cargador fronta´l.xlsx
TRANSCRIPT
INICIO FIN DESCRIPCION
0.00 0.10 zarandeo0.10 0.30 sacar material 00.30 0.36 transporta material
0.36 1.24 acomodo de material1.24 1.55 sacar material1.55 2.07 zarandeo 2.07 2.37 moviliza material sacado2.37 2.45 zarandeo2.45 2.57 del deposito zarandeo2.57 3.50 acomodo de material3.50 4.30 saca material4.30 4.43 zarandeo4.43 5.24 movilza y saca material5.24 5.36 zarandeo5.36 6.19 movilza y saca material6.19 6.30 zarandeo6.30 7.15 moviliza material sacado7.15 7.24 zarandeo7.24 8.16 retira material de la malla8.16 8.33 CMZ8.33 8.44 zarandeo8.44 9.17 saca material9.17 9.29 zarandeo9.29 10.10 moviliza sacado material
10.10 10.22 zarandeo10.22 11.00 saca material11.00 11.12 zarandeo11.12 11.52 moviliza sacado material 11.52 12.40 zarandeo12.40 12.30 movimiento maquinaria12.30 13.44 descanzo del operador13.44 14.09 saca material14.09 14.14 cargio de volquete14.14 14.39 saca material14.39 14.50 moviliza y carga volquete14.50 14.57 cargio de volquete14.57 15.15 saca material seleccionado15.15 15.27 cargio de volquete15.27 15.35 cargio de volquete15.35 15.55 transporte A15.55 16.00 cargio de material bruto16.00 16.14 transporte A16.14 16.24 zarandeo16.24 16.30 transporte A
16.30 16.34 reacomodo zarandeo16.34 16.46 rrelleno de via16.46 16.59 CPV16.59 17.10 TC17.10 17.31 RZ17.31 17.48 TA17.48 17.54 CMBA17.54 18.07 TA18.07 18.17 Z18.17 18.38 TB18.38 18.41 CMBB18.41 18.59 TB18.59 19.07 Z19.07 19.25 TB19.25 19.28 CMBB19.28 19.46 TB19.46 19.56 Z19.56 20.16 TB20.16 20.20 CMBB20.20 20.37 TB20.37 20.46 Z20.46 21.14 TAC21.14 21.18 AC121.18 21.57 TM21.57 22.25 M22.25 23.06 CAC123.06 23.09 CAC223.09 23.16 TAC123.16 23.30 AC123.30 23.40 CAC123.40 23.48 TAC123.48 23.52 AC223.52 24.16 TB24.16 24.19 CMBB24.19 24.37 TB24.37 24.47 Z24.47 25.10 CMBB25.10 25.25 TA25.25 25.36 Z25.36 25.50 TA25.50 25.54 CMBB25.54 26.14 TA26.14 26.24 Z26.24 26.46 TM26.46 27.12 TAC127.12 27.26 AC127.26 28.00 TM28.00 28.16 CAC1
28.16 28.28 TAC128.28 28.35 AC228.35 28.50 TAC128.50 29.05 CMAC29.05 29.18 TAC129.18 29.21 AC229.21 29.35 TAC129.35 29.40 CAC129.40 29.55 AC229.55 29.59 AC229.59 30.33 TB30.33 30.36 CMBB30.36 31.15 TB31.15 32.01 Z32.01 32.33 TB32.33 32.38 CMBB32.38 33.00 TB33.00 33.11 Z33.11 33.31 TB33.31 33.34 CMBB33.34 33.58 TB33.58 34.10 Z34.10 34.28 TB34.28 34.31 CMBB34.31 34.54 TB34.54 35.11 Z35.11 35.23 TC35.23 35.34 RZ35.34 36.00 TC36.00 36.38 TM36.38 36.48 CM36.48 37.05 TC37.05 37.10 RZ37.10 37.25 TC37.25 37.35 CM(TC)37.35 37.43 TC37.43 37.52 RZ37.52 38.05 CM(TC)38.05 38.11 CM(TC)38.11 38.29 TC38.29 38.33 RZ38.33 38.45 TC38.45 38.51 CM(TC)38.51 39.10 TC39.10 39.16 RZ39.16 39.28 TC39.28 39.34 CM(TC)39.34 39.50 TC
39.500.000.00
1
2
EXCAVADORA CATERPILLAR OPERADOR 3AÑOS EXP.
FACTOR DE OPERACIÓN 0.9 %
9 8.0000 15 1080
FACTOR DE EFICIENCIA %PORCENTAJE DE EFICIENCIA
120 0.67 66.67150 0.53 53.33
METROS CUBICOS DESPOJADOS POR DIA
numero de volquete
numero de viajes por volquetes
capacidad del volquete
m3
volumen de material por
dia (m3)
EN UN DIA, LA EXCAVADORA EXTRAE APROXIMADAMENTE 1080 metros cubicosd e
material
oper.5 años oper.3 añosCARGUIO 1 120 150CARGUIO 2 114 144CARGUIO 3 132 144CARGUIO 4 138 150CARGUIO 5 114 156CARGUIO 6 120 138CARGUIO 7 126 144CARGUIO 8 138 144CARGUIO 9 138 144