caso 3 - tunel debajo de un glaciar

Upload: molly-dawson

Post on 02-Jun-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 Caso 3 - Tunel Debajo de Un Glaciar

    1/3

    Impressive Output

    Svea North is located some 40 km from

    Spitsbergens main town of Longyearbyen,

    and there is a fully-functioning mine

    encampment at the site. There is no road,

    and the only access is by boat in summer,

    snowmobile in winter, or by the daily

    flights into the airstrip.

    Despite its remote location, Svea North

    produced an output of nearly 2.7 million t

    from its single longwall face in 2003.

    Indeed, in October, 2003, the mine pro-

    duced a creditable 460,000 t, taking it to

    the number one position in Europe.Average output per miner of 75 t/shift

    makes it one of the most efficient under-

    ground coal mines in the world.

    The seam averages 3.8 m thick, with

    few geological faults, and good overall

    conditions. It lies under 400 m of rock and

    200 m of ice at its deepest, while at its

    shallowest point, there is just 50 m of rock

    between the coal seam and the glacier. The

    estimated coal reserve is 40 million t, of

    which SNSK expects to mine something

    like 32 million t. It is a very marketableproduct at 32 MJ/kg, with a low ash

    content of 5%, and a low sulphur content

    at 0.6%.Svea North is accessed by simply

    driving into the drift in a conventional

    four-wheel drive vehicle.

    SPITSBERGEN, NORWAY

    FACE DRILLING 43

    Tunnelling Beneath a Glacier

    Record PerformanceSpitsbergen, a Norwegian archipel-ago located in the Arctic ocean some12 degrees south of the North Pole,was first mapped officially by Dutchsailor Willem Barents in the late16th century. Russian geologist, VARusanov, discovered extensive coaldeposits in 1912, which are currentlyexploited under an internationaltreaty. Svea North mine, developedin 1999, is located beneath a glacier,over which owner SNSK has had tohaul its output along an ice roadto the port area. The solution was to

    drive a tunnel beneath the glacierand replace trucks with conveyor. Inthis remote and harsh location, con-tractor Leonhard Nilsen & Sonner(LNS) needed reliable equipmentwith good manufacturer support.They chose an Atlas Copco RocketBoomer L2 C drillrig, and not onlycompleted on time, but also broke afew tunnelling records along theway!

    Svea North is accessed by sea during

    the summer.

    Charging the face from the rig basket.

  • 8/11/2019 Caso 3 - Tunel Debajo de Un Glaciar

    2/3

    Since production commenced, a com-

    bination of on-off highway trucks and

    ADTs has hauled the coal the 6 km or so

    from the stockyard at the pit entrance to

    the port area, making up to 50,000journeys/year.

    As the fjord freezes during winter, the

    coal is kept in a 1.6 million t-capacity

    stockpile beside the port until the ships can

    again make their way to the dock.

    Keeping an ice road open in such a

    climate is not easy, with around NKr 5 mil-

    lion/year spent on grading alone, to main-

    tain the required capacity of 16,000 t/day.

    The wear and tear on trucks and loading

    equipment added greatly to this bill,

    making it imperative that an alternative

    solution be found.SNSK decided to replace the ice road

    with a tunnel under the glacier. The 2.6%

    dipping tunnel alignment lies beneath the

    production seam, and it is designed to house

    both a conveyor system, and a channel to

    drain ground water percolating through the

    mine from a lake beneath the glacier.

    The mine has suffered problems with

    excessive water, despite its powerful

    installed pump station and lengthy

    pipelines. Water ingress is greater in

    summer because of the thaw, evidenced bythe longwall being put out of action by

    flooding for much of July and August,

    2002.

    Tunnel Drivage

    LNS was awarded the contract for the

    5.6 km-long x 38 sq m tunnel, and started

    its development in November, 2002, using

    a new Atlas Copco Rocket Boomer L2 C

    drillrig. Planned advance of 100 m/week

    was easily exceeded, with a world

    drill/blast record of 150 m being achieved

    in the best week.

    This rate of advance is normally

    achieved using TBMs, and is extremely

    significant for a drill and blast operation

    because of the dramatic difference in capi-

    tal employed.

    Rock conditions are relatively soft,

    competent and not generally abrasive,although there is some quartzite intrusion.

    LNS used 48 mm bits with three holes in

    front and ballistic buttons, which lasted

    from 300-500 m before regrinding. For

    each round, the blastholes were drilled to

    depths of 5 m and took around 1.5-3 min-

    utes apiece, with 75-76 holes required for

    a full pattern. Productivity was kept at a

    high average rate, with LNS achieving 3-4

    rounds/day, and sometimes five. In the

    worst conditions, this dropped to two

    rounds/day.For charging the upper holes and the

    cut, the Rocket Boomer was equipped with

    a Dyno hose charger mounted in the

    basket. With this device it was possible to

    regulate the volume of explosives injected

    into each hole. A second hose was used

    manually for charging the holes in the

    lower part of the face, without the option

    to regulate the volume of explosives

    injected. A standard emulsion explosive

    was used, mixed in the hole and detonated

    using Nonel. Emulsion explosives are

    more expensive than ANFO, but theirmuch-reduced blasting fumes allow opera-

    tors to return to the face quicker after each

    blast. Another advantage is that emulsion

    components can be transported under the

    flammable material rules, and are not

    classified as explosive until they are in the

    hole.

    The mucking operation took around

    1.5-2 h for around 380 t of blasted rock. A

    conventional loader was used, with a fleet

    of six trucks, with a grader keeping the

    roadway clear and smooth. A face crew ofsix was sufficient for each of the two

    SPITSBERGEN, NORWAY

    44 FACE DRILLING

    Atlas Copco Rocket Boomer L2 C at the

    face.

  • 8/11/2019 Caso 3 - Tunel Debajo de Un Glaciar

    3/3

    shifts/day, while the total LNS crew on this

    project was 52.

    The tunnel was started in permafrost,

    with a 400-500 m transition zone at each

    end to reach solid rock. In these zones,

    melting ice caused problems with the shot-

    crete application. LNS employed an accel-

    erant in the shotcrete mix, and reinforced it

    with steel fibres. Two rockbolts were gen-

    erally required for each metre advance, but

    problems with rock pressures sometimes

    necessitated more extensive bolting, and

    use of a hydraulic scaler. Polyester roof-

    bolts were replaced by 2.4 m and 3 m

    Swellex Manganese bolts in some of the

    more difficult areas.

    The drill and blast portion of the tunnel

    project is now complete. Fitting out, and

    installation of the ventilation and conveyor

    systems, should be finished by the end ofthe first quarter of 2004.

    Equipment Modifications

    The Rocket Boomer L2 C drillrig was

    fitted with Atlas Copcos ABC Regular

    control package, which indicates the hole

    positions, but does not include full-function

    automatic boom movement.

    The contractor has had experience using

    a computerized Rocket Boomer XL3 C on

    the Norwegian mainland, but it was still amajor decision to send an RCS drillrig to a

    remote location like Spitsbergen. During

    commissioning, Atlas Copco provided

    three or four days of basic training at site

    to the new operators. The instructor then

    remained in support for another three

    weeks, and returned some months later for

    a week of follow-up training. The contrac-

    tor has taken care of maintenance and

    operation of the rig during the entire pro-

    ject using his own people, without the need

    of outside assistance.

    In the transition zone between the per-mafrost and the rock, it was found that the

    conventional anti-jamming system fitted to

    the drillrig did not give sufficient warning

    of jamming, resulting in some rod damage.

    Atlas Copco suggested an alternative pro-

    gram, which suited the conditions better by

    simultaneously monitoring rotation, feed

    rate and water flow. This resolved the

    problem, and there were no more instances

    of rod damage caused by jamming.

    By agreement with LNS, Atlas Copco

    evolved a package of spares suited to theremoteness of the operation. However,

    reliability was good, and only the usual

    service parts such as filters and hoses were

    required.

    The SNSK mine also has an Atlas

    Copco Swell bolter, originally supplied in

    1986. This rig was rebuilt in 2001 and

    equipped with the new HBU bolting unit

    with a COP 1028 hydraulic rock drill. This

    bolting unit is used in parts of the mine

    with hard sandstone layers, where rotary

    drilling cannot be used.

    Svea Norths future looks good. The

    mine has a projected life until 2013, andthere are another two deposits of 3.5

    and 2.7 million t nearby that SNSK may

    wish to develop. The company is also car-

    rying out exploration work elsewhere on

    Spitzbergen.

    Acknowledgements

    Atlas Copco is grateful to SNSK and LNS

    for permission to publish this article,

    which is derived from a site report written

    by Mike Woof, editor of World MiningEquipment magazine.

    SPITSBERGEN, NORWAY

    FACE DRILLING 45

    Rockbolts and shotcrete provide the

    main support.