Precios de recursosCALCULO DE PESOS PARA TRANSPORTE DE MATERIALES

PROYECTO : "REHABILTACION Y MEJORAMIENTO CAMINO VECINAL SAN ISIDRO-MARGARITA"TRAMO: SAN ISIDRO - MARGARITAUBICACIN : HUANUCO - LEONCIO PRADO- HERMILIO VALDIZAN

ItemDescripcinUnd.Cantidad Peso (Kg)Parcial (Kg)1.00ALAMBRE NEGRO N 16kg33.27001.0033.272.00ALAMBRE NEGRO N 8kg146.90781.00146.913.00CLAVOS PARA MADERA CON CABEZA DE 2"kg0.20701.000.214.00TUBERIA METALICA D=3"u4.00006.0024.005.00CLAVOS PARA CALAMINAkg12.00001.0012.006.00CLAVOS PARA MADERAkg172.04001.00172.047.00PERNOS 3/8" X 4 "pza9.00000.050.458.00PERNOS 5/8" X 14 "pza8.00000.050.4010.00LAMINA REFLECTIVA ALTA INTENSIDADp23.95000.501.9811.00LAMINA REFELCTIVA GRADO INGEN.p215.81000.507.9112.00CEMENTO PORTLAND TIPO I (42.5 kg) bls2412.810842.50102,544.4613.00MECHA O GUIA NARANJAm19,935.96500.101,993.6014.00ANFOkg3,450.18051.003,450.1815.00FULMINANTEu17,835.80500.101,783.5816.00DINAMITA AL 65%kg1,275.06051.001,275.0617.00YESO DE 28 Kgbls5.014028.00140.3919.00SOLDADURAkg0.10001.000.1020.00BARRENO 5' X 1/8"u0.21263.000.6421.00BARRENO DE 7/8" X 3,5 Y 8 PIES (PROMEDIO)u47.18585.00235.9322.00FIBRA DE VIDRIO DE 4 mm ACABADOm21.47001.502.2123.00WINCHA METALICA DE 5.00 MTS.u0.17310.250.0424.00WINCHA DE FIBRA DE VIDRIO DE 50 MTS.u0.17310.800.1425.00COLA SINTETICAgal0.40004.001.6026.00MADERA CAPIRONA p2105.00001.50157.5027.00MADERA CORRIENTE CEPILLADAp22,500.00001.503,750.0028.00ESTACA DE MADERA TORNILLO p20.78661.501.1829.00TRIPLAY DE 4' X 8' X 4 mmpl2.00003.006.0030.00TRIPLAY DE 19 MMpl70.00006.50455.0031.00MADERA TORNILLO INC. CORTE P/ENCOFRADOp21,900.00001.502,850.0032.00ANGULO DE 1" X 1" X 3/16" m6.80001.208.1633.00PLATINA DE ACERO 4.5" x 3" x 3/8" SEGUN DISEOpza8.00002.5020.0034.00PINTURA ESMALTE gal0.64204.002.5735.00PLANCHA DE ACERO 1/4" X 8" X 8"u2.00004.208.4036.00CALAMINA # 30 DE 1.83 m X 0.83 m X 3 mmpza54.40002.50136.0030773.5937.00BANNER 13 ONZ 3.60X2.40 M RESOLUCION 600 DPIu1.00004.504.50TOTAL PESO DE MATERIALES A TRANSPORTAR150,000.000.00

Analisis de FleteDistancia desde TINGO MARIA a la Obra :d1=32.0KmVelocidad de Transporte : v1=20.0Km/hTiempo necesario para el transporte (Ida y Vuelta ) T=3.20Horas

Costo de Camion 8 Tn =98.30Soles/HMA) Calculo de fleteA.1) FleteCosto / Tn =40.00S/. Por Tn.Flete =6000Nuevos Soles

TOTAL FLETE DE MATERIALES6000NUEVOS SOLES