceptarAceptar03.04.05 TEE DE PVC AGUA C-10 63 mm. U.F.0.000%33.332%1,633.1798%0.000%1,666.50100%1,666.50AceptarAceptar0Aceptar03.04.06 TEE DE PVC AGUA C-10 90 mm. U.F.0.000%5.482%268.5298%0.000%274.00100%274.00AceptarAceptar0Aceptar03.04.07 TEE DE PVC AGUA CON REDUCCIN DE 90 x 63 mm. U.F.0.000%22.722%1,113.2898%0.000%1,136.00100%1,136.00AceptarAceptar0Aceptar03.04.08 CODO PVC C-10 P/AGUA 63mm x 22.5 UF0.000%28.802%1,411.2098%0.000%1,440.00100%1,440.00AceptarAceptar0Aceptar03.04.09 CODO PVC C-10 P/AGUA 63mm x 45 UF0.000%7.262%355.7498%0.000%363.00100%363.00AceptarPresupuesto extendido0Presupuesto extendido03.04.10 CODO PVC C-10 P/AGUA 63mm x 90 UF0.000%9.522%466.4898%0.000%476.00100%476.00Presupuesto extendidoPresupuesto extendido0Aceptar03.04.11 CODO PVC C-10 P/AGUA 90mm x 22.5 UF0.000%5.742%281.2698%0.000%287.00100%287.00AceptarAceptar0Aceptar03.04.12 CODO PVC C-10 P/AGUA 90mm x 45 UF0.000%2.552%124.9598%0.000%127.50100%127.50AceptarAceptar0Aceptar03.04.13 CODO PVC C-10 P/AGUA 90mm x 90 UF0.000%1.722%84.2898%0.000%86.00100%86.00AceptarAceptar0Aceptar03.04.14 REDUCCIN PVC P/AGUA C-10 90 mm x 63 mm U.F0.000%10.072%493.4398%0.000%503.50100%503.50AceptarAceptar0Aceptar03.04.15 TAPON DE PVC P/AGUA C-10 TUBERIA DE 63 mm U.F.0.000%8.512%416.9998%0.000%425.50100%425.50AceptarAceptar0Aceptar03.04.16 VALVULA COMP. HIERRO DUCTIL ISO 7259 DE 63mm0.000%121.602%5,958.4098%0.000%6,080.00100%6,080.00AceptarAceptarAceptar03.04.17 VALVULA COMP. HIERRO DUCTIL ISO 7259 DE 90mm0.000%52.002%2,548.0098%0.000%2,600.00100%2,600.00AceptarAceptar0Aceptar03.04.18 VALVULA COMPUERTA (PURGA) DE 63mm0.000%28.802%1,411.2098%0.000%1,440.00100%1,440.00AceptarAceptar0Aceptar03.04.19 LUBRICANTE PARA TUBERIA DE UNION FLEXIBLE0.000%4.472%219.1898%0.000%223.65100%223.65AceptarAceptar0Aceptar03.05 INSTALACION TUBERIAS Y ACCESORIOSAceptarAceptar0Aceptar03.05.01 INSTALAC.TUBERIA P.V.C. DE 63mm A 110mm0.000%421.502%20,653.3898%0.000%21,074.88100%21,074.88AceptarAceptar0Aceptar03.05.02 INSTALAC. DE ACCESORIOS PVC /RED AGUA POTABLE DE 63mm A 110mm0.000%69.702%3,415.2398%0.000%3,484.93100%3,484.93AceptarAceptar0Aceptar03.05.03 INSTALACION VALVULA COMPUERTA0.000%168.332%8,247.9998%0.000%8,416.32100%8,416.32AceptarAceptar0Aceptar03.05.04 INSTALACION VALVULA COMPUERTA (PURGA)0.000%67.492%3,306.9798%0.000%3,374.46100%3,374.46AceptarAceptar0Aceptar03.06 ANCLAJES / DADOS DE CONCRETOAceptarAceptar0Aceptar03.06.01 MACIZO DE ANCLAJE Fc= 140 Kg/cm2 0.40x0.4x0.40 m.0.000%71.262%3,491.8798%0.000%3,563.13100%3,563.13AceptarAceptarAceptar03.07 PRUEBA HIDRAULICA Y DESINFECCIONAceptarAceptar0Aceptar03.07.01 PRUEBA A ZANJA TAPADA Y DESINFECCION DE TUBERIA HASTA 63mm0.000%67.232%3,294.3798%0.000%3,361.60100%3,361.60AceptarAceptar0Aceptar03.07.02 PRUEBA A ZANJA TAPADA Y DESINFECCION DE TUBERIA HASTA 90mm0.000%14.982%734.1498%0.000%749.12100%749.12AceptarAceptar0Aceptar03.08 CONEXIONES DOMICILIARIAS DE AGUAAceptarAceptar0Aceptar03.08.01 REPOSICIN DE CONEXIONES DOMICILIARIAS DE AGUA0.000%3,306.872%162,036.8198%0.000%165,343.68100%165,343.68AceptarAceptar0Aceptar03.09 SISTEMA CONTRA INCENDIOAceptarAceptar0Aceptar03.09.01 HIDRANTE DE PISO DE 4" (EN TUB 63mm)0.000%257.902%12,637.1098%0.000%12,895.00100%12,895.00AceptarAceptar0Aceptar03.09.02 HIDRANTE DE PISO DE 4" (EN TUB 110mm)0.000%141.402%6,928.6098%0.000%7,070.00100%7,070.00AceptarAceptar0Aceptar04RESERVORIO0.00914.2944,800.150.000%45,714.4445,714.44xxxxxxxxERROR:#REF!62.50%37.50%Aceptar571.4305342.8583914.2888Presupuesto extendido04.01 CASETA DE VALVULASAceptarAceptarAceptar04.01.01 SOLADO DE 2" MEZCLA 1:12 CEMENTO-HORMIGON0.000%2.812%137.5798%0.000%140.38100%140.38AceptarAceptar0Aceptar04.01.02 MALLA METALICA (CARP.METALICA+CONCRETO)0.000%172.532%8,453.7998%0.000%8,626.32100%8,626.32AceptarAceptar0Aceptar04.01.03 TARRAJEO EN INTERIORES Y EXTERIORES CON CEMENTO-ARENA 0.000%8.552%418.8198%0.000%427.36100%427.36AceptarAceptar0Aceptar04.02 SISTEMA DE CLORACIONAceptarAceptar0Aceptar04.02.01 CAMARA PARA MEDIDOR DE CAUDAL0.000%4.412%216.0198%0.000%220.42100%220.42AceptarAceptar0Aceptar04.02.02 INSTALACION DE MEDIDOR DE CAUDAL0.000%102.482%5,021.3498%0.000%5,123.82100%5,123.82AceptarAceptar0Aceptar04.02.03 INSTALACION DE CLORINADOR0.000%242.482%11,881.3498%0.000%12,123.82100%12,123.82AceptarAceptar0Aceptar04.02.04 INSTALACION DE INYECTOR DE CLORO0.000%32.482%1,591.3498%0.000%1,623.82100%1,623.82AceptarAceptar0Aceptar04.03 ACCESORIOS DE LA CAMARA DE CLORACIONAceptarAceptarAceptar04.03.01 BASCULA DE 2 TON0.000%92.482%4,531.3498%0.000%4,623.82100%4,623.82AceptarAceptar0Aceptar04.03.02 TECLE 2 TN Y MONOCARRIL PERFIL I 12" L=8.0M0.000%54.402%2,665.6898%0.000%2,720.08100%2,720.08AceptarAceptar0Aceptar04.03.03 SISTEMA DE CONTROL DE NIVEL0.000%70.002%3,430.0098%0.000%3,500.00100%3,500.00AceptarAceptar0Aceptar04.03.04 PUESTA EN OPERACION GENERAL0.000%131.692%6,452.9198%0.000%6,584.60100%6,584.60AceptarAceptar0Aceptar05TRANSPORTE DE MATERIALES A OBRA18,412.4924,549.9979,787.470.00122,749.95122,749.95xxxxxxxxxxxxxxxAceptar33.33%33.33%33.33%Aceptar8183.33083333338183.33083333338183.330833333324549.9925Presupuesto extendido05.01 TRANSPORTE A OBRA DE MATERIALES Y EQUIPOS18,412.4915%24,549.9920%79,787.4765%0.000%122,749.95100%122,749.95AceptarAceptar0AceptarAceptarAceptar0AceptarSISTEMA DE DESAGUE1,304,366.06558,738.852,076,895.090.003,940,000.003,940,000.00AceptarAceptar0Aceptar01OBRAS PROVISIONALES12,639.523,871.3643,784.030.0060,294.9160,294.91xxxxxxxxAceptar62.50%37.50%Aceptar2419.59906251451.7594375Aceptar01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40m.1,300.00100%0.000%0.000%0.000%1,300.00100%1,300.00AceptarAceptar0Aceptar01.02 ALMACEN Y GUARDIANIA (ALQUILADO)3,000.0050%900.0015%2,100.0035%0.000%6,000.00100%6,000.00AceptarAceptar0Aceptar01.03 CINTA DE SEGURIDAD1,105.4415%736.4510%5,525.6675%0.000%7,367.54100%7,367.54AceptarAceptar0Aceptar01.04 AGUA PARA HUMEDECER EL TERRENO0.000%8.295%157.4995%0.000%165.78100%165.78AceptarAceptar0Aceptar01.05 PUENTES PEATONALES PROVISIONALES153.783%538.2312%3,921.3985%0.000%4,613.40100%4,613.40AceptarAceptar0Aceptar01.06 TRANQUERAS DE MADERA 1.20X1.10m. P/DESVIO TRANSITO VEHICULAR7,080.30100%0.000%0.000%0.000%7,080.30100%7,080.30AceptarAceptar0Aceptar01.07 LIMPIEZA FINAL DE LA OBRA0.000%1,688.395%32,079.5095%0.000%33,767.89100%33,767.89AceptarAceptar0Aceptar02TRABAJOS PRELIMINARES191,145.11212,319.241,032,087.480.001,435,551.821,435,551.82xxxxxxxAceptar42.86%57.14%Aceptar90993.9578571429121325.277142857Aceptar02.01 TRAZO NIVELACION Y REPLANTEO12,191.52100%0.000%0.000%0.000%12,191.52100%12,191.52AceptarAceptar0Aceptar02.02 TRAZO NIVELACION Y REPLANTEO DURANTE LA EJECUCION16,895.4881%1,970.689%2,096.2410%0.000%20,962.40100%20,962.40AceptarAceptar0Aceptar02.03 DEMOLICION DE PAVIMENTO DE CONCRETO DE 8"162,058.1150%48,602.9615%113,432.8935%0.000%324,093.96100%324,093.96AceptarAceptar0Aceptar02.04 REPOSICION DE PAVIMENTO DE CONCRETO DE 8"0.000%161,745.5915%916,558.3585%0.000%1,078,303.94100%1,078,303.94AceptarAceptar0Aceptar03MOVIMIENTO DE TIERRAS495,147.12196,760.01376,662.170.001,068,569.301,068,569.30xxxxxxxxxxxxxxxxxxxxAceptar25.00%25.00%25.00%25.00%Aceptar49190.00349190.00349190.00349190.003196760.012Presupuesto extendido03.01 EXCAVACION MANUAL T.N. P/TUB 160mm. H= 2.00m. P/REHABIL. CONEX. DOMIC.0.000%22,453.2015%127,234.8085%0.000%149,688.00100%149,688.00AceptarAceptar0Aceptar03.02 EXCAVACION MANUAL T.N. P/TUB 160mm/200mm/250mm/315mm/355mm. H= 2.00m.264,047.6467%70,426.0718%59,024.7715%0.000%393,498.48100%393,498.48AceptarAceptar0Aceptar03.03 EXCAVACION MANUAL T.N. P/TUB 355mm. H= 3.00m.0.000%2,151.8315%12,193.6885%0.000%14,345.51100%14,345.51AceptarAceptar0Aceptar03.04 ENTIBADO Y APUNTALAMIENTO14,148.6839%5,795.3016%16,317.8145%0.000%36,261.79100%36,261.79AceptarAceptar0Aceptar03.05 REFINE Y NIVELACION ZANJA T.N. P/TUB 160mm/200mm/250mm/315mm/355mm.16,529.2755%6,033.8220%7,521.0325%0.000%30,084.12100%30,084.12AceptarAceptar0Aceptar03.06 CAMA DE APOYO T.N. P/TUB 160mm/200mm/250mm/315mm/355mm. 43,754.2761%17,155.1124%10,748.7115%0.000%71,658.09100%71,658.09AceptarAceptar0Aceptar03.07 RELLENO COMP. ZANJA TN P/TUB PVC 160mm. H= 2.00m. P/REHABIL. CONEX. DOMIC.0.000%35,639.3535%66,187.3765%0.000%101,826.72100%101,826.72AceptarAceptar0Aceptar03.08 RELLENO COMP. ZANJA T.N. P/TUB PVC 160mm/200mm/250mm/315mm/355mm. H= 2.00m.147,322.8264%26,392.1611%57,904.9925%0.000%231,619.97100%231,619.97AceptarAceptar0Aceptar03.09 RELLENO COMP. ZANJA T.N. P/TUB PVC 160mm/200mm/250mm/315mm/355mm. H= 3.00m.0.000%3,001.2935%5,573.8365%0.000%8,575.12100%8,575.12AceptarAceptar0Aceptar03.10 ELIMINACION CON TRANSPORTE9,344.4430%7,711.8925%13,955.1845%0.000%31,011.50100%31,011.50AceptarAceptar0Aceptar04TUBERIAS Y ACCESORIOS406,885.888,236.0134,162.870.00449,284.76449,284.76xxxxxxxxxxxxxAceptar23.08%38.46%38.46%Aceptar1900.61766923083167.69611538463167.69611538468236.0099Presupuesto extendido04.01 SUMINISTRO AceptarAceptar0Aceptar04.01.01 TUBERIA PVC SAL DESAGUE DE 160mm. SN-2 U.F.36,543.71100%0.000%0.000%0.000%36,543.71100%36,543.71AceptarAceptar0Aceptar04.01.02 TUBERIA PVC SAL DESAGUE DE 200mm. SN-2 U.F.249,914.93100%0.000%0.000%0.000%249,914.93100%249,914.93AceptarAceptar0Aceptar04.01.03 TUBERIA PVC SAL DESAGUE DE 250mm. SN-2 U.F.30,271.66100%0.000%0.000%0.000%30,271.66100%30,271.66AceptarAceptar0Aceptar04.01.04 TUBERIA PVC SAL DESAGUE DE 315mm. SN-2 U.F.76,280.60100%0.000%0.000%0.000%76,280.60100%76,280.60AceptarAceptar0Aceptar04.01.05 TUBERIA FIERRO GALVANIZADO DESAGUE DE 160 MM9,023.28100%0.000%0.000%0.000%9,023.28100%9,023.28AceptarERROR:#REF!0ERROR:#REF!04.02 INSTALACIONERROR:#REF!Aceptar0Aceptar04.02.01 INSTALAC.TUBERIA P.V.C. DESAGUE 160mm.94.152%707.2414%4,207.2884%0.000%5,008.67100%5,008.67AceptarAceptar0Aceptar04.02.02 INSTALAC.TUBERIA P.V.C. DESAGUE 200mm.978.384%2,492.3610%21,320.2486%0.000%24,790.98100%24,790.98AceptarAceptar0Aceptar04.02.03 INSTALAC.TUBERIA P.V.C. DESAGUE 250mm.707.0029%145.546%1,583.2865%0.000%2,435.82100%2,435.82AceptarAceptar0Aceptar04.02.04 INSTALAC.TUBERIA P.V.C. DESAGUE 315mm.3,072.1757%1,531.0228%812.3315%0.000%5,415.52100%5,415.52AceptarAceptar0Aceptar04.02.05 INSTALAC.TUBERIA FIERRO GALVANIZADO 160mm.0.000%3,359.8635%6,239.7365%0.000%9,599.59100%9,599.59AceptarAceptar0Aceptar05CAMARAS DE INSPECCION85,737.7935,788.88194,720.240.00316,246.91316,246.91xxxxxxxxAceptar62.50%37.50%Aceptar22368.051562513420.830937535788.8825Presupuesto extendido05.01 BUZON RED DESAGUE D=1.20 m. H=1.20 - 1.50 m. 70,873.1224%31,584.7611%190,278.9265%0.000%292,736.80100%292,736.80AceptarAceptar0Aceptar05.02 BUZON RED DESAGUE D=1.20 m. H=1.60 - 2.00 m.12,143.1686%1,315.519%708.355%0.000%14,167.02100%14,167.02AceptarAceptar0Aceptar05.03 BUZON RED DESAGUE D=1.20 m. H=2.20 - 3.60 m. 2,721.5133%1,768.9822%3,674.0445%0.008,164.53100%8,164.53AceptarAceptarAceptar05.04 EMPALME A BUZON EXISTENTE0.000%1,119.6395%58.935%0.000%1,178.56100%1,178.56AceptarAceptar0Aceptar06PRUEBAS HIDRAULICAS0.001,844.9110,454.500.0012,299.4112,299.41xxxxxxxxxAceptar22.22%22.22%55.56%Aceptar409.9803333333409.98033333331024.9508333333Aceptar06.01 PRUEBA ZANJA TAPADA P/TUB. DESAGUE 160mm/200mm.0.000%1,513.3315%8,575.5385%0.000%10,088.86100%10,088.86AceptarAceptar0Aceptar06.02 PRUEBA ZANJA TAPADA P/TUB. DESAGUE 250mm/355mm.0.000%331.5815%1,878.9785%0.000%2,210.55100%2,210.55AceptarAceptar0Aceptar07CONEXIONES DOMICILIARIAS DESAGUE0.0058,896.40333,746.240.000%392,642.64392,642.64xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxAceptar10.20%10.20%10.20%10.20%10.20%10.20%10.20%10.20%10.20%8.16%Aceptar6009.83632653066009.83632653066009.83632653066009.83632653066009.83632653066009.83632653066009.83632653066009.83632653066009.83632653064807.869061224558896.396Presupuesto extendido07.01 REHABILITACION CONEXIONES DOMICILIARIAS DESAGUE0.0058,896.4015%333,746.2485%0.000%392,642.64392,642.64AceptarAceptar0Aceptar08TRANSPORTE DE MATERIALES A OBRA112,810.6441,022.0551,277.560.000%205,110.25205,110.25xxxxxxxxAceptar62.50%37.50%Aceptar25638.779687515383.267812541022.0475Presupuesto extendido08.01 TRANSPORTE A OBRA DE MATERIALES Y EQUIPOS112,810.6455%41,022.0520%51,277.5625%0.000%205,110.25100%205,110.25AceptarAceptar0AceptarAceptarAceptar0AceptarPLANTA DE TRATAMIENTO67,565.37351,624.36100,807.812.47520,000.00520,000.00AceptarAceptar0Aceptar01TRABAJOS PRELIMINARES8,713.4416,827.5825,777.660.0051,318.6851,318.68xxxxxxxxxAceptar6,912.0017,009.601,889.960.0025,811.5625,811.5622.22%55.56%22.22%Aceptar3,456.008,504.80944.980.0012,905.7812,905.783739.46288888899348.65722222223739.462888888916827.583Presupuesto extendido01.01 LIMPIEZA DE TERRENO MANUAL931.20100%0.000%0.000%0.000%931.20100%931.20AceptarAceptar0Aceptar01.02 MOVIMIENTO DE TIERRASAceptarAceptarAceptar01.02.01 TRAZO Y REPLANTEO PRELIMINAR2,524.80100%0.000%0.000%0.000%2,524.80100%2,524.80AceptarAceptarAceptar01.02.02 CORTE DE MATERIAL SUELTO R=460 m3/da0.000%8,504.8090%944.9810%0.000%9,449.78100%9,449.78AceptarAceptarAceptar01.02.03 CORTE EN ROCA FIJA CON EQUIPO0.000%1,807.6615%10,243.4185%0.000%12,051.07100%12,051.07AceptarAceptarAceptar01.02.04 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 5 km1,340.646%6,193.2929%13,991.5865%0.000%21,525.50100%21,525.50AceptarAceptarAceptar01.02.05 REFINE Y NIVELACION EN AREA DE PLANTA DE TRATAMIENTO DE AGUAS SERVIDAS3,916.80100%0.000%0.000%0.000%3,916.80100%3,916.80AceptarAceptarAceptar01.03 PRUEBAS DE CONTROL DE CALIDADAceptarAceptarAceptar01.03.01 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION)0.000%95.3835%177.1365%0.000%272.51100%272.51AceptarAceptarAceptar01.03.02 PRUEBA COMPACTACION SUELOS (PROCTOR MODIFICADO DENSIDAD DE CAMPO)0.000%104.2735%193.6565%0.000%297.92100%297.92AceptarAceptar0Aceptar01.03.03 PRUEBA DENSIDAD DE CAMPO0.000%122.1935%226.9265%0.000%349.10100%349.10AceptarAceptar0Aceptar02CAMARA DE EXCEDENTES DE LLUVIA (ALIVIADERO)270.005,433.623.280.005,706.905,706.90xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxAceptar540.0075.596.550.00622.14622.1411.36%11.36%11.36%11.36%11.36%11.36%11.36%11.36%9.09%Aceptar270.0037.793.280.00311.07311.07617.4573295455617.4573295455617.4573295455617.4573295455617.4573295455617.4573295455617.4573295455617.4573295455493.96586363645433.6245Presupuesto extendido02.01 TRAZO Y REPLANTEO PRELIMINAR18.3887%1.588%1.055%0.000%21.01100%21.01AceptarAceptar0Aceptar02.02 EXCAVACION C/EQUIPO PESADO ROCA SUELTA194.0692%16.198%0.000%0.000%210.25100%210.25AceptarAceptar0Presupuesto extendido02.03 CORTE EN ROCA FIJA CON EQUIPO0.000%20.0390%2.2310%0.000%22.25100%22.25Presupuesto extendidoPresupuesto extendido0Aceptar02.04 EXCAVACION DE ZANJA TERRENO SEMIROCOSO TUBERIA 8 - 12"57.56100%0.000%0.000%0.000%57.56100%57.56AceptarAceptar0Aceptar02.05 REFINE DE ZANJA INCLUYE CAMA EN TERRENO NORMAL SEMIROCOSO 8-12"0.000%39.42100%0.000%0.000%39.42100%39.42AceptarAceptar0Aceptar02.06 TENDIDO Y COLOCADO TUBERIA PVC SAL 8"0.000%157.02100%0.000%0.000%157.02100%157.02AceptarAceptar0Aceptar02.07 RELLENO COMPACTADO CON MATERIAL PROPIO0.000%95.96100%0.000%0.000%95.96100%95.96AceptarAceptar0Aceptar02.08 SOLADOS CONCRETO f'c=100 kg/cm2 h=2" PARA CIMENTACION0.000%185.61100%0.000%0.000%185.61100%185.61AceptarAceptar0Aceptar02.09 ENCOFRADO Y DESENCOFRADO ESTRUCTURAS0.000%301.66100%0.000%0.000%301.66100%301.66AceptarAceptarAceptar02.10 ACERO fy=4200 kg/cm2 GRADO 600.000%594.05100%0.000%0.000%594.05100%594.05AceptarAceptar0Aceptar02.11 CONCRETO f'c=210 kg/cm2. CON MEZCLADORA0.000%1,998.83100%0.000%0.000%1,998.83100%1,998.83AceptarAceptar0Aceptar02.12 REJA DE FILTRO GRUESO0.000%1,212.51100%0.000%0.000%1,212.51100%1,212.51AceptarAceptar0Aceptar02.13 TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:2 E=1.50.000%423.29100%0.000%0.000%423.29100%423.29AceptarAceptar0Aceptar02.14 TARRAJEO EN EXTERIORES0.000%275.45100%0.000%0.000%275.45100%275.45AceptarAceptar0Aceptar02.15 CURADO DE CONCRETO MANUAL CON AGUA0.000%11.50100%0.000%0.000%11.50100%11.50AceptarAceptar0Aceptar02.16 PINTURA DE MURO EXTERIORES CON LATEX0.000%100.53100%0.000%0.000%100.53100%100.53AceptarAceptar0Aceptar03CAMARA DE REJAS257.725,044.510.002.475,304.705,304.70xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxAceptar515.4445.080.000.00560.52560.528.93%8.93%8.93%8.93%8.93%8.93%8.93%8.93%8.93%8.93%8.93%Aceptar257.7222.540.000.00280.26280.26450.4030446429450.4030446429450.4030446429450.4030446429450.4030446429450.4030446429450.4030446429450.4030446429450.4030446429450.4030446429450.40304464294954.4334910714Presupuesto extendido03.01 TRAZO Y REPLANTEO PRELIMINAR16.07100%0.000%0.000%0.000%16.07100%16.07AceptarAceptar0Aceptar03.02 EXCAVACION C/EQUIPO PESADO ROCA SUELTA182.18100%0.000%0.000%0.000%182.18100%182.18AceptarAceptarAceptar03.03 CORTE EN ROCA FIJA CON EQUIPO0.000%22.54100%0.000%0.000%22.54100%22.54AceptarAceptar0Aceptar03.04 EXCAVACION DE ZANJA TERRENO SEMIROCOSO TUBERIA 8 - 12"59.47100%0.000%0.000%0.000%59.47100%59.47AceptarAceptar0Aceptar03.05 REFINE DE ZANJA INCLUYE CAMA EN TERRENO NORMAL SEMIROCOSO 8-12"0.000%40.73100%0.000%0.000%40.73100%40.73AceptarAceptar0Aceptar03.06 TENDIDO Y COLOCADO TUBERIA PVC SAL 8"0.000%194.70100%0.000%0.000%194.70100%194.70AceptarAceptar0Aceptar03.07 RELLENO COMPACTADO CON MATERIAL PROPIO0.000%62.45100%0.000%0.000%62.45100%62.45AceptarAceptar0Aceptar03.08 SOLADOS CONCRETO f'c=100 kg/cm2 h=2" PARA CIMENTACION0.000%120.80100%0.000%0.000%120.80100%120.80AceptarAceptar0Aceptar03.09 ENCOFRADO Y DESENCOFRADO ESTRUCTURAS0.000%559.45100%0.000%0.000%559.45100%559.45AceptarAceptar0Aceptar03.10 ACERO fy=4200 kg/cm2 GRADO 600.000%736.20100%0.000%0.000%736.20100%736.20AceptarAceptar0Aceptar03.11 CONCRETO f'c=175 kg/cm2. CON MEZCLADORA0.000%1,669.72100%0.000%0.000%1,669.72100%1,669.72AceptarAceptar0Aceptar03.12 REJA DE FILTRO FINO0.000%697.67100%0.000%0.000%697.67100%697.67AceptarAceptar0Aceptar03.13 TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:2 E=1.50.000%696.13100%0.000%0.000%696.13100%696.13AceptarAceptarAceptar03.14 TARRAJEO EN EXTERIORES0.000%160.6599%0.000%1.621%162.27100%162.27AceptarAceptar0Aceptar03.15 CURADO DE CONCRETO MANUAL CON AGUA0.000%7.5699%0.000%0.081%7.64100%7.64AceptarAceptar0Aceptar03.16 PINTURA DE MURO EXTERIORES CON LATEX0.000%75.9199%0.000%0.771%76.68100%76.68AceptarAceptar0Aceptar04DESARENADOR1,285.9224,452.670.000.0025,738.5925,738.59xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxAceptar2,571.842,245.000.000.004,816.844,816.848.62%8.62%8.62%8.62%8.62%8.62%6.90%8.62%8.62%8.62%8.62%6.90%Aceptar1,285.921,122.500.000.002,408.422,408.422107.98879310342107.98879310342107.98879310342107.98879310342107.98879310342107.98879310341686.39103448282107.98879310342107.98879310342107.98879310342107.98879310341686.391034482824452.67Presupuesto extendido04.01 TRAZO Y REPLANTEO PRELIMINAR38.98100%0.000%0.000%0.000%38.98100%38.98AceptarAceptar0Aceptar04.02 EXCAVACION C/EQUIPO PESADO ROCA SUELTA1,246.9479%333.5921%0.000%0.000%1,580.53100%1,580.53AceptarAceptar0Aceptar04.03 CORTE EN ROCA FIJA CON EQUIPO0.000%167.19100%0.000%0.000%167.19100%167.19AceptarAceptar0Aceptar04.04 EXCAVACION DE ZANJA TERRENO SEMIROCOSO TUBERIA 8 - 12"0.000%621.72100%0.000%0.000%621.72100%621.72AceptarAceptar0Aceptar04.05 REFINE DE ZANJA INCLUYE CAMA EN TERRENO NORMAL SEMIROCOSO 8-12"0.000%218.12100%0.000%0.000%218.12100%218.12AceptarAceptarAceptar04.06 TENDIDO Y COLOCADO TUBERIA PVC SAL 8"0.000%194.70100%0.000%0.000%194.70100%194.70AceptarAceptar0Aceptar04.07 TENDIDO Y COLOCADO TUBERIA PVC SAL 12"0.000%2,078.14100%0.000%0.000%2,078.14100%2,078.14AceptarAceptar0Aceptar04.08 RELLENO COMPACTADO CON MATERIAL PROPIO0.000%177.99100%0.000%0.000%177.99100%177.99AceptarAceptar0Aceptar04.09 SOLADOS CONCRETO f'c=100 kg/cm2 h=2" PARA CIMENTACION0.000%344.27100%0.000%0.000%344.27100%344.27AceptarAceptar0Aceptar04.10 ENCOFRADO Y DESENCOFRADO ESTRUCTURAS0.000%2,706.75100%0.000%0.000%2,706.75100%2,706.75AceptarAceptar0Aceptar04.11 ACERO fy=4200 kg/cm2 GRADO 600.000%2,094.11100%0.000%0.000%2,094.11100%2,094.11AceptarAceptar0Aceptar04.12 CONCRETO f'c=210 kg/cm2. CON MEZCLADORA0.000%6,088.85100%0.000%0.000%6,088.85100%6,088.85AceptarAceptar0Aceptar04.13 SUMINISTRO INSTALACION HIDRAULICA PARA VALVULA PURGA 6" (DESARENADOR)0.000%3,375.95100%0.000%0.000%3,375.95100%3,375.95AceptarAceptar0Aceptar04.14 ESCALERA DE GATO FG D=3/4"0.000%1,728.51100%0.000%0.000%1,728.51100%1,728.51AceptarAceptarAceptar04.15 TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:2 E=1.50.000%3,328.36100%0.000%0.000%3,328.36100%3,328.36AceptarAceptar0Aceptar04.16 TARRAJEO EN EXTERIORES0.000%662.71100%0.000%0.000%662.71100%662.71AceptarAceptar0Aceptar04.17 CURADO DE CONCRETO MANUAL CON AGUA0.000%18.53100%0.000%0.000%18.53100%18.53AceptarAceptar0Aceptar04.18 PINTURA DE MURO EXTERIORES CON LATEX0.000%313.18100%0.000%0.000%313.18100%313.18AceptarAceptar0Aceptar05CAMARA DE GRASAS131.516,303.810.000.006,435.326,435.32xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxAceptar263.02550.320.000.00813.34813.347.58%7.58%7.58%7.58%7.58%7.58%7.58%7.58%7.58%7.58%7.58%7.58%7.58%1.52%Aceptar131.51275.160.000.00406.67406.67477.5613636364477.5613636364477.5613636364477.5613636364477.5613636364477.5613636364477.5613636364477.5613636364477.5613636364477.5613636364477.5613636364477.5613636364477.561363636495.51227272736303.81Presupuesto extendido05.01 TRAZO Y REPLANTEO PRELIMINAR4.21100%0.000%0.000%0.000%4.21100%4.21AceptarAceptar0Aceptar05.02 EXCAVACION C/EQUIPO PESADO ROCA SUELTA86.37100%0.000%0.000%0.000%86.37100%86.37AceptarAceptar0Aceptar05.03 CORTE EN ROCA FIJA CON EQUIPO0.000%9.13100%0.000%0.000%9.13100%9.13AceptarAceptarAceptar05.04 EXCAVACION DE ZANJA TERRENO SEMIROCOSO TUBERIA 8 - 12"40.9313%266.0387%0.000%0.000%306.96100%306.96AceptarAceptar0Aceptar05.05 REFINE DE ZANJA INCLUYE CAMA EN TERRENO NORMAL SEMIROCOSO 8-12"0.000%157.68100%0.000%0.000%157.68100%157.68AceptarAceptar0Aceptar05.06 TENDIDO Y COLOCADO TUBERIA PVC SAP 4"0.000%52.24100%0.000%0.000%52.24100%52.24AceptarAceptar0Aceptar05.07 TENDIDO Y COLOCADO TUBERIA PVC SAL 8"0.000%125.62100%0.000%0.000%125.62100%125.62AceptarAceptar0Aceptar05.08 RELLENO COMPACTADO CON MATERIAL PROPIO0.000%19.22100%0.000%0.000%19.22100%19.22AceptarAceptar0Aceptar05.09 SOLADOS CONCRETO f'c=100 kg/cm2 h=2" PARA CIMENTACION0.000%37.17100%0.000%0.000%37.17100%37.17AceptarAceptar0Aceptar05.10 ENCOFRADO Y DESENCOFRADO ESTRUCTURAS0.000%463.47100%0.000%0.000%463.47100%463.47AceptarAceptar0Aceptar05.11 ACERO fy=4200 kg/cm2 GRADO 600.000%263.33100%0.000%0.000%263.33100%263.33AceptarAceptar0Aceptar05.12 CONCRETO f'c=210 kg/cm2. CON MEZCLADORA0.000%1,992.23100%0.000%0.000%1,992.23100%1,992.23AceptarAceptar0Aceptar05.13 SUMINISTRO INSTALACION HIDRAULICA PARA VALVULA PURGA 4" (CAMARA DE GRASAS)0.000%2,380.62100%0.000%0.000%2,380.62100%2,380.62AceptarAceptar0Aceptar05.14 TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:2 E=1.50.000%430.65100%0.000%0.000%430.65100%430.65AceptarAceptar0Aceptar05.15 TARRAJEO EN EXTERIORES0.000%70.91100%0.000%0.000%70.91100%70.91AceptarAceptar0Aceptar05.16 CURADO DE CONCRETO MANUAL CON AGUA0.000%2.00100%0.000%0.000%2.00100%2.00AceptarAceptar0Aceptar05.17 PINTURA DE MURO EXTERIORES CON LATEX0.000%33.51100%0.000%0.000%33.51100%33.51AceptarAceptar0Aceptar06CAMARA DE DECANTACION PRIMARIA2,679.6798,889.860.000.00101,569.53101,569.53xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxAceptar5,359.342,616.740.000.007,976.087,976.087.69%7.69%7.69%7.69%7.69%7.69%7.69%7.69%7.69%7.69%7.69%7.69%7.69%Aceptar2,679.671,308.370.000.003,988.043,988.047606.91230769237606.91230769237606.91230769237606.91230769237606.91230769237606.91230769237606.91230769237606.91230769237606.91230769237606.91230769237606.91230769237606.91230769237606.912307692398889.86Presupuesto extendido06.01 TRAZO Y REPLANTEO PRELIMINAR130.19100%0.000%0.000%0.000%130.19100%130.19AceptarAceptar0Aceptar06.02 EXCAVACION C/EQUIPO PESADO ROCA SUELTA2,549.4878%708.2122%0.000%0.000%3,257.69100%3,257.69AceptarAceptar0Aceptar06.03 CORTE EN ROCA FIJA CON EQUIPO0.000%344.36100%0.000%0.000%344.36100%344.36AceptarAceptar0Aceptar06.04 EXCAVACION DE ZANJA TERRENO SEMIROCOSO TUBERIA 8 - 12"0.000%255.80100%0.000%0.000%255.80100%255.80AceptarAceptar0Aceptar06.05 REFINE DE ZANJA INCLUYE CAMA EN TERRENO NORMAL SEMIROCOSO 8-12"0.000%131.40100%0.000%0.000%131.40100%131.40AceptarAceptar0Aceptar06.06 TENDIDO Y COLOCADO TUBERIA PVC SAL 4"0.000%1,812.59100%0.000%0.000%1,812.59100%1,812.59AceptarAceptar0Aceptar06.07 TENDIDO Y COLOCADO TUBERIA PVC SAL 8"0.000%439.66100%0.000%0.000%439.66100%439.66AceptarAceptar0Aceptar06.08 RELLENO COMPACTADO CON MATERIAL PROPIO0.000%486.16100%0.000%0.000%486.16100%486.16AceptarAceptar0Aceptar06.09 SOLADOS CONCRETO f'c=100 kg/cm2 h=2" PARA CIMENTACION0.000%940.35100%0.000%0.000%940.35100%940.35AceptarAceptar0Aceptar06.10 ENCOFRADO Y DESENCOFRADO ESTRUCTURAS0.000%7,857.66100%0.000%0.000%7,857.66100%7,857.66AceptarAceptar0Aceptar06.11 ACERO fy=4200 kg/cm2 GRADO 600.000%14,732.14100%0.000%0.000%14,732.14100%14,732.14AceptarAceptar0Aceptar06.12 CONCRETO f'c=210 kg/cm2. CON MEZCLADORA0.000%27,442.69100%0.000%0.000%27,442.69100%27,442.69AceptarAceptar0Aceptar06.13 BUZON DE DESAGUE D=1.20 H=2.00-2.50 / TAPA C0.000%7,802.46100%0.000%0.000%7,802.46100%7,802.46AceptarAceptar0Aceptar06.14 TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:2 E=1.50.000%7,881.97100%0.000%0.000%7,881.97100%7,881.97AceptarAceptar0Aceptar06.15 TARRAJEO EN EXTERIORES0.000%3,669.79100%0.000%0.000%3,669.79100%3,669.79AceptarAceptar0Aceptar06.16 SUMINISTRO DE ACCESORIOS PARA TUBERIAS PVC SAP D=8" (DESARENADOR)0.000%875.18100%0.000%0.000%875.18100%875.18AceptarAceptar0Aceptar06.17 ESCALERA DE GATO FG D=3/4"0.000%2,325.64100%0.000%0.000%2,325.64100%2,325.64AceptarAceptarAceptar06.18 SUMINISTRO E INSTALACION DE BOMBA DE SUCCION DE LODOS0.000%16,012.92100%0.000%0.000%16,012.92100%16,012.92AceptarAceptar0Aceptar06.19 SUMINISTRO E INSTALACION DE TUBO VENTILACION DE FIERRO FUNDIDO DE 4"0.000%1,659.18100%0.000%0.000%1,659.18100%1,659.18AceptarAceptarAceptar06.20 TAPA DE CONCRETO ARMADO F'C=175Kg/cm2 DE 0.80 x 0.40 x 0.15m0.000%1,715.58100%0.000%0.000%1,715.58100%1,715.58AceptarAceptar0Aceptar06.21 CURADO DE CONCRETO MANUAL CON AGUA0.000%61.88100%0.000%0.000%61.88100%61.88AceptarAceptar0Aceptar06.22 PINTURA DE MURO EXTERIORES CON LATEX0.000%1,734.24100%0.000%0.000%1,734.24100%1,734.24AceptarAceptar0Aceptar07CANAL DE DERIVACION EXCEDENTES LLUVIA2,256.2936,809.880.000.0039,066.1739,066.17xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxAceptar7.46%7.46%7.46%7.46%7.46%7.46%7.46%7.46%7.46%7.46%7.46%7.46%7.46%2.99%Aceptar2747.00597014922747.00597014922747.00597014922747.00597014922747.00597014922747.00597014922747.00597014922747.00597014922747.00597014922747.00597014922747.00597014922747.00597014922747.00597014921098.802388059736809.88Presupuesto extendido07.01 TRAZO Y REPLANTEO PRELIMINAR288.72100%0.000%0.000%0.000%288.72100%288.72AceptarAceptar0Aceptar07.02 EXCAVACION C/EQUIPO PESADO ROCA SUELTA1,967.5754%1,709.2846%0.000%0.000%3,676.85100%3,676.85AceptarAceptar0Aceptar07.03 CORTE EN ROCA FIJA CON EQUIPO0.000%388.58100%0.000%0.000%388.58100%388.58AceptarAceptar0Aceptar07.04 REFINE DE ZANJA INCLUYE CAMA EN TERRENO NORMAL SEMIROCOSO 8-12"0.000%1,442.51100%0.000%0.000%1,442.51100%1,442.51AceptarAceptar0Aceptar07.05 TENDIDO Y COLOCADO TUBERIA PVC SAL 4"0.000%720.29100%0.000%0.000%720.29100%720.29AceptarAceptar0Aceptar07.06 TENDIDO Y COLOCADO TUBERIA PVC SAL 8"0.000%1,559.73100%0.000%0.000%1,559.73100%1,559.73AceptarAceptar0Aceptar07.07 TENDIDO Y COLOCADO TUBERIA PVC SAL 12"0.000%14,014.59100%0.000%0.000%14,014.59100%14,014.59AceptarAceptarAceptar07.08 TENDIDO Y COLOCADO TUBERIA PERFILADA 450 MM0.000%3,227.25100%0.000%0.000%3,227.25100%3,227.25AceptarAceptarAceptar07.09 TENDIDO Y COLOCADO TUBERIA PERFILADA 550 MM0.000%12,429.19100%0.000%0.000%12,429.19100%12,429.19AceptarAceptarAceptar07.10 RELLENO COMPACTADO CON MATERIAL PROPIO0.000%1,318.46100%0.000%0.000%1,318.46100%1,318.46AceptarAceptarAceptar08LECHO DE SECADO DE LODOS0.0012,407.312,766.690.0015,174.0015,174.00xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxAceptar7.58%7.58%7.58%7.58%7.58%7.58%7.58%7.58%7.58%7.58%7.58%7.58%7.58%1.52%Aceptar939.9473863636939.9473863636939.9473863636939.9473863636939.9473863636939.9473863636939.9473863636939.9473863636939.9473863636939.9473863636939.9473863636939.9473863636939.9473863636187.9894772727Aceptar08.01 TRAZO Y REPLANTEO PRELIMINAR0.000%181.00100%0.000%0.000%181.00100%181.00AceptarAceptarAceptar08.02 EXCAVACION C/EQUIPO PESADO ROCA SUELTA0.000%983.25100%0.000%0.000%983.25100%983.25AceptarAceptarAceptar08.03 CORTE EN ROCA FIJA CON EQUIPO0.000%103.85100%0.000%0.000%103.85100%103.85AceptarAceptarAceptar08.04 EXCAVACION DE ZANJA TERRENO SEMIROCOSO TUBERIA 8 - 12"0.000%184.18100%0.000%0.000%184.18100%184.18AceptarAceptarAceptar08.05 REFINE DE ZANJA INCLUYE CAMA EN TERRENO NORMAL SEMIROCOSO 8-12"0.000%197.10100%0.000%0.000%197.10100%197.10AceptarAceptarAceptar08.06 TENDIDO Y COLOCADO TUBERIA PVC SAL 4"0.000%762.66100%0.000%0.000%762.66100%762.66AceptarAceptarAceptar08.07 RELLENO COMPACTADO CON MATERIAL PROPIO0.000%679.65100%0.000%0.000%679.65100%679.65AceptarAceptarAceptar08.08 SOLADOS CONCRETO f'c=100 kg/cm2 h=2" PARA CIMENTACION0.000%1,070.67100%0.000%0.000%1,070.67100%1,070.67AceptarAceptarAceptar08.09 ENCOFRADO Y DESENCOFRADO ESTRUCTURAS0.000%1,284.81100%0.000%0.000%1,284.81100%1,284.81AceptarAceptarAceptar08.10 CONCRETO CICLOPEO FC=175 kg/cm2 + 30 % PM.0.000%4,847.00100%0.000%0.000%4,847.00100%4,847.00AceptarAceptar0Aceptar08.11 TARRAJEO EN EXTERIORES0.000%1,277.69100%0.000%0.000%1,277.69100%1,277.69AceptarAceptarAceptar08.12 CURADO DE CONCRETO MANUAL CON AGUA0.000%86.03100%0.000%0.000%86.03100%86.03AceptarAceptar0Aceptar08.13 PINTURA DE MURO EXTERIORES CON LATEX0.000%603.80100%0.000%0.000%603.80100%603.80AceptarAceptarAceptar08.14 FILTRO DE PIEDRA 10"0.000%45.835%870.8495%0.000%916.67100%916.67AceptarAceptar0Aceptar08.15 FILTRO DE CANTO RODADO 4"0.000%22.925%435.4195%0.000%458.33100%458.33AceptarAceptarAceptar08.16 FILTRO DE ARENA GRUESA0.000%15.895%301.9095%0.000%317.79100%317.79AceptarAceptar0Aceptar08.17 COMPUERTAS FIERRO CON VOLANTE DE 0.20x0.20 m0.000%60.985%1,158.5495%0.000%1,219.52100%1,219.52AceptarAceptarAceptar09CASETA DE VIGILANCIA0.000.0034,084.760.0034,084.7634,084.76AceptarAceptar0Aceptar09.01 OBRAS PRELIMINARESAceptarAceptarAceptar09.01.01 TRAZO Y REPLANTEO PRELIMINAR0.000%0.000%75.74100%0.000%75.74100%75.74AceptarAceptarAceptar09.02 MOVIMIENTO DE TIERRASAceptarAceptarAceptar09.02.01 EXCAVACION MANUAL0.000%0.000%358.82100%0.000%358.82100%358.82AceptarAceptar0Aceptar09.02.02 RELLENO COMPACTADO A MANO0.000%0.000%129.26100%0.000%129.26100%129.26AceptarAceptar0Aceptar09.03 CONCRETO SIMPLEAceptarAceptar0Aceptar09.03.01 CONCRETO CICLOPEO f'c=140 kg/cm2 + 30 % PM.0.000%0.000%550.16100%0.000%550.16100%550.16AceptarAceptarAceptar09.03.02 CONCRETO f'c=175 kg/cm2. CON MEZCLADORA0.000%0.000%1,186.11100%0.000%1,186.11100%1,186.11AceptarAceptarAceptar09.03.03 ENCOFRADO Y DESENCOFRADO NORMAL0.000%0.000%652.96100%0.000%652.96100%652.96AceptarAceptarAceptar09.03.04 ENCOFRADO Y DESENCOFRADO PARA LOSAS ALIGERADAS0.000%0.000%1,925.42100%0.000%1,925.42100%1,925.42AceptarAceptar0Aceptar09.04 CONCRETO ARMADOAceptarAceptarAceptar09.04.01 CONCRETO f'c=210 kg/cm20.000%0.000%3,780.68100%0.000%3,780.68100%3,780.68AceptarAceptar0Aceptar09.04.02 ENCOFRADO Y DESENCOFRADO NORMAL0.000%0.000%1,499.60100%0.000%1,499.60100%1,499.60AceptarAceptarAceptar09.04.03 ACERO fy=4200 kg/cm2 GRADO 600.000%0.000%6,101.91100%0.000%6,101.91100%6,101.91AceptarAceptar0Aceptar09.04.04 CONCRETO f'c=210 kg/cm2. PARA LOSA ALIGERADA0.000%0.000%5,699.64100%0.000%5,699.64100%5,699.64AceptarAceptarAceptar09.04.05 LADRILLO HUECO DE ARCILLA h=15 cm PARA TECHO ALIGERADO0.000%0.000%1,457.28100%0.000%1,457.28100%1,457.28AceptarAceptar0Aceptar09.05 MURO Y TABIQUES DE ALBAILERIAAceptarAceptarAceptar09.05.01 MURO DE CABEZA LADRILLO KING-KONG CON CEMENTO-ARENA0.000%0.000%832.15100%0.000%832.15100%832.15AceptarAceptar0Aceptar09.06 REVOQUES ENLUCIDOS Y MOLDURASAceptarAceptarAceptar09.06.01 TARRAJEO INTERIOR CON MORTERO 1:5 X1.5 cm 0.000%0.000%191.85100%0.000%191.85100%191.85AceptarAceptarAceptar09.06.02 TARRAJEO EXTERIOR CON MORTERO 1:5 X 1.5 cm 0.000%0.000%314.93100%0.000%314.93100%314.93AceptarAceptar0Aceptar09.06.03 VESTIDURA DE DERRAMES ANCHO 0.10m MEZCL. C.A. 1:5 E=1.5cm0.000%0.000%109.20100%0.000%109.20100%109.20AceptarAceptarAceptar09.07 CIELORRASOSAceptarAceptar0Aceptar09.07.01 CIELO RASO C.A. 1:5 CON CINTAS DE 1.5 cm 0.000.000%550.49100%0.000%550.49100%550.49AceptarAceptarAceptar09.08 PISOSAceptarAceptar0Aceptar09.08.01 FALSO PISO DE 4" DE CONCRETO 1:100.000.000%467.48100%0.000%467.48100%467.48AceptarAceptarAceptar09.08.02 PISOS DE CONCRETO COLOREADO FROTACHADO E=2.5 cm 0.000%0.000%554.50100%0.000%554.50100%554.50AceptarAceptar0Aceptar09.09 CONTRAZOCALOSAceptarAceptarAceptar09.09.01 CONTRAZOCALO DE CEMENTO PULIDO CON MORTERO 1:5 DE E=2 cm H=30 cm0.000%0.000%354.98100%0.000%354.98100%354.98AceptarAceptar0Aceptar09.10 CUBIERTASAceptarAceptarAceptar09.10.01 CUBIERTA DE TEJA ARCILLA 37.15 cm0.000%0.000%1,415.77100%0.000%1,415.77100%1,415.77AceptarAceptarAceptar09.10.02 CANALETAS PARA AGUAS PLUVIALES0.000%0.000%1,087.48100%0.000%1,087.48100%1,087.48AceptarAceptar0Aceptar09.10.03 TUBERIA FIERRO GALVANIZADO 100 mm 0.000%0.000%1,205.88100%0.000%1,205.88100%1,205.88AceptarAceptarAceptar09.11 CARPINTERIA METALICAAceptarAceptar0Aceptar09.11.01 VENTANA DE FIERRO CON PERFIL DE 1" X 1/8" + HOJA BASTIDOR "L" 3/4"0.000%0.000%215.64100%0.000%215.64100%215.64AceptarAceptarAceptar09.12 PUERTAS Y CERRAJERIAAceptarAceptar0Aceptar09.12.01 PUERTAS DE MADERA TABLEROS REBAJADOS DE 4.5 mm0.000%0.000%455.06100%0.000%455.06100%455.06AceptarAceptarAceptar09.12.02 CERRADURA PARA PUERTA PRINCIPAL PESADA0.000%0.000%122.73100%0.000%122.73100%122.73AceptarAceptar0Aceptar09.13 PINTURAAceptarAceptarAceptar09.13.01 PINTURA VINILICA EN CIELO RASO 2 MANOS0.000%0.000%124.59100%0.000%124.59100%124.59AceptarAceptar0Aceptar09.13.02 PINTURA DE MURO EXTERIORES CON LATEX O SIMILAR0.000%0.000%85.85100%0.000%85.85100%85.85AceptarAceptarAceptar09.13.03 PINTURA DE MURO INTERIOR CON LATEX O SIMILAR0.000%0.000%80.33100%0.000%80.33100%80.33AceptarAceptarAceptar09.13.04 PINTADO DE PUERTAS METALICAS LAC (2 MANOS ANTICORROSIVO + 2 MANOS ESMALTE)0.000%0.000%44.73100%0.000%44.73100%44.73AceptarAceptar0Aceptar09.13.05 PINTADO DE VENTANAS METALICAS (2 MANOS ANTICOROSIVO + 2 ESMALTE)0.000%0.000%16.15100%0.000%16.15100%16.15AceptarAceptarAceptar09.14 VIDRIOS, CRISTALES Y SIMILARESAceptarAceptar0Aceptar09.14.01 VIDRIO SEMIDOBLE PROVISION Y COLOCACION EN VENTANAS FIERRO0.000%0.000%42.44100%0.000%42.44100%42.44AceptarAceptarAceptar09.15 INSTALACIONES ELECTRICASAceptarAceptar0Aceptar09.15.01 SALIDAS ELECTRICAS0.000%0.000%613.80100%0.000%613.80100%613.80AceptarAceptarAceptar09.15.02 POZO CONEXION A TIERRA R