CRON VAL OPCCRONOGRAMA VALORIZADO DE AVANCE DE OBRA

OBRA:MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL EN LA CALLE EDUCADORES TRAMO AV. COLLPA - AV. LOS POETAS -CONTRATISTA:CONSORCIO VIAL EDUCADORESFECHA DE ENTREGA DE TERRENO: 02/07/2013FECHA DE ELABORACION: 22/11/2013ENTIDAD:EN EL DISTRITO CRNL. GREGORIO ALBARRACIN LANCHIPA -TACNA - TACNARESIDENTE DE OBRA:ING. VICTOR RAUL REYES ANAYAFECHA DE INICIO DE PLAZO CONTRACTUAL: 03/07/2013ELABORADO POR: VRAUBICACIN:GREGORIO ALBARRACIN LANCHIPA -TACNA-TACNA INSPECTOR DE OBRA:ING. FELIX FRISANCHO CAMEROFECHA PREVISTA DE TERMINO DE PLAZO CONTRACTUAL: 30/10/2013FECHA REPROGRAMADA DE TERMINO DE PLAZO CONTRACTUAL: 29/12/2013PLAZO EJECUCION:180 d.c.JULIOAGOSTOSEPTIEMBREOCTUBRENOVIEMBREDICIEMBREITEMDESCRIPCIONUNDPRESUPUESTOLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMJVSDLMMETRADOPRECIOPARCIAL12345678910111213141516171819202122232425272728293031123456789101112131415161718192021222324252627282930311234567891011121314151617181920212223242526272829301234567891011121314151617181920212223242526272829303112345678910111213141516171819202122232425262728293012345678910111213141516171819202122232425262728293031

01.01.00OBRAS PROVISIONALESGLB--6,773.165,648.16375.00375.0053.13159.386613.785

01.02.00SEGURIDAD Y SALUDGLB--16,862.777,866.875,386.821,804.54451.141353.4115509.3575

01.03.00TRABAJOS PRELIMINARESGLB--95,190.6884,427.923,833.201,217.01304.25912.7694277.9225

01.04.00VEREDAS DE CONCRETO DE PIEDRA LAVADA COLOREADOGLB--242,370.4001.04.01MOVIMIENTO DE TIERRAS94,957.2756,974.3632,931.17

01.04.02CONCRETO SIMPLE147,413.135,224.80135,592.87

01.05.00JARDINERASGLB13,688.646,844.321,711.085133.248,555.40

01.06.00OTROSGLB8,363.444,784.902470.90

01.07.00BERMAS DE ADOQUINGLB--333,749.6701.07.01MOVIMIENTO DE TIERRAS35,334.8517,667.424,416.853312.64259937.92750

01.07.02ADOQUINADO EN BERMAS298,414.8251,016.23105,844.9423,510.1829510.8788532.61249117.13

01.08.00PAVIMENTACIONGLB--47,396.1023,698.055,924.524443.38513330.155

01.09.00PAVIMENTO EN VIAGLB--250,987.511,870.38249117.13001.10.00SEALIZACIONGLB21,831.5221831.5221831.5201.11.00PORTICO DE INGRESO DE BIENVENIDAGLB24,452.8101.11.01MOVIMIENTO DE TIERRAS966.70738.70228.0001.11.02OBRAS DE CONCRETO SIMPLE282.79282.7901.11.03OBRAS DE CONCRETO ARMADO23,203.3214,559.63926.752780.24

01.12.00CARPINTERIA METALICAGLB5,964.971840.005508.33

01.13.00VARIOSGLB16,649.5316,649.53

01.14.00INSTALACIONES ELECTRICASGLB9,133.959,133.95

01.15.00MITIGACION DE IMPACTO AMBIENTALGLB4,500.001125.001125.001125.00508.06616.941125.00

01.16.00EDUCACION VIALGLB4,000.001000.001000.001000.00451.61548.391000.00

COSTO DIRECTO1,101,915.15162,267.11292,991.80130,650.5724,469.85656,568.8046,189.47426,505.18GASTOS GENERALES (10.20%)112,395.3516,551.2529,885.1613,326.362,495.924,711.3343,503.53UTILIDAD (8.50%)93,662.7913,792.7024,904.3011,105.302,079.943,926.1036,252.94SUB TOTAL1,307,973.29192,611.06347,781.26155,082.2329,045.7154,826.90506,261.65I.G.V(18%)235,435.1934,669.9962,600.6327,914.805,228.239,868.8491,127.10PRESUPUESTO DE OBRA1,543,408.48227,281.05410,381.89182,997.0334,273.9464,695.74597,388.75

% AVANCE MENSUAL14.73%26.59%11.86%2.22%4.19%38.71%% AVANCE ACUMULADO14.73%41.32%53.17%55.39%59.58%98.29%